Current Projects in Atanasoff Hall

ATANSFF-0126B-434391-Remove Short Walls
Construction
Room: 0126
Request date: 4/4/2025
Requested by:
Contact: Brady Streit
Construction start: 4/28/2025
Construction end: 10/27/2025
Description:
We need an ESTIMATE on how much it would cost to remove 3 short walls in this room.
ATANSFF-0226-428065-Remodel
Cost Range Approval
Room: 0226A
Request date: 3/11/2025
Requested by:
Contact: Denise Wulf
Construction start: 7/10/2025
Construction end: 1/8/2026
Description:
Add wall in 226, add conference table with power, chairs, whiteboard, lights, ceiling tile, carpet, and paint
ATANSFF-General-336641-Water Heater Study
On Hold
Room: General
Request date: 1/22/2024
Requested by:
Contact: Denise Wulf
Construction start: 7/9/2025
Construction end: 1/7/2026
Description:
We would like to have the Engineering Team review the recently installed Water Heater for Code Compliance in the mechanical room and develop a detailed plan to correct any deficiencies found that could be shared with either a contractor or in-house staff. An engineering probable cost estimate would be appreciated.