Current Projects in Patterson Hall

PATTRSN- GENERAL-251199-Replace Pavers
Project Closeout
Room: General
Request date: 1/4/2023
Requested by: Brian Adams
Contact: Josef Biechler
Construction start: 5/17/2023
Construction end: 9/14/2023
Description:
Vet Med Plaza pavers Replace about 13 pavers this spring. If we approve a contractor now, they could pour the pavers ahead of time and be ready to install in March-April prior to graduation. I would also see if we would allow them to put a lifting eye lug in the unit for easier install removal and grout or plug it in when completed.
PATTRSN- General-273411-Locate Shut Off Valves
Construction Documents
Room: General
Request date: 4/17/2023
Requested by: John Netwal
Contact: Donna Imhoff
Construction start: 5/21/2024
Construction end: 11/19/2024
Description:
Please put together a project scope and budget to locate shut off valves on cold and hot domestic lines so that the building can be isolated in sections/areas. Eventually will need detailed drawings indicating valve locations and sizes as well as a recommendation for order of install.
PATTRSN- General-289964-Monument Sign
Construction Documents
Room: General
Request date: 6/27/2023
Requested by: Brian Adams
Contact: Joseph Stoberl
Construction start: 5/21/2024
Construction end: 11/19/2024
Description:
Sign shop to update the Monument sign for Veterinary Medicine building to Update the building being renamed. Chris Strawhacker has details.
PATTRSN-1001-239740-Lounge Furniture
Project Closeout
Room: 1001
Request date: 11/17/2022
Requested by: Brian Adams
Contact: Josef Biechler
Construction start: 11/14/2023
Construction end: 4/15/2024
Description:
Provide new lounge furniture and backpack shelves in VM 1001 area just outside of 1010 Anatomy lab. The space has to accommodate the existing AED, printer and access to both elevator and stairs.
PATTRSN-1074-311908-Casework Replacement
Construction Documents
Room: 1074
Request date: 9/28/2023
Requested by: William Robertson
Contact: Steven Daniels
Construction start: 7/2/2024
Construction end: 12/31/2024
Description:
Please estimate the cost of replacing the casework in this laboratory.
PATTRSN-1127-224249-Electrical
Construction Documents
Room: 1127
Request date: 9/15/2022
Requested by: Brian Adams
Contact: Troy Bowers
Construction start: 5/21/2024
Construction end: 11/19/2024
Description:
Remove the existing non grounded power system and install a traditional non surgical electrical panels to feed the labs. Troy Bowers is aware of the situation.
PATTRSN-1140-334995-Remodel
Construction Documents
Room: 1140
Request date: 1/5/2024
Requested by: Brian Adams
Contact: Steven Daniels
Construction start: 6/7/2024
Construction end: 12/6/2024
Description:
Patterson hall rooms 1140, 1142, 1146 and 1150 are rooms under consideration for remodeling and updating for a new hire for a new lab. Only (3) rooms are anticipated to be used for the new person and these are the choices we are considering. Replace flooring, cabinetry, lights and paint including sinks and eyewashes'. 1/10/2024 Adding Scope we would like to include rooms 1142 and 1144 in this project.
PATTRSN-1218F-309396-Remodel
Schematic Design
Room: 1218F
Request date: 9/8/2023
Requested by: William Robertson
Contact: Steven Daniels
Construction start: 7/15/2024
Construction end: 1/13/2025
Description:
Renovate rooms 1218E & 1218F, including new ceiling, light fixtures, casework, floor tiles, etc.
PATTRSN-1222B-341842-Casework Replacement
Bidding
Room: 1222B
Request date: 2/6/2024
Requested by: William Robertson
Contact: Josef Biechler
Construction start: 4/26/2024
Construction end: 10/25/2024
Description:
Replace base cabinets, benchtop, sink and faucet. Steve Daniels has the details.
PATTRSN-1371-287389-Remodel
Construction Documents
Room: 1371
Request date: 6/15/2023
Requested by: Brian Adams
Contact: Steven Daniels
Construction start: 7/5/2024
Construction end: 1/3/2025
Description:
Jr Surgery wants to renovate some spaces for offices and lab space. Rooms included are 1310, 1312, 1371, 1377. Electrical, hvac, lighting, ceiling, sprinkler, fire alarm modifications needed to make a lab and to make an office in the spaces. Update 1/3/2024 - Remodel in room 1371 only
PATTRSN-1470-274164-Break Room Remodel
Project Closeout
Room: 1470
Request date: 4/25/2023
Requested by: Brian Adams
Contact: Josef Biechler
Construction start: 1/10/2024
Construction end: 4/26/2024
Description:
Break room, needs power distribution, label outlets to be read without taking cover plate off, floor strip and wax, and new furnishings. Keep existing cabinetry. LED light fixtures. 7/19/2023 - Adding Scope We are expanding the scope to add a new countertop and explore options for trash and recycling under that new countertop.
PATTRSN-1544-251789-Lab Back Up Power
Budget Approval
Room: 1544
Request date: 1/10/2023
Requested by: John Beary
Contact: Melissa Warg
Construction start: 5/13/2024
Construction end: 11/11/2024
Description:
attn Troy Bower rm 1544 needs a large custom UPS designed for the LCMS's in this room. Dave Borts sent troy specs for this equipment before christmas.
PATTRSN-1674-354801-Hoist System Extension
Schematic Design
Room: 1674
Request date: 4/2/2024
Requested by: Supun Dissanayake
Contact: Eric Ohrt
Construction start: 7/20/2024
Construction end: 1/18/2025
Description:
This is a request for an extension of the current hoist system track from the ceiling in the loading dock (Rm. 1674). The extension would be from the current end point of the track in the dock, extending out an extra ~10ft. towards the garage door to allow for proper coverage of roll off containers during body disposal.
PATTRSN-2111-334993-Fume Hood Repair & Lighting
Bidding
Room: 2111
Request date: 1/5/2024
Requested by: Brian Adams
Contact: Josef Biechler
Construction start: 5/3/2024
Construction end: 11/1/2024
Description:
Fume hood was damaged in a sprinkler discharge. Can it be repaired, or does it need replaced? What is the estimate to get a working fume hood? 1/29/24 - Added Scope Light Replacement added.
PATTRSN-2220-336675-Heat Exchanger Study
Construction Documents
Room: 2220
Request date: 1/22/2024
Requested by: John Netwal
Contact: Donna Imhoff
Construction start: 5/21/2024
Construction end: 11/19/2024
Description:
We would like to have the Engineering Team review the recent Heat Exchanger Installation for code compliance and safety in the mechanical room M2220 and develop a detailed plan to correct any deficiencies found that could be shared with either a contractor or in-house staff. An engineering probable cost estimate would be appreciated.
PATTRSN-2225-329853-Restrooms Sink and Countertop Replacement
Construction Documents
Room: 2225
Request date: 12/13/2023
Requested by: Brian Adams
Contact: Steven Daniels
Construction start: 5/21/2024
Construction end: 11/19/2024
Description:
Patterson hall restrooms 2225 and 2221 replace the sink countertop with a trough style sink like Student Innovation Center has.
PATTRSN-2259-272996-Flooring and Paint
Project Closeout
Room: 2259
Request date: 4/12/2023
Requested by: Melody Gustafson
Contact: Josef Biechler
Construction start: 7/17/2023
Construction end: 7/28/2023
Description:
New flooring and paint
PATTRSN-2280-348176-Furniture Replacement
Schematic Design
Room: 2280
Request date: 3/5/2024
Requested by: Justin Nolting
Contact: Rebecca Cantrall
Construction start: 7/15/2024
Construction end: 1/13/2025
Description:
Please start a project request for Vet Med Library. 2280 Patterson Hall, 1800 Christensen Dr, Ames, IA 50010. We would like to have some old furniture removed and replaced with 4 new powered Allsteel stride tables with individual partitions or similar to what is at Parks Library room 130. Along with 3 Brody chairs w/ power. Use PG103217 for worktag.
PATTRSN-2709-349888-Lab Emergency Power
Schematic Design
Room: 2709
Request date: 3/26/2024
Requested by: Supun Dissanayake
Contact: Steve Larson
Construction start: 7/15/2024
Construction end: 1/13/2025
Description:
We are trying to get an emergency power outlet for our Histology lab. I am checking with you to see if you will be able to help with checking the available generator capacity. Thank you for your assistance!
PATTRSN-2718-302034-Desk, Table and Chairs
Project Closeout
Room: 2718
Request date: 8/14/2023
Requested by: Supun Dissanayake
Contact: Leigh Wiand
Construction start: 12/22/2023
Construction end: 4/17/2024
Description:
Dr. Todd Bell would like to order a sit/stand desk, a round table, and four chairs to go with that. I sent the request to Tisha Campbell from Procurement. However, since this involves furniture moving and additional furniture requests, she suggested we go through FP&M a project assigned to one of the FP&M designers. She also mentioned that FP&M designers will be able to provide different furniture options as well as finish options. We would like to get a quote for this project.
PATTRSN-2754A-337313-Casework
Project Initiation
Room: 2754A
Request date: 1/26/2024
Requested by: Matthew Brewer
Contact: Josef Biechler
Construction start: 5/5/2024
Construction end: 11/3/2024
Description:
I need a small lab bench in this room. There is a concrete beam/rib that runs vertically on the wall, making this spot a challenge. It needs some kind of custom built countertop and some storage underneath
PATTRSN-2761-181613-Configure Three Work Stations
Project Closeout
Room: 2761
Request date: 4/12/2022
Requested by: Matthew Brewer
Contact: Melissa Warg
Construction start: 11/29/2023
Construction end: 1/9/2024
Description:
Need designer to configure space for 3 work stations in Rm 2761 and one work station in Rm 2761A. Will need desk, divider panels and above head cabinets. Requesting estimate
PATTRSN-Emergency Circuits
Construction Documents
Room: General
Request date: 8/31/2020
Requested by: William Robertson
Contact: Troy Bowers
Construction start: 5/21/2024
Construction end: 11/19/2024
Description:
Emergency Circuits
PATTRSN-General-315924-Room Signage
Bidding
Room: General
Request date: 10/6/2023
Requested by: Brian Adams
Contact: Josef Biechler
Construction start: 4/26/2024
Construction end: 10/25/2024
Description:
Room signage, black frame, clear removable lens, numbers and braille on the sign. Signs to be mechanically fastened to the walls since the double sided tape does not seem to last. List of rooms is in uploaded attachment.
PATTRSN-General-330452-Cage Washer Installation
Schematic Design
Room: General
Request date: 12/18/2023
Requested by: Dean Isaacson
Contact: Bruce Bonestroo
Construction start: 7/15/2024
Construction end: 1/13/2025
Description:
This project is going to encompass the entire demolition of the old cage washers in VMRI 40 and Patterson Hall and install of the new cage washers in both buildings. (separate projects per building) PR1223962-VMRI 40-329818-Cage Washer Installation PR1226578-PATTRSN-General-330452-Cage Washer Installation
PATTRSN-General-356062-Chair Cylinder Replacement
Construction Documents
Room: General
Request date: 4/16/2024
Requested by: Brian Adams
Contact: Rebecca Cantrall
Construction start: 6/26/2024
Construction end: 12/25/2024
Description:
This started as a possible warranty request, but ended up no longer being on warranty. I’ve requested a revised quote with just the part (replacement chair cylinder) and any shipping as Brian Adams at PATTRSN will be receiving & installing the new part.