Current Projects in Black Engineering Bldg

BLACK-0087-336418-Flooring Replacement
Construction
Room: 0087
Request date: 1/19/2024
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start: 3/12/2024
Construction end: 9/10/2024
Description:
EHS tested mastic under tiles and found asbestos. During summer we would like the tiles and mastic removed. Clean sealed cement floor is what we would like to end up with.
BLACK-1059-348255-Sealing Concrete Floor
Project Closeout
Room: 1059
Request date: 3/6/2024
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start: 3/29/2024
Construction end: 4/4/2024
Description:
once I have that research lab emptied please remove the paint from the floor and seal the concrete
BLACK-1091-341854-Tile Removal & Concrete Finish
Project Closeout
Room: 1091
Request date: 2/6/2024
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start:
Construction end:
Description:
Remove floor tiles, polish and seal concrete floor in the empty half of this room. I showed it to Eric Ohrt so he is familiar. I was hoping we could schedule this last week of February if that works.
BLACK-1104-343580-Floor Abatement
Construction
Room: 1104
Request date: 2/26/2024
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start: 4/10/2024
Construction end: 10/9/2024
Description:
remove floor tiles and asbestos in mastik (tested and confirmed by EH&S). polish and seal concrete floor.
BLACK-2022-322850-Office Furniture and Design
Construction
Room: 2022
Request date: 11/3/2023
Requested by: Sougata Roy
Contact: Eric Ohrt
Construction start: 2/2/2024
Construction end: 8/2/2024
Description:
I would like to setup my office space with proper furniture and designs. It will be helpful if someone stop by my office to discuss and share their ideas for that. Thanks!
BLACK-2043 & 2045-215107-Flooring and Furniture
Project Closeout
Room: 2043
Request date: 8/9/2022
Requested by: Sandy Sayer
Contact: Melissa Warg
Construction start: 10/27/2023
Construction end: 3/12/2024
Description:
New Flooring in Room 2043 and Furniture in Room 2045
BLACK-2045A-309140-Window Coverings
Project Closeout
Room: 2045A
Request date: 9/6/2023
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start: 12/22/2023
Construction end: 4/10/2024
Description:
Ann Hawkins is in this office and she needs a different window blind that what is currently installed. The glare off of the white roof is a problem. Could we please have Garrett Young from Heartland Window Treatments come over and talk to Ann to find a window treatment solution?
BLACK-General-336419-Safety Showers
Bidding
Room: General
Request date: 1/19/2024
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start: 4/30/2024
Construction end: 10/29/2024
Description:
EHS has indicated multiple research labs on the first floor of Black require safety showers. 1116, 1095 and 1103
BLACK-GENERAL-337207-Third Floor Carpet Replacement
Construction Documents
Room: General
Request date: 1/25/2024
Requested by: Sandy Sayer
Contact: Carrie Choudhury
Construction start: 5/24/2024
Construction end: 11/22/2024
Description:
New carpet in all the offices and conference rooms on the third floor like what we have been installing on the second floor. When all the IMSE folks move out when their new building is done replace all the carpet on the third floor with the new carpet we are having installed on second.
BLACK-General-341774-2nd Floor Carpet Replacement
Construction Documents
Room: General
Request date: 2/6/2024
Requested by: Sandy Sayer
Contact: Carrie Choudhury
Construction start: 5/24/2024
Construction end: 11/22/2024
Description:
New carpet for the rest of the 2nd floor offices in 3 phases over summer Phase 1: 2008, 2011, 2020, 2030, 2038, 2035, 2078, 2098 Phase 2: 2010, 2016, 2026, 2034, 2068, 2072, 2092, 2102 Phase 3: 2012, 2018, 2028, 2036, 2070, 2074, 2096
BLACK-General-357837-New carpet squares installed over raised floors in computer lab 1012 and a cla
Room: General
Request date: 4/29/2024
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start:
Construction end:
Description:
New carpet squares installed over raised floors in computer lab 1012 and a classroom 95E in Black. We prefer square tiles that can be carpet taped at the corners so we can still access the wiring underneath. Like the carpet in 1020 Black. There is a lot of foo traffic and rolling chairs so something that wears well.
BLACK-Room 1115-Fume Hood
Project Closeout
Room: 1115
Request date: 7/16/2021
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start:
Construction end:
Description:
Install new fume hood with acid and flammables base cabinet
BLACK-Room 2013-Remodel
Construction
Room: 2013
Request date: 10/15/2021
Requested by: Sandy Sayer
Contact: Eric Ohrt
Construction start: 3/13/2024
Construction end: 9/11/2024
Description:
Constructing a wall in 2019A making that large office into two offices and installing a door to the created office space. 8/17/2023 - Change is Room to 2013
BLACK-Room 2081-Fume Hood
Schematic Design
Room: 2081
Request date: 10/14/2021
Requested by: Sandy Sayer
Contact: Mike McCoy
Construction start: 5/12/2024
Construction end: 5/12/2024
Description:
Install fume hood with flammables/acid base cabinet
BLACK-Room 2103-Fume Hood
Cost Range Approval
Room: 2103
Request date: 7/16/2021
Requested by: Sandy Sayer
Contact: Melissa Warg
Construction start: 5/12/2024
Construction end: 5/12/2024
Description:
Install new fume hood with acid and flammables base cabinet