16 Joseph Mesner WG35331 S - Repack bypass valve between header and G tunnel Open
18 Lindsey Wanderscheid WJ35696 - Utilities - Power Plant - Boiler Resiliency Study Open
22 Joseph Mesner WH30040 S - Repack valve going to the gauge on the 400# header Open
24 Joseph Mesner WH48288 TG5 - Oil pressure to TG engage piston is on 4 PSI Open
27 Joseph Mesner WJ11288 WT-DW - Leak in the demin line west side of DA Open