CP002505 - SPORTS PERFORMANCE CENTER & JACK TRICE STADIUM IMPROVEMENTS NORTH

SITE UTILITIES

Project Team

Project Manager Jon Harvey
Construction Manager Renee Fleming
Design Professional SUBSTANCE ARCHITECTURE
Prime Contractor /
Construction Manager

Project Information

Project Type UTILITIES/TELECOMM
Construction Type NEW BUILDING
Administrative Unit ATHLETICS
Space Type ATHLETICS
Gross Sq Ft 0

Project Cost

Project Budget $90,000,000
Project Cost GSF 0
Construction Budget $1,300,000
Construction Cost GSF 0
% Complete 28%

Schedule Information

Bid Date 3/28/2019
Status CONSTRUCTION
Contract Award Date 04/04/2019
Construction Completion Date 10/14/2019

Project Description

A NEW FACILITY WILL BE CONSTRUCTED ON THE EAST SIDE OF THE BERGSTROM FOOTBALL COMPLEX THAT WILL BE USED BY ALL STUDENT-ATHLETES. THIS FACILITY WILL PROVIDE AN EXPANDED ACADEMIC AND STUDENT AFFAIRS CENTER, COMMONS AREA FOR STUDENTS TO GATHER AND INTERACT WITH FELLOW STUDENT-ATHLETES, AND A FULL SERVICE SPORTS NUTRITION CENTER INCLUDING FUELING STATIONS AND A DINING FACILITY THAT WILL BE STAFFED BY REGISTERED DIETICIANS. THE FACILITY WILL ALSO INCLUDE EXPANDED SERVICE AREAS INCLUDING SPORTS MEDICINE, STRENGTH AND CONDITIONING, AND LOCKER ROOMS FOR MULTIPLE VARSITY SPORTS.

Webcams associated with this project

Sports Performance Center