Current Projects in Kildee Hall

KILDEE- General-208569-Condensate Evaluation and Reconfiguration
Cost Range Approval
Room: General
Request date: 7/19/2022
Requested by: John Netwal
Contact: Melissa Warg
Construction start: 7/10/2024
Construction end: 1/8/2025
Description:
Kildee condensate system needs to be evlauated and redesigned. There are system failures caused by improper designinstallation.
KILDEE- GENERAL-268364-1st Floor Wayfinding Signage
Project Closeout
Room: General
Request date: 3/29/2023
Requested by: Cory Walker
Contact: Josef Biechler
Construction start:
Construction end:
Description:
Add wayfinding signage on first floor Kildee Hall. Coordinate with Printing Services (Elaine Broome Cheaney) for 8 wall signs, 11 blade signs and 5 appliques at this time. Intention is to have a red background with white lettering. A word document can be provided that helps illustrate the placement and verbiage for each sign. I'm not certain of the sub type selections so made the best choice. if not appropriate, please advise
KILDEE-0005-350757-Furniture and Access
Cost Range Approval
Room: 0005
Request date: 3/27/2024
Requested by: Cory Walker
Contact: Melissa Warg
Construction start: 7/10/2024
Construction end: 1/8/2025
Description:
Convert Conference Room space into Lactation room. It currently has a sink but separate work order in place to update counter / fixtures. We are looking to update the door access by changing the lock, add some chairs (need), Desk (have), possible refrigerator and other accommodations for the space as appropriate.
KILDEE-1204-323008-Tables
Construction Documents
Room: 1204
Request date: 11/3/2023
Requested by: Cory Walker
Contact: Rebecca Cantrall
Construction start: 5/26/2024
Construction end: 11/24/2024
Description:
Look at options for different tables. Current tables are 4' x 10' - Qty. 15. Looking at possible narrower tables to increase seating capacity. Not determined at this time if seating would be changed or not.
KILDEE-1204-350842-Furniture
Bidding
Room: 1204
Request date: 3/28/2024
Requested by: Cory Walker
Contact: Josef Biechler
Construction start: 5/1/2024
Construction end: 10/30/2024
Description:
Seeking to add additional seating to Ensminger room with similar matching task chairs (qty. 23) as well as lobby seating / table and 8 side chairs in 1221 office suite. We are currently working with Rebecca Cantrall on styles, fabrics, etc. to coincide with ID# 323008
KILDEE-General-336651-PRV Study
Construction Documents
Room: General
Request date: 1/22/2024
Requested by: John Netwal
Contact: Brian Grove
Construction start: 5/26/2024
Construction end: 11/24/2024
Description:
We would like to have the Engineering Team review the recently installed PRV for code compliance and safety in the mechanical room and develop a detailed plan to correct any deficiencies found that could be either shared with a contractors or in-house staff. An engineering probable cost estimated would be greatly appreciated.
KILDEE-M0026-293580-Concrete Floor Drain Repair
Construction Documents
Room: M0026
Request date: 7/7/2023
Requested by: Brady Streit
Contact: Brian Grove
Construction start: 5/26/2024
Construction end: 11/24/2024
Description:
High Priority - This came from FPM Building Maintenance Kildee Hall - Mechanical Room 0026 - Center floor drain is plugged and needs cleaned out with drain cleaning machine/snake. Drain issue that needs to be turned into a project. We are unable to clear this drain and when we plunge it water comes up around electrical conduits in the vicinity. This leads us to believe that we have a deteriorated pipe under the concrete. This will require a plumbing contractor that has the capability to demo concrete, make the repairs, and replace the concrete. Ben Adams has extensive knowledge about this problem and claims that it has been turned in as a project before.