Current Projects

Loading project list, please wait...
CP # Project Construction Budget Phase Phase % Bid Date Begin Const Comp / Occ Project Manager Const Manager
2206 Ag Engineering & Agronomy Farm-Rainout Shelters PRE-DESIGN Mark Huss Mark Huss
2401 Armory-Window Replacement-Phase 2 $159,600 DESIGN-CD 04/12/2018 05/01/2018 09/30/2018 Jon Harvey John Boehmer
2269 Barton Residence Hall-FY17 Life Cycle $223,300 COMPLETE 97 06/01/2016 07/31/2017 Mark Huss
2409 Barton-Lyon-Freeman-Roof Replacements $855,800 CONSTRUCTION 0 01/23/2018 01/29/2018 09/30/2018 David Blum Darrell Reeves
2394 Beardshear Hall-Air Handling Unit Replacement $304,320 BID 01/30/2018 05/01/2018 08/31/2018 Mark Grief Rob Ebel
2212 Beardshear Hall-Suite 2150 Remodel $90,000 POST CONSTRUCTION 100 11/19/2015 11/30/2015 03/31/2016 Kerry Dixon Lynn Burnett
2292 Bergstrom Football Complex-Expansion Study COMPLETE 100 09/30/2016 Dan Sloan
2402 Bergstrom Football Complex-Johnny Majors Filming Platforms $203,500 CONSTRUCTION 07/31/2017 11/30/2017 Jon Harvey
2146 Bessey Hall Space Reallocation Study $35,000 COMPLETE 100 07/31/2016 Dan Sloan
2351 Beyer Hall-Infrastructure Improvements $1,430,000 CONSTRUCTION 66 07/20/2017 08/01/2017 04/30/2018 Jon Harvey Danelda Allen
2055 Biosciences Facilities-Advanced Teaching & Research Building $42,185,000 CONSTRUCTION 91 03/16/2016 10/01/2015 01/31/2018 Mark Grief Renee Fleming
2115 Biosciences Facilities-Bessey Hall Addition $20,250,000 CLOSEOUT 98 03/03/2016 03/17/2016 08/15/2017 Mark Grief Rob Ebel
2272 Birch, Welch & Roberts Residence Halls-FY17 Life Cycle Improvements $695,738 COMPLETE 99 05/01/2017 08/31/2017 Mark Huss
2317 Black Engineering Node Room Electrical Panel Additions $59,630 CONSTRUCTION 95 06/01/2016 07/01/2016 05/31/2017 Jim Haberichter Jim Haberichter
2259 Campanile-Stanton Memorial Carillon Renovation CONSTRUCTION 100 08/01/2016 08/31/2017 David Blum Bart Dobson
2427 College Creek-Bank Erosion Repair $108,900 CONSTRUCTION 0 10/17/2017 11/14/2017 04/20/2018 Rhonda Martin Mike Parsons
2223 Coover Hall-Building Envelope and Infrastructure Study COMPLETE 100 08/01/2015 09/30/2016 Dan Nutini
2395 Curtiss Farm-Outdoor Archery Range $25,000 CONSTRUCTION 11 07/01/2017 10/31/2017 Mark Huss Troy Chandler
2274 Department of Residence-Elevator Safety Improvements FY17 $545,000 COMPLETE 100 04/01/2016 05/01/2017 08/31/2017 Mark Huss
2469 Department of Residence-Elevator Safety Improvements FY18 $495,000 QUOTE 0 05/31/2018 08/31/2018 Jennie Elliott
2230 Department of Residence-Office Consolidation Study COMPLETE 100 Dan Sloan
2429 East Hall-Electrical Panels & Disconnect Replacement $214,500 CONSTRUCTION 0 12/12/2017 12/18/2018 08/31/2018 David Blum Troy Chandler
2495 Eaton Hall-Life Cycle Improvements $535,000 QUOTE 0 05/31/2018 08/31/2018 Jennie Elliott
2153 Forker Building-Kinesiology Renovation $4,495,400 POST CONSTRUCTION 95 03/10/2016 08/01/2016 09/30/2017 Jon Harvey Mike Parsons
2368 Forker Building-South and West Vestibule Remodeling $247,000 CLOSEOUT 91 06/06/2017 07/01/2017 10/30/2017 Jon Harvey Mike Parsons
2392 Forker Building-Tennis Court Building $46,600 POST CONSTRUCTION 72 08/28/2017 08/31/2017 12/31/2017 Jon Harvey Nathan Graves
2482 Frederiksen Court-11-13-Life Cycle Improvements-Flooring & Painting $760,000 QUOTE 0 05/31/2018 08/31/2018 Jennie Elliott
2267 Frederiksen Court-Fire Alarm System Upgrade-Phase 1 $139,700 COMPLETE Mark Huss Leroy Brown
2264 Freeman and Lyon Residence Halls-Life Cycle Improvements $422,500 COMPLETE 98 05/01/2016 07/31/2016 Mark Huss
2056 Friley Residence Hall-Dining Renovation $6,297,500 CLOSEOUT 97 09/13/2016 09/30/2016 08/31/2017 Elizabeth Clarke Mike Parsons
2243 Friley Residence Hall-Hall Director Apartment Remodel $192,500 CLOSEOUT 95 03/29/2016 05/01/2016 07/31/2016 Elizabeth Clarke Bob Catus
2472 Friley Residence Hall-Life Cycle Improvements $1,055,080 QUOTE 05/31/2019 08/31/2019 Jennie Elliott
2436 Friley Residence Hall-Window Replacement $3,907,490 CONSTRUCTION 01/25/2018 02/13/2018 07/31/2020 David Blum Danelda Allen
2135 Gerdin Business Building Addition Study $97,570 STUDY 96 02/29/2016 Dan Sloan
2186 Gilman Hall-Master Plan Study COMPLETE 100 08/31/2015 11/30/2016 Dan Nutini
2311 Gilman Hall-Remove Air Handling Units 2 & 3 $58,450 CONSTRUCTION 95 05/01/2017 08/31/2017 Jim Haberichter Jim Haberichter
2353 Gilman Hall-Rooms 2653 & 2659 Remodeling $84,740 BID 95 04/07/2017 05/01/2017 07/31/2017 Jim Haberichter Jim Haberichter
2447 Hamilton Hall-Window Replacement-Phase 2 $165,000 CONSTRUCTION 02/15/2018 02/19/2018 08/31/2018 Jennie Elliott Mike Parsons
2359 Heady Hall-Classroom Improvements $74,614 BID 0 01/19/2018 01/31/2018 08/31/2018 Wes Gee Russ Dodson
2422 Hilton Coliseum Parking Expansion $3,010,700 BID 03/13/2018 04/30/2018 08/31/2018 Angie Solberg Rob Ebel
2407 Hilton Coliseum-Ceiling Refinish DESIGN-CD 05/01/2018 07/31/2018 Jon Harvey Mike Parsons
2278 Howe Hall-Various Rooms Modernization $12,000 COMPLETE 0 05/01/2016 07/31/2016 Jordan Hutchens Jordan Hutchens
2477 Human Nutritional Sciences Building-AHU 1-Humidification System Replacement $181,500 DESIGN-CD Jon Harvey
2287 Institutional Roads 2016-Pavement Management Plan COMPLETE 100 04/01/2016 07/31/2016 Angie Solberg
2271 Institutional Roads 2016-Special Maintenance $0 COMPLETE 100 06/01/2016 08/31/2016 Angie Solberg
2345 Institutional Roads 2017-Pavement Preservation $0 COMPLETE 05/01/2017 08/31/2018 Angie Solberg Angie Solberg
2343 Institutional Roads 2018-Union Drive and Welch Road Reconstruction $2,043,000 CONSTRUCTION 0 12/19/2017 01/10/2018 06/30/2019 Angie Solberg Leroy Brown
2377 Iowa Braille and Sight Saving School-Bowling Lane Removal $38,000 QUOTE 0 Jon Harvey Bob Catus
2432 Iowa Braille and Sight Saving School-Old Main-Fire Sprinkler Upgrades $132,000 Jon Harvey
2403 Iowa Braille and Sight Saving School-Palmer Hall Window Sash Replacement $99,750 CONSTRUCTION 100 09/01/2017 12/31/2017 Jon Harvey Brad Tonyan
2366 Iowa School for the Deaf-Careers Building Accessible Ramp $77,000 ON HOLD Jon Harvey Brad Tonyan
2094 Jack Trice Stadium Improvements-Phase 3-Green Space-Landscaping $7,835,900 CONSTRUCTION 30 01/26/2017 06/01/2017 06/30/2018 Jon Harvey Bob Catus
2094 Jack Trice Stadium Improvements-Phase 3-Green Space-Paving and Site Work $2,234,100 CONSTRUCTION 97 03/29/2016 04/01/2016 10/31/2016 Jon Harvey Bob Catus
2386 Jack Trice Stadium-Technology Upgrades $137,500 CLOSEOUT 95 05/23/2017 06/01/2017 08/31/2017 Jon Harvey Bob Catus
2435 Knoll-Exterior Repairs-Roof Replacement $266,274 CONSTRUCTION 0 11/30/2017 12/05/2018 04/04/2018 Mark Huss Danelda Allen
2408 Lagomarcino Hall-East Entry and Dean's Suite Remodeling $128,000 CONSTRUCTION 97 08/31/2017 11/15/2017 01/31/2018 Kerry Dixon Darrell Reeves
2308 Lagomarcino Hall-School of Education Feasibility Study COMPLETE 100 08/31/2017 Brandi Latterell Brandi Latterell
2247 LeBaron Hall Study COMPLETE 100 03/01/2016 11/30/2016 Dan Nutini
2410 Lied Recreation Athletic Facility-Flood Mitigation Upgrades $64,500 BID 95 Mark Graeve Mark Graeve
2393 Lied Recreation Athletic Facility-Lighting Upgrades $206,415 COMPLETE 95 07/06/2017 07/01/2017 11/30/2017 Wes Gee Darrell Reeves
2326 Lincoln Way Multimodal Crossing Data Collection and Analysis $100,887 STUDY 59 08/01/2016 01/31/2018 Cathy Brown
2468 Linden Residence Hall-Life Cycle Improvements $1,200,000 QUOTE 0 05/31/2018 07/31/2018 Jennie Elliott
2437 Linden Residence Hall-Window Replacement $1,327,700 CONSTRUCTION 0 12/19/2017 01/05/2018 07/27/2018 David Blum Darrell Reeves
2249 MacKay Hall-Center Wing Window Replacement $150,000 CONSTRUCTION 0 01/18/2018 05/31/2018 08/10/2018 Kerry Dixon Danelda Allen
2385 Maple-Willow-Larch Recreation Fields Improvements-Irrigation and Turf $1,151,000 BID 02/22/2018 03/31/2018 09/30/2018 Wes Gee Mike Parsons
2385 Maple-Willow-Larch Recreation Fields Improvements-Site Electrical and Lighting $1,095,000 CONSTRUCTION 78 12/05/2017 12/22/2017 07/16/2018 Wes Gee Mike Parsons
2006 Marston Hall Renovation $18,557,009 POST CONSTRUCTION 100 01/22/2015 07/01/2014 07/31/2016 Kerry Dixon Russ Dodson
2418 Memorial Union-Dining Services Central Space Remodel $1,320,000 BID 03/27/2018 Elizabeth Clarke Darrell Reeves
2417 Memorial Union-Dining Services Franchise Space Remodel $371,410 CLOSEOUT 95 09/26/2017 09/27/2017 12/08/2017 Elizabeth Clarke Darrell Reeves
2254 Memorial Union-Northeast Addition Feasibility Study $65,000 COMPLETE 100 01/01/2016 07/31/2016 Dan Sloan
2194 Molecular Biology Building and Roy J. Carver co-Lab Space Utilization Study COMPLETE 100 05/01/2015 10/31/2016 Margie Tabor
2350 Molecular Biology Building-Consolidated Microscopy Facility $249,200 CLOSEOUT 101 05/11/2017 06/01/2017 11/30/2017 Wes Gee Rob Ebel
2479 Music-AHU2 Humidification System Replacement $148,000 DESIGN-CD 04/10/2018 05/31/2018 08/31/2018 Jon Harvey John Boehmer
2325 National Swine Research & Information Center-Elevator Jack Repair $118,000 COMPLETE 77 08/01/2016 10/01/2016 Rick Reedholm Rick Reedholm
2473 Oak-Elm Residence-Life Cycle Improvements $1,055,840 QUOTE 05/31/2019 08/31/2019 Jennie Elliott
2216 Oakwood Trail Extension COMPLETE 89 10/01/2016 11/30/2016 Angie Solberg
2357 Osborn Drive Sidewalk Widening-Phase Three-East Corridor $108,000 CONSTRUCTION 0 12/07/2017 12/08/2017 07/27/2018 Rhonda Martin Mike Parsons
2404 Parking Lot 96-Expansion $642,000 BID 03/08/2018 05/31/2018 08/31/2018 Angie Solberg Mike Parsons
2451 Parking Lots 2018-Pavement Preservation $176,000 DESIGN-CD 05/31/2018 08/31/2018 Angie Solberg Mike Parsons
2379 Parks Library-Restroom Renovations $1,743,500 BID 03/06/2018 05/31/2018 08/31/2019 Elizabeth Clarke John Boehmer
2424 Parks Library-Roof Replacement Sections E-I, Q & R $880,000 CONSTRUCTION 66 09/12/2017 09/13/2017 01/11/2018 Wes Gee Mike Parsons
2283 Parks Library-Space Feasibility Study COMPLETE 100 04/01/2016 12/31/2016 Dan Nutini John Boehmer
2330 Pearson Hall-Rooms 0157, 2130, 2140, 2223 and 2229 Remodel $189,221 POST CONSTRUCTION 95 02/23/2017 04/01/2017 08/31/2017 David Blum Lynn Burnett
2307 Recreation Services Outdoor Facilities-Master Plan Study STUDY 94 06/01/2016 10/31/2016 Dan Sloan
2336 Reiman Gardens-Hillside Garden Improvements $196,350 CONSTRUCTION 93 10/18/2016 10/01/2016 04/30/2017 Chris Strawhacker Bob Catus
2363 Reiman Gardens-Southwest Corner Improvements-Landscaping $2,611,100 BID 02/20/2018 03/31/2018 10/31/2018 Mark Huss John Boehmer
2363 Reiman Gardens-Southwest Corner Improvements-Site Preparation $62,200 CLOSEOUT 90 04/06/2017 04/30/2017 07/31/2017 Mark Huss Bob Catus
2277 Richardson Court Residence Halls-Bathroom Remodeling-Phase 1 $2,000,000 CLOSEOUT 100 01/24/2017 05/01/2017 08/31/2018 David Blum Leroy Brown
2268 Schilletter Village-Exterior Improvements-Phase 1 $197,500 COMPLETE 100 04/30/2017 10/31/2017 Mark Huss
2380 Science Hall-Roof Replacement Sections A B F & G $237,297 COMPLETE 100 07/06/2017 06/01/2017 09/30/2017 Wes Gee Mike Parsons
2400 State Gym and Lied Recreation Athletic Facility-Access Control Upgrades $24,000 COMPLETE 07/01/2017 10/31/2017 Mark Grief
2225 Student Innovation Center $59,000,000 CONSTRUCTION 11 03/07/2017 03/01/2017 01/31/2020 Elizabeth Clarke Leroy Brown
2383 Thielen Student Health Center-Roof Replacement-Sections A,C-H & L $201,400 COMPLETE 100 08/10/2017 08/11/2017 11/19/2017 Wes Gee Lynn Burnett
2306 Towers Community-Feasibility Study COMPLETE 91 06/01/2016 08/31/2016 Dan Sloan
2339 Town Engineering-Bridge Crane Load Brake Repairs QUOTE 12/16/2016 01/01/2016 07/31/2017 Mark Huss Jim Haberichter
2458 Union Drive Community Center-Clyde's Dining Renovation $765,600 BID 03/29/2018 David Blum Rob Ebel
2284 University Boulevard & Highway 30 West Bound Exit Ramp-Traffic Signal $116,000 CONSTRUCTION 78 08/01/2016 10/31/2016 Angie Solberg Angie Solberg
2191 University Village-Roof and Window Replacement FY16 COMPLETE 100 09/01/2016 01/31/2017 Mark Huss
2324 Utilities-Chilled Water West Campus Distribution Improvements $4,070,000 CONSTRUCTION 0 01/18/2018 02/08/2018 08/09/2019 Randy Larabee Leroy Brown
1998 Utilities-Haber Road Substation Expansion $1,780,000 CLOSEOUT 100 03/11/2014 03/18/2014 06/30/2016 Randy Larabee Randy Larabee
2322 Utilities-Increase Chilled Water Capacity-Paint Shop Boiler $147,400 CLOSEOUT 95 05/25/2017 06/01/2017 09/30/2017 Lindsey Wanderscheid Mike Murray
2322 Utilities-Increase Chilled Water Capacity-Plant/Yard $6,000,000 CONSTRUCTION 64 06/06/2017 06/30/2017 06/30/2018 Lindsey Wanderscheid Lindsey Wanderscheid
2322 Utilities-Increase Chilled Water Capacity-West Corridor $4,000,000 CONSTRUCTION 98 04/04/2017 04/30/2017 06/30/2018 Lindsey Wanderscheid Lindsey Wanderscheid
2387 Utilities-Lied Recreation Athletic Facility-Steam Supply Replacement $1,142,700 CONSTRUCTION 0 01/09/2018 01/19/2018 08/12/2018 Wes Gee Leroy Brown
2229 Utilities-North Chilled Water Plant-C5 Controls Replacement $87,000 CLOSEOUT 0 10/01/2016 04/30/2017 Lindsey Wanderscheid Lindsey Wanderscheid
2213 Utilities-North Chilled Water Plant-Chiller #6 Study CLOSEOUT 99 10/01/2015 03/31/2016 Lindsey Wanderscheid Lindsey Wanderscheid
2476 Utilities-Power Plant-Chiller 3 Compressor Overhall 2018 $170,000 Lindsey Wanderscheid
2463 Utilities-Power Plant-Export Meter Replacement $29,500 CONSTRUCTION Jeff Witt Lindsey Wanderscheid
2423 Utilities-Power Plant-Fire Alarm System Improvements $418,000 DESIGN-CD Lindsey Wanderscheid
2344 Utilities-Power Plant-North Bucket Elevator Repairs $50,000 COMPLETE 100 04/01/2017 04/30/2017 Lindsey Wanderscheid Lindsey Wanderscheid
2320 Utilities-Power Plant-Programmable Logic Controller Upgrades $401,650 CONSTRUCTION 0 09/01/2016 08/31/2019 Lindsey Wanderscheid Lindsey Wanderscheid
2309 Utilities-Power Plant-Stack Repairs 2017 $132,000 POST CONSTRUCTION 102 02/16/2017 04/01/2017 07/31/2017 Lindsey Wanderscheid Lindsey Wanderscheid
2340 Utilities-Power Plant-Stoker Building Repairs $1,648,900 CONSTRUCTION 74 08/31/2017 09/22/2017 04/30/2018 Lindsey Wanderscheid Mike Parsons
2378 Utilities-Power Plant-TG6 Overhaul 2018 $450,000 CONSTRUCTION 12/01/2017 03/31/2018 Lindsey Wanderscheid Lindsey Wanderscheid
2475 Utilities-South Campus-No. 1 Feeder Replacement $145,000 BID 03/15/2018 04/30/2018 07/31/2018 Mike Olson Mike Olson
1953 Utilities-Stoker Boiler Replacement $23,370,978 COMPLETE 100 06/10/2014 08/01/2014 02/29/2016 Jeff Witt Lindsey Wanderscheid
2497 Various Buildings-A17.3 Code Elevator Upgrades-Mechanical Electrical Plumbing $522,500 PRE-DESIGN Jennie Elliott
2494 Various Buildings-A17.3 Code Elevators Upgrades-Elevator $522,500 Jennie Elliott
2140 Various Elevator Repairs FY15 $93,585 POST CONSTRUCTION 100 09/01/2017 01/31/2018 Kerry Dixon
2239 Veterinary Medicine-Commons and Cafe Remodeling $1,632,000 CONSTRUCTION 59 04/25/2017 05/01/2017 08/31/2018 Wes Gee Danelda Allen
2239 Veterinary Medicine-Commons and Cafe Remodeling-Rooms 2005, 2098, 2532, 2784, & 2780 Modifications $53,956 CLOSEOUT 85 04/20/2017 05/31/2017 07/31/2017 Wes Gee Brad Tonyan
2425 Veterinary Medicine-Domestic Water Line Replacement-Phase 3 $124,410 CONSTRUCTION 81 10/12/2017 10/13/2017 03/31/2018 Mark Grief Darrell Reeves
2438 Veterinary Medicine-Exterior Freezer-Site and Building Preparation $20,600 CONSTRUCTION 95 08/14/2017 08/17/2017 09/15/2017 Jordan Hutchens Jordan Hutchens
2381 Veterinary Medicine-Room 1365G Remodeling $69,000 COMPLETE 95 05/22/2017 05/01/2017 08/31/2017 Nathan Graves Nathan Graves
2389 Veterinary Medicine-Rooms 1321 & 1323 Remodel $76,000 COMPLETE 95 05/22/2017 05/31/2017 08/31/2017 Nathan Graves Nathan Graves
2384 Veterinary Medicine-Rooms 2280, 2280A-C Lighting Replacement $100,000 CONSTRUCTION 98 06/01/2017 07/31/2017 Kenny Thelen Kenny Thelen
2415 Veterinary Medicine-Stereotactic Radiation Therapy Addition $550,000 CONSTRUCTION 0 01/11/2018 01/29/2018 07/03/2018 Wes Gee Rob Ebel
2355 Wallace and Wilson Residence Halls-Window Replacement-Phase 2 $2,700,000 CONSTRUCTION 0 01/04/2018 01/16/2018 07/31/2018 Mark Grief Renee Fleming
2443 Welch Avenue-CyRide Turnaround $214,500 CONSTRUCTION 01/30/2018 02/05/2018 08/06/2018 Angie Solberg Renee Fleming
2446 Zaffarano Physics Addition-Exterior Repairs $619,300 BID 03/22/2018 08/31/2018 10/31/2018 David Blum Mike Parsons
2445 Zaffarano Physics Addition-Fan Coil Replacement-Phase 2 $155,000 CONSTRUCTION 0 11/14/2017 01/31/2018 06/25/2018 David Blum Mike Parsons