Current Projects in Student Services Building

Student Services Building-First Floor-Remodel
CP1235453
Initiated date: 2/28/2024
Contact: Angela Solberg
Description:
This project will convert two offices into a more centrally located conference room, convert the conference room in the office suite area into three new offices, create an office suite for the Dean of Students, and upgrade finishes in multiple offices and corridors to match other recently completed interior improvements. This project includes, but is not limited to, architectural, mechanical, electrical, technology, equipment, finishes, and furniture.
STD SER-2010-447286-Furniture Upgrades
PR1283919
Initiated date: 8/1/2025
Contact: Amy Tremain
Description:
We are moving all of Student wellness over to the 2010 office area with all those offices in that hallway on the second floor of SSB. We are wanting to upgrade some of our furniture for this move. We have been working a bit with Tracy Borts from DSO who has just completed this process. The carpet/paint we've been told is very similar to the DSO redesign. Shes shared some of the furniture they've purchased, and we imagine we'd want a lot of the same. We already upgraded our office chairs back in April with Procurement.
Student Services Building-Pressure Reducing Valve-Relocation
PR1117011
Initiated date: 8/28/2025
Contact: Amy Tremain
Description:
Please put together a project to move the PRV in this building from its current location. It is currently in a crawlspace under the building where there is no floor (dirtmud only) making repairs, adjustments, etc. difficultdangerous. I will need a scope and cost for this project only.
Student Services Building-Third Floor-Estimate
PR1244624
Initiated date: 8/28/2025
Contact: Mitchell Hlavacek
Description:
We are wanting to get estimates done and figure out what the process would look like for us to complete the following projects. 1. Changing flooring throughout the entire 3rd floor of Student Services. We are wanting to know what the cost would be if we got carpet everywhere compared to the price of having certain areas tiled as well. We are wanting to match the style of the first floor of Student Services if possible. 2. Patching and painting the entire 3rd floor of Student Services.
STD SER-General-338221-Fire Escape Repairs
PR1232607
Initiated date: 9/16/2025
Contact: Amy Tremain
Description:
Fire Escape Repairs - Fire Escape Inspection Report in the LX folder and G Drive folder. Bricks appear to be coming loose below the third-floor landing where the fire escape attaches to the exterior of the building. Have the fire escape inspected by a registered design professional and place particular emphasis on this area. By section 1104.16.5.1 this should be repeated every 5 years.