| Description: | ROOM M0778 - INSTALL CONDENSATE FROM FLASH TANK |
|---|---|
| Building: | GILMAN HALL |
| Requester: | DOBSON, BART |
| Work Order |
Description | Sold To | Billed Amount |
Pending Amount |
Total Amount |
Labor Hours |
|---|---|---|---|---|---|---|
| W962085 | NIGHT CALL 02/11/12 - SHUTDOWN FIRE PANEL | 112-11-20 (BUILDING REPAIRS) |
$429.37 | $429.37 | 6 | |
| W962086 | ASSIST WITH GILMAN CONDENSATE | 112-11-20 (BUILDING REPAIRS) |
$236.74 | $236.74 | 3 | |
| W962008 | PURCHASE MATERIAL | 112-11-20 (BUILDING REPAIRS) |
$629.13 | $629.13 | 0 | |
| W962010 | MECHANICAL CONTRACTOR - WALDINGER | 112-11-20 (BUILDING REPAIRS) |
$3,958.79 | $3,958.79 | 0 | |
| Totals: | $5,254.03 | $0.00 | $5,254.03 | 9 | ||
Questions? Contact FP&M Accounting at 294-4688