START DATE: Tuesday, 8/7/2007 7:00 AM
END DATE: Wednesday, 8/15/2007 4:00 PM
AFFECTED SIDEWALK: Sidewalk on south side of Osborn Drive north of LeBaron
ALTERNATE ROUTE: Sidewalk on North side of Osborn Drive
WHY: Install water line to MacKay
DEADLINE for comments or requests to reschedule: Fri Aug 3 4:00 pm
COORDINATOR: Mike Murray at mimurray@mail.adp.iastate.edu or 294-8751
View this location on campus map:
http://www.fpm.iastate.edu/maps/closeup.asp?layer=base&left=591&top=1548&xshow=816&yshow=1708
Directional boring equipment will be set up in this area. The drive into the LeBaron/MacKay loading dock should not be affected.
Due to maintenance or construction activities, we must schedule a temporary sidewalk closure in the proximity of your building or a building occupied by your department.
Please inform/share information regarding this PROPOSED sidewalk closure with others in your building or department to assure that we have the input of all affected faculty/staff.
Reply to the coordinator (listed above) with any issues or concerns. If this proposed interruption will not work for you, contact the coordinator with suggestions for an alternate date and time.
For a list of current campus road, sidewalk, and parking lot closures, visit our web site at http://www.fpm.iastate.edu/notify/road_closures.asp
Thank you for your input and cooperation,
Facilities Planning and Management
WE WILL SEND A FINAL SIDEWALK CLOSURE NOTICE AFTER THE COMMENT DEADLINE.
---------------------------------------------------
You have received this email message because you are subscribed to one or more of our notification lists. To see and modify the notification lists that you are subscribed to, go to http://www.fpm.iastate.edu/notify/subscribe.asp