Current Projects in Town Engineering Building

Town - Rm 0387 - 398897 - Provide 3 Independent Circuits and Temperature Control
Bidding
Room: General
Request date: 10/30/2024
Requested by:
Contact: Mitchell Hlavacek
Construction start: 5/13/2025
Construction end: 11/11/2025
Description:
Provide a cost range estimate to provide the following features in room 0387. Provide a separate estimate for each room as we use the estimates to select the best path forward. --Provide 3 independent, isolated circuits, such that 3 computers could be hosted on each circuit --Provide temperature control. The room will need to be able to be cooled, as the computers will generate heat.
TOWN-0034-441150-Replace and improve lighting
Project Initiation
Room: 0034
Request date: 5/5/2025
Requested by:
Contact: Mitchell Hlavacek
Construction start: 7/27/2025
Construction end: 1/25/2026
Description:
Replace and improve the lighting in Town 34. LED fixtures are preferred. Include estimates for Town 0040 and 0042 as well. Please provide an estimate for each room, so we can make the decision by room. Thank you.
TOWN-0074-362380-Replace Emergency Power Generator
Project Closeout
Room: 0074
Request date: 5/13/2024
Requested by:
Contact: Eric Ohrt
Construction start: 11/8/2024
Construction end: 1/21/2025
Description:
Replace emergency power generator with abandoned generator from Gerdin
TOWN-0130-376731-Overhead Door North Structures Lab
Project Closeout
Room: 0130
Request date: 7/23/2024
Requested by:
Contact: Eric Ohrt
Construction start: 11/8/2024
Construction end: 3/3/2025
Description:
Provide cost analysis and possible solutions for overhead door issues in the north structures lab, room 130 Wooden overhead door -- the north door on the west side: Door is in bad condition and is not used because of this. Provide estimate to infill. West side, south door: Provide estimate to upgrade the seal package to reduce excessive infiltration and rodents through gaps. Provide estimate to replace door with one that fits better for improved energy efficiency. Photos attached Work tags to attach: SG0518112
TOWN-0134-382561-Repurpose Office Space
Project Closeout
Room: 0134
Request date: 8/9/2024
Requested by:
Contact: Mitchell Hlavacek
Construction start: 8/25/2025
Construction end: 3/24/2026
Description:
Repurpose Town 134 into graduate student office space.
TOWN-0178-343193-New Diffusers
Project Closeout
Room: 0178
Request date: 2/20/2024
Requested by:
Contact: Eric Ohrt
Construction start: 3/13/2024
Construction end: 3/28/2024
Description:
The new diffusers in room 0178.
TOWN-0220-416686-Purchase 8 additional chairs
Project Closeout
Room: 0220
Request date: 1/27/2025
Requested by:
Contact: Mitchell Hlavacek
Construction start: 2/4/2025
Construction end: 4/23/2025
Description:
Purchase 8 additional chairs for Town 220. Current chairs were purchased on PR1229914. These 8 should be the same chair so they match. I don''t need design; just 8 additional chairs. We only ordered 32 and need 40.
TOWN-0322-435502-Replace whiteboards
Construction Documents
Room: 0322
Request date: 4/21/2025
Requested by:
Contact: Carrie Choudhury
Construction start: 7/8/2025
Construction end: 1/6/2026
Description:
Replace whiteboards in Town 322 with Deco boards similar to what is in Town 220 and 230. Be sure that when installed, they are secure to the wall and don't flex.
TOWN-General-336671-Heat Exchanger Study
On Hold
Room: General
Request date: 1/22/2024
Requested by:
Contact: Denise Wulf
Construction start: 7/8/2025
Construction end: 1/6/2026
Description:
We would like to have the Engineering Team review the recently replaced Heat Exchanger for code compliance and safety in the mechanical room and develop a detailed plan to correct any deficiencies found that could be shared with either a contractor or in-house staff. An engineering probable cost estimate would be appreciated.
TOWN-General-355438-Exterior Building Signs
Project Closeout
Room: General
Request date: 4/10/2024
Requested by:
Contact: Joseph Stoberl
Construction start:
Construction end:
Description:
ATTN: Joe Stoberl Relocate Town Engineering Building sign on east side of building to the south, just south of the bike racks, between the two trees near the diagonal walk. Install a second Town Engineering Building sign on the north side of the building. Project and both locations have been discussed with Joe. TOWN Additional location information: North and east side of building; exterior Work tags to attach: PG101370
TOWN-Room C0124-335115-Furniture Replacement
Project Closeout
Room: C0124
Request date: 1/8/2024
Requested by:
Contact: Mitchell Hlavacek
Construction start: 7/9/2024
Construction end: 5/7/2025
Description:
Replace furniture in the north-south hallway on the west side of the building: Please proceed with planning and a detailed estimate.