Current Projects in Ross Hall

ROSS H-0212-341913-Conference Room Signage
Construction Documents
Room: 0212
Request date: 2/7/2024
Requested by: Candice Miller
Contact: Joseph Stoberl
Construction start: 8/7/2024
Construction end: 2/5/2025
Description:
I was not sure if this would be considered a project? We need two new signs for each side of our Ross 212 Conference Room. The current signs are 14"L x 5"H. Black background with white lettering (I'll attach a photo to this request). They currently say: Department of English Faculty-Graduate Student Lounge & Reading Room We would like new signs (same size to avoid wall repair) that say: Department of English Conference Room
ROSS H-0218-342683-Remodel
Construction
Room: 0218
Request date: 2/16/2024
Requested by: Candice Miller
Contact: Jennifer Warrick
Construction start: 5/17/2024
Construction end: 11/15/2024
Description:
218 Ross Hall is currently more of a storage room right now, but we do keep a lot of DVD's stored in there for our Film Studies course instructor, among other miscellaneous items such as a couple of old desks, wheeled carts, etc. We are working on relocating the DVD's, and we can either Surplus some of the rest of the items, or move them to our other storage room, 318. We are interested in converting 218 to a dining type area for people to use for lunch or breaks. We will not have any appliances or countertop electrical items, we mainly just want some tables and chairs to make it a nice space in which to eat or gather.
ROSS H-0218-350788-Lunchroom Sign
Construction Documents
Room: 0218
Request date: 3/27/2024
Requested by: Candice Miller
Contact: Joseph Stoberl
Construction start: 8/7/2024
Construction end: 2/5/2025
Description:
Duane Strah stopped by today in reference to Request number 341913 which was for new signs needed for Ross 212. We talked with him about making a another new sign for what is going to be our new Lunchroom, 218 Ross. It will be exactly like the sign that hangs from the ceiling directing people to our mailroom, but it will say "Lunchroom", with arrows on each side pointing to the room. Duane suggested I put in this ticket.
ROSS H-0529-375579-New Office Furniture
Schematic Design
Room: 0529
Request date: 7/9/2024
Requested by: Ashley Harris
Contact: Judy Dugan
Construction start: 10/7/2024
Construction end: 4/7/2025
Description:
Filip Viskupic in the Political Science department would like to purchase furniture for his office. He would like to see what furniture is available, specifically rugs, bookshelves, and a printer stand.
ROSS H-GENERAL-342099-Wall Monitor Display Case
Project Closeout
Room: General
Request date: 2/9/2024
Requested by: Candice Miller
Contact: Jennifer Warrick
Construction start: 3/20/2024
Construction end: 6/13/2024
Description:
We have a 65" monitor that we would like to have mounted on the 2nd floor in the hallway, south wall, immediately preceding the 212 Ross Conference Room. We will need you to purchase the mount for the monitor. There is an electrical outlet on that wall toward the ground that will need to be relocated so it sits behind the monitor. Lastly, we would like to know an estimate on either purchasing a pre-made "box" to surround the monitor on each side to protect it from possible damage (if someone should accidentally catch their bookbag on it while walking through the hall, or other similar scenario), or if Carpentry could possibly make such a box.