Current Projects in Carrie Chapman Catt Hall
CATT- RMS 0141 & 0143 – ADJ. HT. DESKS
Budget Approval
Room: 0143
Request date: 5/5/2025
Requested by: Kathleen Houseman
Contact: Alexa Peters
Construction start: 7/6/2025
Construction end: 1/4/2026
Description:
Would like an estimate for two rising desks similar to the one in Catt 151.
Additional location information: 0151
Work tags to attach: PG 100152
CATT-0223-368825-Furniture and AV Feedback
Project Closeout
Room: 0223
Request date: 6/5/2024
Requested by: Monic Behnken
Contact: Jennifer Warrick
Construction start:
Construction end:
Description:
We would like a consultation to convert the room from office space to a strategic planning epi-center. We would need furniture and AV feedback.
CATT-0251-430657-Move Office Door
Project Closeout
Room: 0251
Request date: 3/31/2025
Requested by: Rebecca Baldwin
Contact: Brady Streit
Construction start: 10/2/2025
Construction end: 5/1/2026
Description:
The door to office 251 faces one of our conference rooms and I would like to see about moving it so it faces the main entrance on the 2nd floor. Worktag PG100128.
CATT-0307-435370-Longer table
On Hold
Room: 0307
Request date: 4/17/2025
Requested by: Melissa Martin
Contact: Alexa Peters
Construction start:
Construction end:
Description:
Looking to obtain a longer table for our conference room. The current table (60 x 42) isn't big enough for all of us to fit around.
Work tags to attach: PG101141