Current Projects in Beyer Hall
BEYER-1306-403587-Add chilled water to rooms 1306, 1308 and 1310
Construction Documents
Room: 1306
Request date: 11/7/2024
Requested by: Garry Greenlee
Contact: Mike McCoy
Construction start: 7/11/2025
Construction end: 1/9/2026
Description:
Rec Services would like to investigate the possibility and cost to provide chilled water AC to Beyer Hall Food Pantry (SHOP) rooms 1306, 1308 and meeting room 1310.
BEYER-2304-382923-Rec Services Office Space
Construction
Room: 2304
Request date: 8/13/2024
Requested by: Garry Greenlee
Contact: Brady Streit
Construction start: 4/22/2025
Construction end: 10/21/2025
Description:
Rec Services needs to create office space in 2304, 2304a,2304b,2304c and 2302. This would include removing a closet that in not structural, designing two new offices in 2304 (glass walls), new office furniture, new conference room tables and chairs. Rec Service would like to meet and discuss our options so we are on the same page.
BEYER-2308-405215- Add second office
On Hold
Room: 2308
Request date: 12/2/2024
Requested by: Garry Greenlee
Contact: Alexa Peters
Construction start: 4/22/2025
Construction end: 10/21/2025
Description:
At Beyer Hall room 2308 has one office with glass walls. We need to add a second office with matching glass walls/door. Our preference would be directly south of office 2308A. If that is not possible then directly west of 2308A. Heating and cooling would need to be provided to this space from existing sources.