START DATE: Friday, 4/9/2010 7:00 AM
END DATE: Friday, 4/9/2010 9:00 AM
AFFECTED BUILDING/S: Moli-Bio
WHAT: Chilled Water
EFFECT OR IMPACT ON BUILDING SYSTEM: There will be no cooling for a/c or equip.
WHY: Repairing chill water meter
COORDINATOR: Phil Phipps at pphipps@iastate.edu or 291-5208
Due to maintenance or construction activities, we must temporarily interrupt utility service in or near your building or a building occupied by your department.
Please inform/share information regarding this SCHEDULED utility outage with others in your building or department to assure proper notification of all affected faculty/staff.
You may contact the coordinator (listed above) if you have any questions or if any problems arise concerning this scheduled interruption.
NOTE: Weather may alter these scheduled dates. We will attempt to keep you informed of major schedule changes.
Thank you for your cooperation,
Facilities Planning and Management
FINAL UTILITY OUTAGE NOTICE
---------------------------------------------------
You have received this email message because you are subscribed to one or more of our notification lists. To see and modify the notification lists that you are subscribed to, go to http://www.fpm.iastate.edu/notify/subscribe.asp