START DATE: Tuesday, 7/19/2011 6:00 AM
END DATE: Tuesday, 7/19/2011 8:00 AM
AFFECTED BUILDING/S: Friley (North section of building only)
WHAT: Electrical
EFFECT OR IMPACT ON BUILDING SYSTEM: No Electrical Service in the north sections of the Building
WHY: To replace building metering
COORDINATOR: Randy Larabee at rlarabee@iastate.edu or 294-2716
Due to maintenance or construction activities, we must temporarily interrupt utility service in or near your building or a building occupied by your department.
Please inform/share information regarding this SCHEDULED utility outage with others in your building or department to assure proper notification of all affected faculty/staff.
You may contact the coordinator (listed above) if you have any questions or if any problems arise concerning this scheduled interruption.
NOTE: Weather may alter these scheduled dates. We will attempt to keep you informed of major schedule changes.
Thank you for your cooperation,
Facilities Planning and Management