| Requestor | BAUMGARN, KATHLEEN M |
|---|---|
| Location | 0045 PHYSICS |
| Description | ROOM 45 - CLASSROOM REMODEL |
| Details | No estimate requested, project will be approved ITEMS: CEILING, SIGNAGE, ELECTRICAL, LIGHTING, PHONE/DATA, AUDIO/VISUAL, PAINTING, WINDOW COVERINGS, FURNITURE Remodeling this classroom to improve lighting and add media technology, as well as gas, compressed air and DC power. This work needs to be completed next Summer 2012. Thanks! Katie Desired completion date: AUGUST 2012 Known time constraints: Complete by start of fall 2012 classes, August 15, 2012 Desired project cost: $25,000-50,000 |
| Status | PROJECT COMPLETED AND CLOSED OUT Billing Info |
| Contact | |
| Close Date | 11/30/2012 2:00:09 PM |
| Const Start | |