Current Projects

Loading project list, please wait...
Administrative Services Building-HVAC System Conversion
CP number: CP002721
Total Construction Budget: $2,356,489
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace the building roof and HVAC system. The HVAC system will be relocated from the roof, replaced in a new mechanical room, and connected to the campus chilled water system. This project includes, but is not limited to: removal of the existing building boilers and roof-top HVAC system, connection to the campus chilled water loop, construction of a mechanical room on the west side of the building, installation of new air handling equipment, boilers, and associated components, and replacement of the existing roof system.
Administrative Services Building-HVAC System Conversion
Construction
Scope number: PS01
Construction Budget: $2,356,489
Begin construction: 10/01/2022
Occupancy / completion: 05/14/2023
Gross sq.ft.: 1420
Net sq.ft.: 1420
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager: Mark Grief
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, the replacement of the building roof and removal of the underperforming HVAC system from the roof, replacing it with a new mechanical room building, new energy efficient air handling system, and connection to the adjacent campus chilled water system. This project includes removal of the existing HVAC system, connection to the campus chilled water loop, construction of a new two-story mechanical room on the west side of the building, installation of new air handling equipment, cooling coils and associated components, replacement of the existing ASB roof system, relocation of the existing emergency generator. All the work associated with this will require a phased approach and the new system must be operational prior to the removal of the existing HVAC systems.
Bid Date: 06/23/2022

Subcontractors (13)

Ag-37-Lab and Classroom Welding Fume Extractor-Installation
CP number: CP1167231
Total Construction Budget: $189,200
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will install a welding fume ventilation and exhaust system in the laboratory and classroom building (AG-37) at the AG-450 farm.
Ag-37-Lab and Classroom Welding Fume Extractor-Installation
Construction
Scope number: PS01
Construction Budget: $190,200
Prime contractor: Multiple Constructors
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
This project will install a welding fume ventilation and exhaust system in the laboratory and classroom building (AG-37) at the AG-450 farm.
Bid Date: TBD
Agronomy Hall-Common Area Improvements
CP number: CP941036
Total Construction Budget: $650,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, remodeling three primary corridors spaces by removing and replacing old ceiling systems with new lay-in and decorative ceilings, new lighting, new paint finishes on walls and any exposed ceiling, and a new floor base. The common student hub area will be updated to receive new carpet and a coffee bar, and a new rated glass door will be installed. New furniture to include cafe style tables, chairs, and benches.
Agronomy Hall-Common Area Improvements
Scope number: PS01
Construction Budget: $599,900
Begin construction: 02/13/2023
Occupancy / completion: 08/11/2023
Gross sq.ft.: 8243
Net sq.ft.: 8243
Prime contractor: TRINITY CONSTRUCTION GRP LTD
Project manager: Hayley Sandholm
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, remodeling three primary corridor spaces. Improvements include removing and replacing old ceiling systems with new lay-in and decorative ceilings, new lighting, new paint finishes on walls and any exposed ceiling, and new floor base. The common student hub area will be updated to receive new carpet and a coffee bar. A new rated glass door will be installed to improve visibility and to better welcome students into the space.
Bid Date: 12/15/2022

Subcontractors (9)

Agronomy Hall-Masonry Repairs-Phase 1
CP number: CP002641
Total Construction Budget: $737,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, provide needed repairs to extend the useful life of the building envelope including tuckpointing, masonry repairs, skylight replacement, sealant replacement, and exterior brick cleaning.
Agronomy Hall-Masonry Repairs-Phase 1
Construction
Scope number: PS01
Construction Budget: $669,016
Begin construction: 05/15/2023
Occupancy / completion: 06/30/2023
Prime contractor: BI STATE MASONRY INC
Project manager: Angela Solberg
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, tuckpointing of exterior masonry, re-caulking of control joints and around windows, cleaning of exterior masonry and windows, and replacement of a metal frame skylight window system.
Bid Date: 12/01/2022

Subcontractors (2)

Agronomy Hall-Room 1102-Remodel
CP number: CP1159336
Total Construction Budget: $103,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, remodeling the existing office space. Work to include asbestos abatement, architectural, electrical, and furniture and carpet replacement.
Agronomy Hall-Room 1102-Remodel
Scope number: PS01
Construction Budget: $103,800
Begin construction: 06/01/2023
Occupancy / completion: 08/15/2023
Gross sq.ft.: 1540
Net sq.ft.: 1540
Project manager: Josef Biechler
Construction manager: Josef Biechler
Contract description of work:
This project includes, but is not limited to, remodeling the existing office space. Work to include asbestos abatement, architectural, electrical, and furniture and carpet replacement.
AM Transmitter Building-KURE Relocation
CP number: CP002715
Total Construction Budget: $140,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, structural evaluation of the existing WOI-AM Tower, modifications to the Am Transmitter Building, relocation of some existing equipment, and purchase of new equipment required to relocate KURE 88.5 from Zaffarano.
AM Transmitter Building-KURE Relocation
Complete
Scope number: PS01
Construction Budget: $40,000
Prime contractor: Multiple Constructors
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, STRUCTURAL EVALUATION OF THE EXISTING WOI-AM TOWER, MODIFICATIONS TO THE AM TRANSMITTER BUILDING, AND RELOCATION OF SOME EXISTING EQUIPMENT AND PURCHASE OF NEW EQUIPMENT REQUIRED TO RELOCATE KURE 88.5 FROM ZAFFARANO.
Bid Date: TBD
Applied Science Complex 1-Room 0222-Remodel
CP number: CP1158811
Total Construction Budget: $57,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel an existing laboratory to accommodate new faculty research. This project includes, but is not limited to architectural, mechanical, electrical and fixed equipment.
Applied Science Complex 1-Room 0222-Remodel
Complete
Scope number: PS01
Construction Budget: $84,000
Begin construction: 06/01/2023
Occupancy / completion: 07/30/2023
Project manager: Josef Biechler
Construction manager: Josef Biechler
Contract description of work:
This project will remodel an existing laboratory to accommodate new faculty research. This project includes, but is not limited to architectural, mechanical, electrical and fixed equipment.
Applied Science Complex 4-Renovation
CP number: CP002734
Total Construction Budget: $296,568
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, new rooftop unit and removal of existing infrared heating system, new dust collection system, new trench drain with sediment trap, relocation of air compressor from AMSL, new electrical transformer and panel for building, new security lighting for building entry, new interior led lighting, and installation of additional outlets and power drops.
Applied Science Complex 4-Renovation
Complete
Scope number: PS02
Construction Budget: $298,400
Begin construction: 10/28/2021
Occupancy / completion: 05/06/2022
Gross sq.ft.: 3969
Prime contractor: HPC LLC
Project manager: Elizabeth Clarke
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, mechanical and electrical upgrades to an existing single story metal building. Mechanical scope includes new unitary heating and cooling equipment and ductwork, new dust collector, and updates to existing building automation system to support new equipment. Electrical scope includes new electrical transformer and panel, new lighting, and new fire alarm panel. Scope of work includes replacement of existing interior doors with rated doors and modifications to existing gypsum walls to meet fire rating requirements.
Bid Date: 10/19/2021

Subcontractors (8)

Armstrong Memorial Research and Demonstration Farm-Machine Storage Building
CP number: CP1164931
Total Construction Budget: $319,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, design and construction of a machine storage building. The building will be approximately 7200 gsf and have metal roofing and siding.
Armstrong Memorial Research and Demonstration Farm-Machine Storage Building
Bid
Scope number: PS01
Construction Budget: $250,000
Occupancy / completion: 02/05/2024
Gross sq.ft.: 7200
Net sq.ft.: 7200
Prime contractor: TBD
Project manager: Mark Huss
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, design and construction of a machine storage building. The building will be approximately 7,200 gsf, will be post frame construction, and will have metal roofing and siding.
Bid Date: 10/24/2023 (Tentative)
Atanasoff Hall-Hallway Improvements
CP number: CP921495
Total Construction Budget: $12,044
includes the bid estimate and contingency for this scope of work
Overall project description of work:
There is a need to provide space for students in the Computer Science Department and from across campus to do homework, create projects, and have a space to connect with the department, other students, and faculty.
Atanasoff Hall-Hallway Improvements
Complete
Scope number: PS01
Construction Budget: $64,800
Prime contractor: Multiple Constructors
Project manager: Leigh Wiand
Construction manager: Leigh Wiand
Contract description of work:
This project will add additional fixed seating, work surfaces, whiteboards, and monitors for student study and collaboration to the first and second floor hallways.
Bid Date: TBD
Atanasoff Hall-Office Space-Improvements
CP number: CP1042019
Total Construction Budget: $52,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will improve seven private offices. The project includes, but is not limited to, paint, carpet with a rubber base, and furniture.
Atanasoff Hall-Office Space-Improvements
Complete
Scope number: PS01
Construction Budget: $72,200
Prime contractor: TBD
Project manager: Leigh Wiand
Construction manager: Leigh Wiand
Contract description of work:
This project will improve seven private offices. The project includes, but is not limited to, paint, carpet with a rubber base, and furniture.
Bid Date: TBD
Barbara E Forker Building-Room 0196-Improvements
CP number: CP1085389
Total Construction Budget: $89,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remove light fixtures, switches and controls from the existing room and install new dimmable LED fixtures, LED color lights, lighting controls, and light switches.
Barbara E Forker Building-Room 0196-Improvements
Complete
Scope number: PS01
Construction Budget: $89,700
Prime contractor: Multiple Constructors
Project manager: Josef Biechler
Construction manager: Josef Biechler
Contract description of work:
This project will remove light fixtures, switches and controls from the existing room and install new dimmable LED fixtures, LED color lights, lighting controls, and light switches.
Bid Date: TBD
Barbara E Forker Building-Room 0287-Remodel
CP number: CP1193418
Total Construction Budget: $10,200
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing space to an open computer lab. This project includes, but is not limited to, architectural, electrical, telecommunications, and furniture.
Barbara E Forker Building-Room 0287-Remodel
Quote
Scope number: PS01
Construction Budget: $12,100
Gross sq.ft.: 1241
Prime contractor: Multiple Constructors
Project manager: Jordan Babler
Construction manager: Jordan Babler
Contract description of work:
This project will remodel the existing space to an open computer lab. This project includes, but is not limited to, architectural, electrical, telecommunications, and furniture.
Bid Date: TBD
Barton and Friley Residence Halls-Fire Escape-Repairs
CP number: CP1118617
Total Construction Budget: $115,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, structural reinforcing and repairs to the existing fire escapes at both the north and south ends of Barton Residence Hall and the existing west fire escape of Friley Residence Hall. At Barton Residence Hall, four doors leading to the fire escapes will be replaced with new fire-rated doors.
Barton and Friley Residence Halls-Fire Escape-Repairs
Scope number: PS01
Construction Budget: $159,000
Begin construction: 06/26/2023
Occupancy / completion: 08/11/2023
Prime contractor: WESTERN SPECIALTY CONTRACTORS
Project manager: Jennifer Evans
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, structural reinforcing and repairs to the existing fire escapes at both the north and south ends of Barton Residence Hall and the existing west fire escape of Friley Residence Hall.

Subcontractors (2)

Barton Residence Hall-Window Replacement
CP number: CP002483
Total Construction Budget: $580,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Project scope as follows: provide abatement and monitoring services, remove and replace windows, remove and replace associated window sealants and replace blinds.
Barton Residence Hall-Window Replacement
On Hold
Scope number: PS01
Construction Budget: $500,000
Begin construction: 03/15/2019
Occupancy / completion: 02/28/2020
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager: Mark Huss
Contract description of work:
The project consists of, but is not limited to, the replacement of approximately 118 windows.
Bid Date: 02/27/2019

Subcontractors (2)

Beardshear Hall-Chilled Water Line Replacement-Phase 2
CP number: CP002646
Total Construction Budget: $242,743
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of the main chilled water lines in the basement, installation of additional gate valves to provide for improved zoning of the chilled water service, preparation for the replacement of the risers and returns for the next phase, and relocation of existing cable trays for better access.
Beardshear Hall-Chilled Water Line Replacement-Phase 2
Construction
Scope number: PS01
Construction Budget: $220,675
Begin construction: 07/24/2023
Occupancy / completion: 02/16/2024
Prime contractor: MANNING SEIVERT MECHANICAL CONTRACTORS INC
Project manager: Mark Grief
Construction manager: Barton Dobson
Contract description of work:
This project includes, but is not limited to, the replacement of the main chilled water lines in the basement, installation of additional gate valves to provide for improved zoning of the chilled water service, preparation for the replacement of the risers and returns for the next phase, and relocation of existing cable trays for better access.
Beardshear Hall-Room 1350-Remodel
CP number: CP1095296
Total Construction Budget: $683,370
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, remodeling the existing office suite and adjacent treasurer's office. The existing conference room will be expanded, individual office spaces will be created, and the interior finishes updated.
Beardshear Hall-Room 1350-Remodel
Construction
Scope number: PS01
Construction Budget: $713,350
Begin construction: 09/11/2023
Occupancy / completion: 01/03/2024
Gross sq.ft.: 4000
Net sq.ft.: 4000
Prime contractor: GREINER CONSTRUCTION INC
Project manager: Hayley Sandholm
Construction manager: Barton Dobson
Contract description of work:
This project includes, but is not limited to, remodeling the existing office suite and adjacent treasurer's office. The existing conference room will be expanded, individual office spaces will be created, and the interior finishes updated.

Subcontractors (11)

Beardshear Hall-Rooms 1550L & 2510-Remodel
CP number: CP947833
Total Construction Budget: $58,950
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing conference rooms to accommodate virtual and hybrid meetings. This project includes, but is not limited to, replacement of electrical power, lighting, mechanical system components, plumbing lines and fixtures, existing furniture, and upgrade audio/visual equipment.
Beardshear Hall-Rooms 1550L & 2510-Remodel
Complete
Scope number: PS01
Construction Budget: $61,150
Prime contractor: Multiple Constructors
Project manager: Jennifer Warrick
Construction manager: Jennifer Warrick
Contract description of work:
This project will remodel the existing conference rooms to accommodate virtual and hybrid meetings. This project includes, but is not limited to, replacement of electrical power, lighting, mechanical system components, plumbing lines and fixtures, existing furniture, and upgrade audio/visual equipment
Bid Date: TBD
Bergstrom Indoor Training Facility-LED Lighting Upgrades
CP number: CP002599
Total Construction Budget: $464,630
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will convert the indoor lighting of Bergstrom indoor practice facility to led. Project will remove the existing lighting and replace with new color changing led lights. This will increase the overall light levels to an average of 70 fc (foot candles).
Bergstrom Indoor Training Facility-LED Lighting Upgrades
Complete
Scope number: PS01
Begin construction: 02/28/2020
Occupancy / completion: 03/31/2020
Prime contractor: Multiple Constructors
Project manager: Jonathan Harvey
Construction manager: John Boehmer
Contract description of work:
THIS PROJECT WILL CONVERT THE INDOOR LIGHTING OF BERGSTROM INDOOR PRACTICE FACILITY TO LED. PROJECT WILL REMOVE THE EXISTING LIGHTING AND REPLACE WITH NEW COLOR CHANGING LED LIGHTS. THIS WILL INCREASE THE OVERALL LIGHT LEVELS TO AN AVERAGE OF 70 FC (FOOT CANDLES).
Bid Date: 10/13/2020
Bessey Hall-Room 0003-Remodel
CP number: CP1007392
Total Construction Budget: $126,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing storage space for the installation of insect rearing chambers. The project includes, but is not limited to, architectural work, mechanical and electrical work, and the purchase of three Pervical insect rearing chambers.
Bessey Hall-Room 0003-Remodel
Complete
Scope number: PS01
Construction Budget: $85,800
Begin construction: 03/20/2023
Occupancy / completion: 03/31/2023
Gross sq.ft.: 1183
Net sq.ft.: 1183
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will remodel the existing storage space for the installation of insect rearing chambers. The project includes, but is not limited to, architectural work, mechanical and electrical work, and the purchase of three pervical insect rearing chambers.
Bid Date: 02/10/2023
Beyer Hall-Elevator 1181 Modernization
CP number: CP002513
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Project scope as follows: new car and corridor fixtures; new door operators and related car and corridor door operating equipment; new cab shell, platform, and interior finishes; new structural components to suite capacity and c1 loading; new code compliant machine room.
Beyer Hall-Elevator 1181 Modernization
Scope number: PS01
Prime contractor: TBD
Project manager: Jonathan Harvey
Construction manager:
Contract description of work:
PROJECT SCOPE IS AS FOLLOWS: NEW CAR AND CORRIDOR FIXTURES; NEW DOOR OPERATORS AND RELATED CAR AND CORRIDOR DOOR OPERATING EQUIPMENT; NEW CAB SHELL, PLATFORM, AND INTERIOR FINISHES; NEW STRUCTURAL COMPONENTS TO SUITE CAPACITY AND C1 LOADING; NEW CODE COMPLIANT MACHINE ROOM.
Bid Date: 02/28/2022
Beyer Hall-Room 2500-Remodel
CP number: CP942796
Total Construction Budget: $224,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, removal of existing partial 5 foot high raised floor, installation of a new 6 foot high raised floor, constructing landing pits deep enough to help prevent injuries, and providing stairs and a ramp to existing doors.
Beyer Hall-Room 2500-Remodel
Bid
Scope number: PS01
Construction Budget: $204,000
Begin construction: 05/25/2023
Occupancy / completion: 09/29/2023
Gross sq.ft.: 1324
Net sq.ft.: 1324
Prime contractor: TBD
Project manager: Jonathan Harvey
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, demolition of partial raised floor; installation of new raised floor, stairs, and ramp; new electrical; and renovation of existing mechanical duct system.
Beyer Hall-Rooms 1312 and 1316-Renovation
CP number: CP002617
Total Construction Budget: $492,670
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will renovate the existing squash courts in rooms 1312 and 1316 in Beyer Hall. The renovation will transform the rooms into recreational spaces to provide a variety of traditional and electronic gaming platforms. This project will provide for approximately 20 e-gaming stations, 12 e-sports gaming stations, and a gaming console area at the first floor. This project will also provide a loft structure for a future project to complete finishes, furniture, and equipment at the loft area for additional gaming opportunities as funds become available.
Beyer Hall-Rooms 1312 and 1316-Renovation
Complete
Scope number: PS01
Construction Budget: $484,989
Begin construction: 11/06/2020
Occupancy / completion: 09/10/2020
Gross sq.ft.: 1945
Net sq.ft.: 1945
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager: David Blum
Construction manager: Darrell Reeves
Contract description of work:
The project consists of, but is not limited to, the demolition of two existing recreational squash court interiors and renovating the existing space into a recreational electronic sports and gaming computer lab.
Bid Date: 02/20/2020

Subcontractors (17)

Beyer Hall-Swimming Pool-Repairs
CP number: CP1088360
Total Construction Budget: $181,742
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement and repairs of the existing heat exchanger, cast iron piping, and associated valves. The swimming pool will also be assessed to determine what repairs or items require replacement in the future.
Beyer Hall-Swimming Pool-Repairs
Construction
Scope number: PS01
Construction Budget: $165,220
Begin construction: 07/10/2023
Occupancy / completion: 08/20/2023
Prime contractor: PLEVA PLUMBING & HEATING INC
Project manager: Mark Grief
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, replacement of existing pool steam-to-water heat exchanger and associated piping and controls. Replacement of several manual isolation valves and pipe couplings. Project must be completed by 6:00 a.m. on August 20, 2023.

Subcontractors (1)

BioCentury Research Farm-AHU1-Modifications
CP number: CP002759
Total Construction Budget: $36,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, modifications to air handler unit 1 (AHU1) serving the main building for the BioCentury Research Farm.
BioCentury Research Farm-AHU1-Modifications
Pre-Design
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager:
Contract description of work:
This project includes, but is not limited to, modifications to air handler unit 1 (AHU1) serving the main building for the BioCentury Research Farm.
Bid Date: TBD
Biocentury Research Farm-Vehicle Dynamometer Facility
CP number: CP002214
Total Construction Budget: $570,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will convert approximately 60% of the space in an existing pre-engineered steel building currently used for storage on the Biocentury Research Farm. The space will be remodeled to include all of the features planned at the previous location.
Biocentury Research Farm-Vehicle Dynamometer Facility-Concrete
Complete
Biocentury Research Farm-Vehicle Dynamometer Facility-Electrical Improvements
Post Construction
Biocentury Research Farm-Vehicle Dynamometer Facility-Interior Remodeling
Complete
Birch, Welch, and Roberts Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
CP number: CP1001532
Total Construction Budget: $50,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of a new sub-drain along the south exterior wall of Welch Hall and the west exterior wall of Birch Hall within the south courtyard, which will be connected to a new area intake. There will be an additional storm pipe connecting the new intake to an existing manhole. On the west side of the courtyard, the area of an existing intake will be regraded and the intake itself removed and replaced at a lower elevation to help move water away from the sidewalk. Additional work to include tree trimming and removal and the site grading for improved drainage.
Birch, Welch, and Roberts Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
Bid
Scope number: PS01
Construction Budget: $46,000
Begin construction: 05/22/2023
Occupancy / completion: 07/28/2023
Prime contractor: TBD
Project manager: Jennifer Evans
Construction manager: John Boehmer
Contract description of work:
This project includes, but is not limited, to installation of new sub drain along the south exterior wall of Welch Hall and west exterior wall of Birch Hall, within the south courtyard. This new sub drain will be connected to a new area intake. There will be additional storm pipe connecting the new intake to an existing manhole. On the west side of the courtyard, the area of an existing intake will be regraded, the intake itself removed and replaced at a lower elevation to help move water away from the sidewalk. The entire site will be regraded for improved drainage.
Black Engineering-Emergency Power Transfer Switch-Replacement
CP number: CP002649
Total Construction Budget: $263,320
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will install one or more new emergency and standby power transfer switches, associated cabling, and new electrical distribution equipment to replace the existing transfer switch and existing electrical distribution equipment in their current location in the basement main electrical room of Black Engineering.
Black Engineering-Emergency Power Transfer Switch-Replacement
Design-DD
Scope number: PS01
Construction Budget: $269,320
Begin construction: 05/31/2024
Prime contractor: TBD
Project manager: David Blum
Construction manager:
Contract description of work:
This project will install one or more new emergency and standby power transfer switches, associated cabling, and new electrical distribution equipment to replace the existing transfer switch and existing electrical distribution equipment in their current location in the basement main electrical room of Black Engineering.
Bid Date: TBD
Buchanan Residence Hall-Water Service Piping-Replacement
CP number: CP1094910
Total Construction Budget: $112,550
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of the existing water main and related components serving Buchanan Residence Hall from the PIV to the building. An emergency repair of the main in January 2023 replaced the water main from the city main to the PIV.
Buchanan Residence Hall-Water Service Piping-Replacement
Complete
Scope number: PS01
Construction Budget: $97,864
Begin construction: 06/01/2023
Occupancy / completion: 07/21/2023
Prime contractor: MAINLINE CONSTRUCTION INC
Project manager: David Blum
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, new 8 inch Ductile Iron water pipe, remove abandoned utilities, remove and replace PCC sidewalk, and grading with topsoil.
Carver Hall-Fire System Standpipes-Improvements
CP number: CP917640
Total Construction Budget: $536,930
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of four Class 1 fire system standpipes to serve the building, a new fire hydrant, and a new fire department connection on the east side of the building. The northwest standpipe will have tamper switch valves for a future sprinkler system.
Carver Hall-Fire System Standpipes-Improvements
Construction
Scope number: PS01
Construction Budget: $494,927
Begin construction: 12/04/2023
Occupancy / completion: 05/31/2024
Gross sq.ft.: 133500
Net sq.ft.: 133500
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager: Hayley Sandholm
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, the installation of four Class 1 fire system standpipes to serve the building, a new fire hydrant, and a new fire department connection on the east side of the building. The northwest standpipe will have tamper switch valves for a future sprinkler system.

Subcontractors (3)

Carver Hall-Room 0208-Remodel
CP number: CP1164561
Total Construction Budget: $42,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing office space assigned to the College of Liberal Arts and Sciences (LAS) into a student service center. This project includes, but is not limited to, architectural, mechanical, electrical, and furniture installation.
Carver Hall-Room 0208-Remodel
Construction
Scope number: PS01
Construction Budget: $45,200
Gross sq.ft.: 1490
Net sq.ft.: 1490
Prime contractor: Multiple Constructors
Project manager: Jennifer Warrick
Construction manager: Jennifer Warrick
Contract description of work:
This project will remodel the existing office space assigned to the College of Liberal Arts and Sciences (LAS) into a student service center. This project includes, but is not limited to, architectural, mechanical, electrical, and furniture installation.
Bid Date: TBD
College of Design-Rooms 0452 & 0458-Furniture Replacement
CP number: CP1191484
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of landscape architecture studio furniture in rooms 0452 and 0458. Included in the replacement will be 38 butcher block adjustable tables and chairs and 8 power hubs. Work to include architecture, furniture, and electrical.
College of Design-Rooms 0452 & 0458-Furniture Replacement
Quote
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
This project includes, but is not limited to, the replacement of landscape architecture studio furniture in rooms 0452 and 0458. Included in the replacement will be 38 butcher block adjustable tables and chairs and 8 power hubs. Work to include architecture, furniture, and electrical.
Bid Date: TBD
College of Design-Window Replacement
CP number: CP002720
Total Construction Budget: $2,197,960
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, exterior window replacement, exterior concrete panel exterior cleaning, exterior concrete joint sealant replacement, and interior wall and finish repairs.
College of Design-Window Replacement
Scope number: PS01
Construction Budget: $2,354,000
Begin construction: 11/01/2021
Occupancy / completion: 04/17/2023
Prime contractor: WILSON GROUP INC
Project manager: David Blum
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, cleaning the existing exterior concrete building surface, removing and replacing existing sealant joints at exterior concrete walls, removing and replacing existing ribbon window units, and replacing identified damaged interior wall assembly and finishes.
Bid Date: 10/28/2021

Subcontractors (5)

Curtiss Farm-Feed Mill and Grain Science Complex
CP number: CP002509
Total Construction Budget: $23,350,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project is constructing a feed mill and grain science facility with all associated site work, site utilities, grain storage, and feed processing equipment. The project also includes educational and warehouse space. This facility will replace three existing, outdated feed mills. The complex will help address significant needs of the Iowa agricultural industry. There is a shortfall of skilled employees for grain and feed facilities, which this complex will help address with new educational programs, as well as research and extension programs. This complex will enhance education and research, while concurrently providing the custom, diverse feeds required for university livestock. The project is located on the university Curtiss Farm, south of US Highway 30 in Ames.
Curtiss Farm-Feed Mill and Grain Science Complex
Construction
Curtiss Farm-Feed Mill and Grain Science Complex-Grain Center Control Building-Build-Out
Curtiss Farm-Feed Mill and Grain Science Complex-Sanitary Sewer Extension
Construction
Curtiss Hall-Exterior Masonry Repair
CP number: CP002623
Total Construction Budget: $423,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will focus on renewing the exterior of Curtiss Hall. Work includes, but is not limited to, limestone masonry repair or replacement of cracked and deteriorated stone, tuck-pointing, sealant replacement, and masonry and stone cleaning.
Curtiss Hall-Exterior Masonry Repair
Scope number: PS01
Construction Budget: $330,000
Begin construction: 05/15/2023
Occupancy / completion: 08/08/2023
Prime contractor: AJWD
Project manager: Angela Solberg
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, stone repair, stone mortar repointing, joint sealant replacement and masonry cleaning.
Bid Date: 08/30/2022
Cyclone Sports Complex-Soccer Field-Replacement
CP number: CP905958
Total Construction Budget: $1,250,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remove the existing soccer field synthetic turf system, regrade, install irrigation and drainage and subgrade for natural turf, grow new turf, cut and sod the soccer field. Drainage improvements on the existing natural turf soccer practice field will be completed as well.
Cyclone Sports Complex-Soccer Field-Replacement
Construction
Cyclone Sports Complex-Soccer Field-Replacement-Practice Field Drainage Improvements
Complete
CYTown-Parking and Infrastructure Improvements
CP number: CP1004288
Total Construction Budget: $22,770,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, construction of replacement parking with new lighting and installation of underground infrastructure, which would include new water, power, gas, telecommunications, storm sewer, and sanitary lines to support future development. The project would also relocate the CyRide Transit Hub and raise a portion of the site above 100-year flood plain of Ioway Creek.
CYTown-Parking and Infrastructure Improvements
Construction
CYTown-Parking and Infrastructure-Phase 2
Dairy Farm-Cow Bedding System Conversion
CP number: CP917722
Total Construction Budget: $275,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, facility modifications and equipment to convert the existing lactating cow-free stall barn bedding from a compost deep bedding and mattress system to a sand bedding system. This will include the removal of the existing concrete and new concrete to allow for the sand system and modifications to the settling tank. New equipment will include a vacuum truck to collect the manure and sand-laden material and deliver it to new sand separation equipment.
Dairy Farm-Cow Bedding System Conversion
Complete
Scope number: PS01
Construction Budget: $164,300
Begin construction: 09/19/2022
Occupancy / completion: 12/19/2022
Prime contractor: WOODRUFF CONSTRUCTION INC
Project manager: Mark Huss
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, the materials and labor to remove the concrete in the lactating cow free stall pens and replacing with new concrete designed for the use of sand bedding.
Bid Date: 08/23/2022
Department of Residence-Elevator Safety Improvements FY18
CP number: CP002469
Total Construction Budget: $495,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT CONSISTS OF REPLACING AND ADDING SAFETY EQUIPMENT TO TWO ELEVATORS LOCATED IN MAPLE RESIDENCE HALL AND ONE IN MAPLE-WILLOW-LARCH COMMONS. THE AREAS OF WORK WILL INCLUDE FIRE RECALL, REPLACEMENT OF OBSOLETE PARTS, AND UPGRADES OF EQUIPMENT.
Department of Residence-Elevator Safety Improvements FY18
Construction
Scope number: PS01
Occupancy / completion: 08/31/2022
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager: Mark Huss
Contract description of work:
THIS PROJECT CONSISTS OF REPLACING AND ADDING SAFETY EQUIPMENT TO TWO ELEVATORS LOCATED IN MAPLE RESIDENCE HALL AND ONE IN MAPLE-WILLOW-LARCH COMMONS. THE AREAS OF WORK WILL INCLUDE FIRE RECALL, REPLACEMENT OF OBSOLETE PARTS, AND UPGRADES OF EQUIPMENT.
Bid Date: TBD
DESIGN-R0125-272542-Lactation Room & Gender Neutral Bathroom
CP number: PR1160783
Total Construction Budget: $63,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
We would like to investigate converting the men's restroom on the first floor into a lactation space and the women's bathroom (R0175) into a family/gender neutral bathroom.
College of Design-Rooms R0125 & R0175-Remodel
Bid
Scope number: PS01
Construction Budget: $63,400
Occupancy / completion: 01/08/2024
Prime contractor: TBD
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
This project will remodel existing restroom R0125 into a lactation room and restroom R0175 into a family/gender neutral restroom.
Durham Center-Clean Agent Fire Suppression System-Improvements
CP number: CP907055
Total Construction Budget: $692,694
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will install a new clean agent, waterless fire suppression system that includes, but is not limited to, a new chemical agent fire suppression system, a very early smoke detection system, integration of system controls into the existing fire alarm system, sealing of room envelope penetrations and new fire-smoke dampers in ventilation ducts.
Durham Center-Clean Agent Fire Suppression System-Improvements
Scope number: PS01
Construction Budget: $692,694
Begin construction: 01/31/2022
Occupancy / completion: 01/15/2023
Gross sq.ft.: 7646
Net sq.ft.: 7646
Prime contractor: WOODRUFF CONSTRUCTION INC
Project manager: Mark Grief
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, installation of new clean agent fire suppression system to serve data center space. Project also includes limited modifications to double-interlock pre-action system serving space, installation of combination fire/smoke dampers in ductwork serving space, limited architectural modifications, etc. All work associated with fire alarm systems shall be included as part of Bid Alternate #2 or Bid Alternate #3. Refer to Bid Alternate descriptions and documents for additional information.
Bid Date: 01/27/2022

Subcontractors (5)

East of University Boulevard Site Improvements-Recreation Services
CP number: CP002439
Total Construction Budget: $7,506,320
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL RENOVATE THE EXISTING SOUTHEAST RECREATION COMPLEX LOCATED EAST OF UNIVERSITY BOULEVARD BETWEEN SOUTH 4TH AND SOUTH 16TH STREETS. THIS RENOVATION OF THE EXISTING COMPLEX WILL ILLUMINATE THE PLAYING FIELDS TO LIGHTING LEVELS RECOMMENDED FOR SPORT CLUBS AND AMATEUR FACILITIES, PROVIDE IRRIGATION, IMPROVE FIELD DRAINAGE, PLAYING SURFACE DURABILITY, AND MAINTAINABILITY.
East of University Boulevard Site Improvements-Recreation Services
Complete
East of University Boulevard Site Improvements-Recreation Services-Field Lighting
Complete
East of University Boulevard Site Improvements-Recreation Services-Foot Wash
Design-CD
EHSSB-Interior Improvements
CP number: CP1088271
Total Construction Budget: $302,680
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, architectural, electrical, and interior design work required to replace the existing raised floor system. The existing system furniture will be removed, prior to the new raised floor installation, and reinstalled at completion. New carpet tiles and floor base will also be installed.
EHSSB-Interior Improvements
Construction
Scope number: PS01
Construction Budget: $275,160
Begin construction: 05/29/2023
Occupancy / completion: 10/01/2023
Gross sq.ft.: 9920
Net sq.ft.: 9920
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager: Jennifer Evans
Construction manager: John Boehmer
Contract description of work:
This project includes, but is not limited to, architectural, electrical, and interior design work required to replace the existing raised floor system. The existing system furniture will be removed, prior to the new raised floor installation, and reinstalled at completion. New carpet tiles and floor base will also be installed.

Subcontractors (2)

Family Resource Center-Remodel
CP number: CP1008443
Total Construction Budget: $253,300
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of heating and cooling units, removal of vinyl floor tile and replace with new flooring, removal of plastic laminate countertops and replacement with solid surface countertops, replace damaged base cabinet doors, modification of kitchen cabinets for a new oven range and hood, installation of a garbage disposal, replacement of fiberglass reinforced panels in room 1053, refinishing wood windowsills, painting rooms, repairs to EIFS and miscellaneous masonry damage, cleaning the exterior, and replacement of exterior sealant joints.
Family Resource Center-Remodel
Scope number: PS01
Construction Budget: $79,500
Begin construction: 09/08/2023
Occupancy / completion: 08/23/2023
Prime contractor: STEIN HEATING & COOLING INC
Project manager: Elizabeth Clarke
Construction manager: Mick McBride
Contract description of work:
This project includes, but is not limited to, the replacement of heating and cooling units.
Farm House Lane-Reconstruction
CP number: CP002663
Total Construction Budget: $533,180
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL RECONSTRUCT AND WIDEN A PORTION OF FARM HOUSE LANE BETWEEN LOT 43 AND LOT 49. WORK WILL INCLUDE, BUT IS NOT LIMITED TO: SUBGRADE IMPROVEMENTS, ROADWAY RECONSTRUCTION AND WIDENING TO 21 FEET, BIKE PARKING, UTILITY WORK AS NECESSARY, AND UPGRADE STREET LIGHTING TO CAMPUS STANDARD .
Farm House Lane-Reconstruction
Scope number: PS03
Construction Budget: $533,180
Begin construction: 02/07/2022
Occupancy / completion: 08/22/2022
Prime contractor: CALIBER CONCRETE LLC
Project manager: Angela Solberg
Construction manager: John Boehmer
Contract description of work:
The project consists of, but is not limited to, reconstruction and widening of Farm House Lane from Parking Lot 49 to Troxel Hall, storm sewer, lighting, bike parking and concrete sidewalks.
Bid Date: 02/03/2022

Subcontractors (3)

Forestry Greenhouse-Demolition
CP number: CP1001237
Total Construction Budget: $172,645
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the abatement of all asbestos containing pipe fitting insulation, glazing/glazing compound, transite wall paneling, and all associated sealants. The entire greenhouse and selected site facilities will be demolished. The site will be restored by grading and seeding.
Forestry Greenhouse-Demolition
Complete
Scope number: PS01
Construction Budget: $149,750
Begin construction: 04/17/2023
Occupancy / completion: 05/31/2023
Gross sq.ft.: 12461
Net sq.ft.: 12461
Prime contractor: LINNCO INC
Project manager: Jennifer Evans
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, demolition of the remaining Greenhouse structure and selected site facilities. Final site to be restored including grading and seeding. The abatement of all asbestos containing pipe-fitting insulation, glazing/glazing compound, transite wall paneling, and all associated sealants will be complete prior to building demolition.
Bid Date: 12/20/2022

Subcontractors (1)

Frederiksen Court-Building 31-Fire Alarm System Upgrade
CP number: CP986875
Total Construction Budget: $374,620
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, fire alarm system upgrade including replacement of panel and all wiring according to DoR standards, and replacement of the apartment devices with addressable devices.
Frederiksen Court-Building 31-Fire Alarm System Upgrade
Post Construction
Scope number: PS01
Construction Budget: $340,560
Begin construction: 05/15/2023
Occupancy / completion: 07/28/2023
Gross sq.ft.: 19662
Net sq.ft.: 19662
Prime contractor: COMMONWEALTH ELECTRIC
Project manager: Mark Grief
Construction manager: Danelda Allen
Contract description of work:
The project consists of, but is not limited to, fire alarm system upgrade including replacement of panel and all wiring according to Department of Residence standards and replacement of the apartment devices with addressable devices.

Subcontractors (2)

Frederiksen Court-Buildings 13, 21, 22, and 23-Sprinkler Replacement
CP number: CP1162170
Total Construction Budget: $385,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of the sprinkler heads in Frederiksen Court Buildings 13, 21, 22, and 23.
Frederiksen Court-Buildings 13, 21, 22, and 23-Sprinkler Replacement
Construction
Scope number: PS01
Construction Budget: $385,000
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager:
Contract description of work:
This project includes, but is not limited to, the replacement of the sprinkler heads in Frederiksen Court Buildings 13, 21, 22, and 23.
Bid Date: TBD
Friley Residence Hall-Bathroom Improvements
CP number: CP002724
Total Construction Budget: $13,900,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL REMODEL THE BATHROOMS IN FRILEY RESIDENCE HALL, CONVERTING THEM TO PRIVATE, MORE ACCESSIBLE SPACES. THE WORK WILL ALSO INCLUDE MECHANICAL, ELECTRICAL AND PLUMBING SYSTEMS ALONG WITH INTERIOR FINISHES.THIS PROJECT WILL BE COMPLETED IN PHASES OVER THE NEXT FOUR CONSECUTIVE SUMMERS.
Friley Residence Hall-Bathroom Improvements-Locations 7 & 8
Construction
Friley Residence Hall-Bathroom Improvements-Stack A
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack B
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack C
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack D
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack E & Stack F
Bid
Friley Residence Hall-Bathroom Improvements-Stack G
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack H
Design-CD
Friley Residence Hall-Courtyard Roof-Improvements
CP number: CP1000679
Total Construction Budget: $1,023,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The Friley Residence Hall courtyard area is both an outdoor seating area and a structural roof over food service and dining areas below the courtyard. The courtyard consists of a concrete deck, which is now deteriorated. This project includes, but is not limited to, repairs to the deck and the installation of a new protective waterproof membrane. A new pedestal mounted paver system will be installed over the membrane to provide a courtyard walking surface.
Friley Residence Hall-Courtyard Roof-Improvements
Design-DD
Scope number: PS01
Construction Budget: $1,023,000
Prime contractor: TBD
Project manager: Angela Solberg
Construction manager:
Contract description of work:
The Friley Residence Hall courtyard area is both an outdoor seating area and a structural roof over food service and dining areas below the courtyard. The courtyard consists of a concrete deck, which is now deteriorated. This project includes, but is not limited to, repairs to the deck and the installation of a new protective waterproof membrane. A new pedestal mounted paver system will be installed over the membrane to provide a courtyard walking surface.
Bid Date: TBD
Friley Residence Hall-Roof Replacement
CP number: CP002538
Total Construction Budget: $3,992,170
includes the bid estimate and contingency for this scope of work
Overall project description of work:
REPLACEMENT OF ROOF INCLUDING: REPLACE SLATE ROOF WITH ARCHITECTURAL ASPHALT SHINGLES, REPAIR OR REPLACE ROOF DORMERS AND DORMER WINDOWS, REPLACE GUTTERS, AND PROVIDE ABATEMENT OF HAZARDOUS MATERIALS AS REQUIRED.
Friley Residence Hall-Roof Replacement
Post Construction
Friley Residence Hall-Roof Replacement-Dock Roof
Construction
Gilman Hall-Accessible Restroom Improvements
CP number: CP002672
Total Construction Budget: $380,172
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, improved access to restrooms in Gilman Hall.
Gilman Hall-Accessible Restroom Improvements
Complete
Scope number: PS01
Construction Budget: $397,230
Begin construction: 09/26/2022
Occupancy / completion: 03/18/2023
Gross sq.ft.: 495
Net sq.ft.: 495
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager: Mark Grief
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, the renovation of existing space on level 1 in Gilman Hall into a new mens restroom including plumbing improvements, electrical improvements and the installation of new lighting.
Bid Date: 07/14/2022

Subcontractors (9)

Gilman Hall-Electrical Panel Replacement-Phase 2
CP number: CP002651
Total Construction Budget: $485,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will replace outdated electrical panels in Gilman Hall with serviceable fully supported equipment and install new electrical distribution equipment and feeders. This project will also begin to remove and replace electrical equipment feeder sources that cross between original Gilman Hall and 1964 Gilman Addition.
Gilman Hall-Electrical Panel Replacement-Phase 2
Design-DD
Scope number: PS01
Construction Budget: $485,700
Begin construction: 05/31/2024
Occupancy / completion: 08/30/2024
Prime contractor: TBD
Project manager: David Blum
Construction manager:
Contract description of work:
The project will replace outdated electrical panels in Gilman Hall with serviceable fully supported equipment and install new electrical distribution equipment and feeders. This project will also begin to remove and replace electrical equipment feeder sources that cross between original Gilman Hall and 1964 Gilman Addition.
Bid Date: TBD
Gilman Hall-Wayfinding and Signage-Improvements
CP number: CP1010532
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to evaluation of existing building signage to determine exact quantity, correct numbering and notable space labeling for installation of new room signage. At applicable locations, existing room signage will be removed and wall surfaces will be patched and repaired ready for installation of new, accessible room signage.
Gilman Hall-Wayfinding and Signage-Improvements
On Hold
Scope number: PS01
Construction Budget: $208,000
Prime contractor: Multiple Constructors
Project manager: Jennifer Evans
Construction manager: Jennifer Evans
Contract description of work:
This project includes, but is not limited to evaluation of existing building signage to determine exact quantity, correct numbering and notable space labeling for installation of new room signage. At applicable locations, existing room signage will be removed and wall surfaces will be patched and repaired ready for installation of new, accessible room signage.
Bid Date: TBD
Heady Hall-Room 0368A-Remodel
CP number: CP1166397
Total Construction Budget: $64,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing conference room. This project includes, but is not limited, to architectural, mechanical, and electrical work, and furniture installation.
Heady Hall-Room 0368A-Remodel
Construction
Scope number: PS01
Construction Budget: $64,700
Begin construction: 12/18/2023
Occupancy / completion: 01/12/2024
Gross sq.ft.: 1270
Net sq.ft.: 1270
Project manager: Jennifer Warrick
Construction manager: Jennifer Warrick
Contract description of work:
This project will remodel the existing conference room. This project includes, but is not limited, to architectural, mechanical, and electrical work, and furniture installation.
Heady Hall-Rooms 0178, 0180, 0180A, and 0180B-Remodel
CP number: CP1004872
Total Construction Budget: $62,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing spaces to create a graduate student lounge. The project includes, but is not limited to, architectural, mechanical, and electrical work, a new audio-visual system, and carpet and furniture installation.
Heady Hall-Rooms 0178, 0180, 0180A, and 0180B-Remodel
Complete
Scope number: PS01
Construction Budget: $62,400
Occupancy / completion: 09/30/2022
Project manager: Jennifer Warrick
Construction manager: Jennifer Warrick
Contract description of work:
This project will remodel the existing spaces to create a graduate student lounge. The project includes, but is not limited to, architectural, mechanical, and electrical work, a new audio-visual system, and carpet and furniture installation.
Bid Date: 07/06/2022
Helser Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
CP number: CP1001574
Total Construction Budget: $82,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, exterior regrading, waterproofing, and sidewalk repair on the northwest corner of Helser Residence Hall between Helser and Eaton Hall. This will include some interior wall repairs. Smaller areas around the building will have regrading and sidewalk repair completed.
Helser Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
Bid
Scope number: PS01
Construction Budget: $75,000
Begin construction: 05/22/2023
Occupancy / completion: 07/28/2023
Prime contractor: TBD
Project manager: Jennifer Evans
Construction manager: John Boehmer
Contract description of work:
This project includes, but is not limited to, installation of additional area drains and new storm pipe to help divert water away from the north west entrance door of Helser Hall and lower level window wells along the north side of the building. A portion of an existing sidewalk will be removed and replaced to meet ADA slope requirements and to prevent water from ponding. Rock bed will be used for erosion protection and to keep water from collecting against face of the building. The area of Work will be regraded for overall improved
Helser Residence Hall-Laundry Improvements
CP number: CP1001298
Total Construction Budget: $775,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, relocation of the laundry facilities from the basement to the first floor and the construction of four new individual bathrooms in the location of two existing offices and one existing restroom of Helser Residence Hall.
Helser Residence Hall-Laundry Improvements
Scope number: PS01
Construction Budget: $404,990
Begin construction: 11/01/2022
Occupancy / completion: 05/25/2023
Gross sq.ft.: 550
Net sq.ft.: 550
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager: Angela Solberg
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, remodel of an existing first floor bathroom into new resident laundry area. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Bid Date: 10/04/2022

Subcontractors (10)

Hilton Coliseum-Rooms 0176, 0176A, 0188, and 0188A-Renovation
CP number: CP964884
Total Construction Budget: $737,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to new lockers, new flooring, new wall finishes, new ceilings and lighting, demolition and new stud wall construction, and updated graphics.
Hilton Coliseum-Rooms 0176, 0176A, 0188, and 0188A-Renovation
Construction
Scope number: PS01
Construction Budget: $737,330
Begin construction: 05/15/2023
Occupancy / completion: 10/06/2023
Gross sq.ft.: 3280
Net sq.ft.: 2740
Prime contractor: NEUMANN BROTHERS INC
Project manager: Jonathan Harvey
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, demolition of existing finishes and walls; installation of new stud walls, flooring, finishes, and ceilings; new lighting; and modifications to existing mechanical system.

Subcontractors (8)

Horticulture Research Station-AVES Building
CP number: CP002762
Total Construction Budget: $275,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
General Description of Project This project includes, but is not limited to, the design, materials, and construction of a new building for Aviary and Vertebrate Education and Research on the Horticulture Research Station. The project includes, but is not limited to, the materials and labor to construct a wood-frame building with metal siding and roofing of approximately 2240 gsf. The building will have concrete foundations and a partial concrete floor. The building will include spaces for aviary research.
Horticulture Research Station-AVES Building
Post Construction
Scope number: PS01
Construction Budget: $251,570
Begin construction: 07/13/2022
Occupancy / completion: 09/20/2022
Gross sq.ft.: 2240
Net sq.ft.: 2240
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager: Mark Huss
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, the materials and labor to construct a wood frame building with metal siding and roofing. The building will be approximately 2240 square feet. The project will include site work and footings excavation. The building will have concrete foundations, a partial concrete floor, metal exterior doors and frames, and eight interior metal doors and frames.
Bid Date: 06/21/2022

Subcontractors (2)

Horticulture Research Station-Machine Storage Building
CP number: CP1053242
Total Construction Budget: $143,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the design and construction of a 6000 square feet post frame storage building. The building will be uninsulated and not heated. The building will have a concrete floor, a metal roof, and metal siding.
Horticulture Research Station-Machine Storage Building
Design-CD
Scope number: PS01
Construction Budget: $143,000
Prime contractor: TBD
Project manager: Mark Huss
Construction manager: Mick McBride
Contract description of work:
This project includes, but is not limited to, the design and construction of a 6000 square feet post frame storage building. The building will be uninsulated and not heated. The building will have a concrete floor, a metal roof, and metal siding.
Bid Date: TBD
Howe Hall-Room 2622-Remodel
CP number: CP1146403
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the remodeling of the existing office space to collocate staff of the Center for Excellence in Learning and Teaching in Howe Hall. Work will include architectural, mechanical, and electrical work, and fixed equipment and furniture.
Howe Hall-Room 2622-Remodel
Complete
Scope number: PS01
Construction Budget: $91,400
Begin construction: 05/01/2023
Occupancy / completion: 05/26/2023
Gross sq.ft.: 1670
Net sq.ft.: 1670
Project manager: Leigh Wiand
Construction manager: Leigh Wiand
Contract description of work:
This project includes, but is not limited to, the remodeling of the existing office space to collocate staff of the Center for Excellence in Learning and Teaching in Howe Hall. Work will include architectural, mechanical, and electrical work, and fixed equipment and furniture.
Howe Hall-Room 2624-Remodel
CP number: CP1091732
Total Construction Budget: $90,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project includes, but is not limited to the remodel of the existing office space including architectural, mechanical, electrical and furniture installation.
Howe Hall-Room 2624-Remodel
Complete
Scope number: PS01
Construction Budget: $90,000
Occupancy / completion: 01/17/2023
Gross sq.ft.: 5328
Net sq.ft.: 5328
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
The project includes, but is not limited to the remodel of the existing office space including architectural, mechanical, electrical and furniture installation.
Bid Date: 11/18/2022
Howe Hall-Rooms 2624 and 2624D-H-Remodel
CP number: CP1159890
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing office space. This project includes, but is not limited to, architectural, mechanical, and electrical work, and new furniture.
Howe Hall-Rooms 2624 and 2624D-H-Remodel
Scope number: PS01
Construction Budget: $92,200
Begin construction: 06/01/2023
Occupancy / completion: 07/07/2023
Gross sq.ft.: 1670
Net sq.ft.: 1670
Project manager: Leigh Wiand
Construction manager: Leigh Wiand
Contract description of work:
This is a university approved project with a budget of $187,750. The project will renovate several existing offices to consolidate the Center for Excellence in Learning and Teaching (CELT) into one location on campus. CELT staff support university faculty with a growing emphasis in on-line instruction. The summer is the least disruptive time to accomplish this work in Howe Hall and then relocate the CELT staff.
Human Nutritional Sciences Building-Research Labs-Remodel
CP number: CP1015970
Total Construction Budget: $1,650,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel existing teaching laboratory spaces in the Human Nutritional Sciences Building to accommodate textile science research laboratories relocating from LeBaron Hall. Work will consist of interior demolition and construction of new walls, casework, fume hoods, and finishes. The mechanical and electrical systems will also be updated to support the remodeled laboratories. An existing environmental chamber and 3-D body scanner will be relocated to the new laboratories.
Human Nutritional Sciences Building-Research Labs-Remodel
Construction
Scope number: PS01
Construction Budget: $1,457,474
Begin construction: 08/01/2023
Occupancy / completion: 03/18/2024
Gross sq.ft.: 2677
Net sq.ft.: 2399
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager: Elizabeth Clarke
Construction manager: Darrell Reeves
Contract description of work:
The project consists of, but is not limited to, remodel of existing teaching laboratory space to accommodate textile science research laboratories. Work includes demolition of interior space including existing walls, casework, equipment, and finishes. New work includes, but is not limited to, new walls, casework, fume hoods, doors, finishes, and infill of existing wall openings and roof patching to accommodate new mechanical rooftop equipment. Mechanical scope includes new supply and exhaust ductwork, new building automation controls, and new plumbing to support lab equipment in the space. Electrical scope incudes a new panel, new power services to support lab equipment, new lighting, and new fire alarm devices. Fire protection scope includes removal and re-installation of sprinkler piping and heads in the space.

Subcontractors (10)

Information Technology Services-Animal Science Teaching Farms-Fiber Expansion
CP number: CP1170264
Total Construction Budget: $164,650
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of conduit, ground boxes, and a vault for the future expansion of ISUs data network to the Animal Science Research Farms.
Information Technology Services-Animal Science Teaching Farms-Fiber Expansion
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Travis Van Dyke
Construction manager: Travis Van Dyke
Contract description of work:
This project includes, but is not limited to, the installation of conduit, ground boxes, and a vault for the future expansion of ISUs data network to the Animal Science Research Farms
Bid Date: TBD
Information Technology Services-Central Campus-Fiber and Wireless Expansion
CP number: CP1118671
Total Construction Budget: $126,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of conduit, vaults, and ground boxes for future fiber and wireless internet expansion of central campus.
Information Technology Services-Central Campus-Fiber and Wireless Expansion
Pre-Design
Scope number: PS01
Construction Budget: $133,000
Prime contractor: Iowa State University
Project manager: Caleb Barduson
Construction manager: Caleb Barduson
Contract description of work:
This project includes, but is not limited to, the installation of conduit, vaults, and ground boxes for future fiber and wireless internet expansion of central campus.
Bid Date: TBD
Institutional Roads 2023-Pavement Preservation
CP number: CP1160447
Total Construction Budget: $236,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Planned work includes, but is not limited to, asphalt and concrete road patching in several locations across campus.
Institutional Roads 2023-Pavement Preservation
Design-CD
Scope number: PS01
Construction Budget: $236,500
Prime contractor: TBD
Project manager: Angela Solberg
Construction manager:
Contract description of work:
Planned work includes, but is not limited to, asphalt and concrete road patching in several locations across campus.
Bid Date: TBD
Institutional Roads 2023-State Avenue and Mortensen Road-Traffic Signal Installation
CP number: CP1168159
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of a permanent traffic signal at the intersection of State Avenue and Mortensen Road in partnership with the City of Ames.
Institutional Roads 2023-State Avenue and Mortensen Road-Traffic Signal Installation
Design-CD
Scope number: PS01
Construction Budget: $180,000
Prime contractor: Multiple Constructors
Project manager: Angela Solberg
Construction manager:
Contract description of work:
This project includes, but is not limited to, the installation of a permanent traffic signal at the intersection of State Avenue and Mortensen Road in partnership with the City of Ames.
Bid Date: TBD
Institutional Roads 2024-Scholl Road-Reconstruction
CP number: CP1168167
Total Construction Budget: $737,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Scholl Road is owned by the university and provides access to the Applied Science complex northwest of the main campus. This project includes, but is not limited to, the reconstruction of the southern portion of Scholl Road, from Ontario Street to north of the railroad tracks, including drainage improvements and sidewalks. The project is included in the Institutional Road program funded by the Iowa Department of Transportation.
Institutional Roads 2024-Scholl Road-Reconstruction
Design-DD
Scope number: PS01
Construction Budget: $737,000
Prime contractor: TBD
Project manager: Angela Solberg
Construction manager:
Contract description of work:
Scholl Road is owned by the university and provides access to the Applied Science complex northwest of the main campus. This project includes, but is not limited to, the reconstruction of the southern portion of Scholl Road, from Ontario Street to north of the railroad tracks, including drainage improvements and sidewalks. The project is included in the Institutional Road program funded by the Iowa Department of Transportation.
Bid Date: TBD
Iowa School for the Deaf-Long Hall High School-Upgrades
CP number: CP002648
Total Construction Budget: $4,293,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will address deferred maintenance issues and provide the necessary upgrades. The revised budget includes painting and carpet in all classrooms and offices, new roller shades on all windows, sheetrock, life safety, upgraded lighting, mechanical, and electrical work.
Iowa School for the Deaf-Long Hall High School-Upgrades
Complete
Scope number: PS01
Construction Budget: $4,172,500
Begin construction: 06/23/2021
Occupancy / completion: 07/29/2022
Prime contractor: DOWNS ELECTRIC INC
Project manager: Jonathan Harvey
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, removal and replacement of existing exterior windows; miscellaneous exterior masonry repair; mechanical, electrical, and life safety upgrades; and new floor and ceiling finishes.
Bid Date: 06/17/2021

Subcontractors (7)

Iowa School for the Deaf-Pool Dehumidification System-Replacement
CP number: CP002723
Total Construction Budget: $424,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, REPLACEMENT OF THE EXISTING POOL DEHUMIDIFICATION SYSTEM.
Iowa School for the Deaf-Pool Dehumidification System-Replacement
Complete
Scope number: PS01
Construction Budget: $405,300
Begin construction: 03/18/2021
Occupancy / completion: 09/24/2021
Prime contractor: GRUNWALD MECHANICAL CONTRACTOR
Project manager: Jonathan Harvey
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, removal and replacement of the existing pool dehumidification system. Contractor is responsible for any required new steel and electrical work.
Bid Date: 03/02/2021

Subcontractors (6)

Iowa School for the Deaf-Southeast Parking Lot-Expansion
CP number: CP1118018
Total Construction Budget: $247,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the expansion of the existing asphalt parking lot located in the southeast quadrant of the Iowa School for the Deaf campus. This project will construct approximately 22 new parking stalls.
Iowa School for the Deaf-Southeast Parking Lot-Expansion
Construction
Scope number: PS01
Construction Budget: $239,513
Begin construction: 08/21/2023
Occupancy / completion: 09/29/2023
Gross sq.ft.: 13644
Net sq.ft.: 13644
Prime contractor: BLUFFS PAVING & UTILITY COMPANY INC
Project manager: Angela Solberg
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, pavement removal, grading, subgrade prep, 6 inch PCC pavement, 5 inch PCC sidewalk, and site lighting at Iowa School for the Deaf in Council Bluffs, Iowa.

Subcontractors (3)

ISU Child Care Center at Veterinary Medicine-Improvements
CP number: CP1008416
Total Construction Budget: $463,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of heating and cooling units, installation of a switch for garbage disposal, and updating of HVAC controls.
ISU Child Care Center at Veterinary Medicine-Improvements
Construction
Scope number: PS01
Construction Budget: $445,711
Occupancy / completion: 03/14/2024
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager: Elizabeth Clarke
Construction manager: Ben Haywood
Contract description of work:
This project includes, but is not limited to, the replacement of heating and cooling units, installation of a switch for garbage disposal, and updating of HVAC controls.

Subcontractors (5)

ISU Family Resource Center-Playground Landscape Improvements
CP number: CP1042380
Total Construction Budget: $119,759
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide several safety improvements to the playground. The project includes, but is not limited to, concrete repairs, repair and sealing of the splintering wood fence panels and wood beams throughout the playground, fine grade and sod lawn areas, and adding wood safety mulch to the playground areas.
ISU Family Resource Center-Playground Landscape Improvements
Scope number: PS01
Construction Budget: $120,100
Prime contractor: TBD
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will provide several safety improvements to the playground. The project includes, but is not limited to, concrete repairs, repair and sealing of the splintering wood fence panels and wood beams throughout the playground, fine grade and sod lawn areas, and adding wood safety mulch to the playground areas.
Bid Date: TBD
Jack Trice Stadium-East Gateway Bridge
CP number: CP002683
Total Construction Budget: $8,163,750
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THE PROJECT WILL CONSTRUCT A BRIDGE OVER SOUTH UNIVERSITY BOULEVARD TO CONNECT THE EAST CONCOURSE OF JACK TRICE STADIUM AND FOOTBALL GAME DAY PARKING EAST OF SOUTH UNIVERSITY BOULEVARD. A SIDEWALK WILL BE CONSTRUCTED ALONG THE EAST SIDE OF THE EXISTING STADIUM RING ROAD AND A FENCE MATCHING THE EXISTING REIMAN GARDENS FENCING WILL BE CONTINUED ALONG THE WEST SIDE OF UNIVERSITY BOULEVARD.
Jack Trice Stadium-East Gateway Bridge
Post Construction
Scope number: PS01
Construction Budget: $8,163,750
Begin construction: 06/04/2021
Occupancy / completion: 09/01/2022
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager: Jonathan Harvey
Construction manager: Darrell Reeves
Contract description of work:
The project consists of, but is not limited to, the construction of an elevated gateway bridge over South University Boulevard to connect the east concourse of Jack Trice Stadium and game day parking east of South University Boulevard. A sidewalk will be added along the east side of the existing stadium ring road. The existing Reiman Gardens fencing on the north will be continued along the west side of University Boulevard.
Bid Date: 05/27/2021

Subcontractors (15)

Jack Trice Stadium-Press Box Elevator-Improvements
CP number: CP965420
Total Construction Budget: $284,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, modernizing the elevator controller, hoisting equipment, and door operations.
Jack Trice Stadium-Press Box Elevator-Improvements
Design-CD
Scope number: PS01
Begin construction: 11/28/2024
Prime contractor: TBD
Project manager: Kelly Kalvelage
Construction manager: Ben Haywood
Contract description of work:
This project includes, but is not limited to, modernizing the elevator controller, hoisting equipment, and door operations.
Jack Trice Stadium-Press Box-Roof Replacement
CP number: CP002611
Total Construction Budget: $110,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
REPLACE ROOF ON THE EXISTING PRESS BOX TOWER AT JACK TRICE STADIUM.
Jack Trice Stadium-Press Box-Roof Replacement
Complete
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Jonathan Harvey
Construction manager: Jonathan Harvey
Contract description of work:
REPLACE ROOF ON THE EXISTING PRESS BOX TOWER AT JACK TRICE STADIUM.
Bid Date: TBD
Jacobson Athletic Building-Room 2035-Remodel
CP number: CP942806
Total Construction Budget: $260,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will remodel the existing Hunziker Auditorium and create a level floor that will replace the existing stepped floor. The existing unused storage space will be removed, and that space captured within the auditorium.
Jacobson Athletic Building-Room 2035-Remodel
Complete
Scope number: PS01
Construction Budget: $237,000
Begin construction: 05/19/2022
Occupancy / completion: 09/11/2022
Gross sq.ft.: 1470
Net sq.ft.: 1470
Prime contractor: GTG CONSTRUCTION LLC
Project manager: Jonathan Harvey
Construction manager: Danelda Allen
Contract description of work:
The project consists of, but is not limited to, demolition of existing flooring, stairs, walls, and doors. Construction of new glass partition walls, raised floor platform, new doors, electrical and mechanical modifications to existing, and new lighting.
Bid Date: 05/12/2022

Subcontractors (9)

Jeff & Deb Hansen Ag Student Learning Center-Room 1200-Door Replacement
CP number: CP1164860
Total Construction Budget: $98,300
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remove roll-up door components and install new sliding doors. This project includes, but is not limited to, architecture work.
Jeff & Deb Hansen Ag Student Learning Center-Room 1200-Door Replacement
Design-CD
Scope number: PS01
Construction Budget: $98,800
Prime contractor: TBD
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will remove roll-up door components and install new sliding doors. This project includes, but is not limited to, architecture work.
Bid Date: TBD
Kildee Hall-AHU2 and UVU4-Replacement
CP number: CP002632
Total Construction Budget: $1,899,040
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace Air Handling Unit (AHU) 2 and Unit Ventilator Unit (UVU) 4 with a semi-custom design unit to serve the west laboratory spaces in the building. Additionally, Mechanical Room M0026 will be prepared for future AHU replacements and improved maintenance access. This project includes, but is limited to replacement of AHU 2 and UVU 4 with a new AHU, ductwork and pipe reconfiguration, motor control center and control panel relocation and upgrade, improved access, and relocation of the existing electrical transformer.
Kildee Hall-AHU2 and UVU4-Replacement
Construction
Scope number: PS01
Construction Budget: $1,726,393
Begin construction: 07/17/2023
Occupancy / completion: 04/10/2025
Gross sq.ft.: 183971
Net sq.ft.: 183971
Prime contractor: MANNING SEIVERT MECHANICAL CONTRACTORS INC
Project manager: Mark Grief
Construction manager: John Boehmer
Contract description of work:
The project includes, but is not limited to, the replacement of Air Handling Unit (AHU) 2 and Unit Ventilator Unit (UVU) 4 with a semi-custom design unit to serve the west laboratory spaces in the building, new ductwork and pipe reconfiguration, along with improved access and relocation of the existing electrical transformer. Additionally, Mechanical Room M0026 will be prepared for future AHU replacements and improved maintenance access.

Subcontractors (5)

Kildee Hall-Common Area Improvements
CP number: CP1017060
Total Construction Budget: $64,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of graphic wall paneling along various first and third floor corridor walls of the original Kildee Hall building. Also included is the reconfiguration of the door swing into Suite 0119.
Kildee Hall-Common Area Improvements
Construction
Scope number: PS01
Construction Budget: $59,000
Begin construction: 09/05/2023
Occupancy / completion: 01/12/2024
Project manager: Jennifer Evans
Construction manager: Ben Haywood
Contract description of work:
This project includes, but is not limited to, updating finishes, wayfinding, space and door reconfiguration, new furniture, and additional power outlets/technology.
Kildee Hall-Roof Replacement-Sections A and B
CP number: CP002758
Total Construction Budget: $517,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace roof Sections A and B at Kildee Hall. These sections have a history of leaks and will be 31 years at this intended replacement date. The typical useful life for this type of roof system is 20 to 25 years. The project includes, but is not limited to, replacement with a new roof designed that has a minimum useful life expectancy of 30 years. Roof insulation will be increased to current energy codes, and the appropriate roof safety systems and equipment will be installed to current University standards. All masonry walls and features above this roofline that tie directly into this system will be repaired, tuck-pointed, or caulked to prevent water infiltration through these critical interfaces.
Kildee Hall-Roof Replacement-Sections A and B
Scope number: PS01
Construction Budget: $644,600
Begin construction: 05/08/2023
Occupancy / completion: 07/28/2023
Gross sq.ft.: 20000
Net sq.ft.: 20000
Prime contractor: CENTRAL STATES ROOFING INC
Project manager: Hayley Sandholm
Construction manager: John Boehmer
Contract description of work:
The project consists of, but is not limited to, replacing the roof system with a more substantial replacement, increasing insulation to current energy codes, and adding the appropriate roof safety systems and equipment.
Bid Date: 04/26/2022
Lied Recreation Athletic Center-Room 0152-Remodel
CP number: CP1006636
Total Construction Budget: $117,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing space by adding a single-user restroom at the entry of room 0152 with a new door into room C0130. This project includes, but is not limited to, architectural, mechanical and electrical work, plumbing repairs, and patching of existing concrete floors.
Lied Athletic Center-Room 0152-Remodel
Complete
Scope number: PS01
Construction Budget: $45,700
Occupancy / completion: 08/15/2022
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will remodel the existing space by adding a single-user restroom at the entry of Room 0152 with a new door into Room C0130. This project includes, but is not limited to, architectural, mechanical and electrical work, plumbing repairs, and patching of existing concrete floors.
Bid Date: 05/19/2022
Linden Residence Hall & Wallace Wilson Commons-Elevator Safety Improvements
CP number: CP002373
Total Construction Budget: $235,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT CONSISTS OF REPLACING AND ADDING SAFETY EQUIPMENT TO TWO (2) FREIGHT ELEVATORS LOCATED IN THE LINDEN RESIDENCE HALL AND THE WALLACE WILSON COMMONS. SEVERAL DEFICIENCIES WILL BE CORRECTED INCLUDING, FIRE RECALL, REPLACE OBSOLETE PARTS, AND UPGRADE EQUIPMENT THAT HAS EXCEEDED LIFE EXPECTANCY.
Linden Residence Hall & Wallace Wilson Commons-Elevator Safety Improvements
Construction
Scope number: PS01
Construction Budget: $235,000
Occupancy / completion: 08/31/2022
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager: Mark Huss
Contract description of work:
This project consists of replacing and adding safety equipment to two (2) freight elevators located in the Linden Residence Hall and the Wallace Wilson commons. Several deficiencies will be corrected including, fire recall, replace obsolete parts, and upgrade of equipment that has exceeded life expectancy.
Bid Date: TBD
Memorial Union-Bookstore-Lighting Replacement
CP number: CP1118655
Total Construction Budget: $389,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, replacing the lighting throughout the University Bookstore. New fixtures, LED bulbs, and additional lighting solutions are needed throughout the space.
Memorial Union-Bookstore-Lighting Replacement
Design-CD
Scope number: PS01
Gross sq.ft.: 21000
Net sq.ft.: 21000
Prime contractor: TBD
Project manager: Hayley Sandholm
Construction manager: Kasi Province
Contract description of work:
This project includes, but is not limited to, replacing the lighting throughout the University Bookstore. New fixtures, LED bulbs, and additional lighting solutions are needed throughout the space.
Bid Date: 12/05/2023 (Tentative)
Memorial Union-Dining Services-Poco Picante-Remodel
CP number: CP002657
Total Construction Budget: $180,550
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL REMODEL AN EXISTING ISU DINING VENUE WITHIN THE MEMORIAL UNION TO UPDATE FINISHES, LIGHTING, AND EQUIPMENT. WORK INCLUDES, BUT IS NOT LIMITED TO: FINISH UPDATES, EQUIPMENT REPLACEMENTS, AND MECHANICAL, ELECTRICAL AND PLUMBING MODIFICATIONS.
Memorial Union-Dining Services-Poco Picante-Remodel
Complete
Scope number: PS01
Construction Budget: $180,550
Begin construction: 02/10/2021
Occupancy / completion: 09/22/2021
Gross sq.ft.: 250
Net sq.ft.: 250
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager: David Blum
Construction manager: Darrell Reeves
Contract description of work:
The project consists of, but is not limited to, renovation of 250 square foot food service venue located on the first floor of the Memorial Union. Scope includes installation of new counters & food service equipment, and lighting fixtures. Demolition and installation of modified plumbing and electrical to support the renovated space.
Bid Date: 02/09/2021

Subcontractors (6)

Memorial Union-Fountain of the Four Seasons-Renovation
CP number: CP1017470
Total Construction Budget: $1,343,310
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the renovation of the pool basin, fountainhead well, mechanical pit, tunnel, pool lighting, and upgrades to the mechanical and electrical systems of the Fountain of the Four Seasons at the exterior north courtyard of the Memorial Union. The original limestone sculptures of the four maidens will be removed, conserved, and replicated. The sculpture replications will be placed at the original site within the renovated fountain. The original sculptures will be placed in a location to be determined by the University Museums.
Memorial Union-Fountain of the Four Seasons-Renovation
Construction
Scope number: PS01
Construction Budget: $1,243,800
Begin construction: 06/05/2023
Occupancy / completion: 10/27/2023
Prime contractor: NEUMANN BROTHERS INC
Project manager: David Blum
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, the renovation of the Memorial Union Fountain of the Four Seasons. Salvage and reinstallation of paving system and limestone units, select limestone unit replacements, select plumbing salvage, demolition and reconstruction of concrete structures, mechanical, electrical, and waterproofing systems. Coordination with Owners representative of installation of limestone sculptures and terra cotta units by others.

Subcontractors (8)

Memorial Union-Graphic and Wayfinding-Improvements
CP number: CP965450
Total Construction Budget: $93,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, improving the signage, graphical identification, and wayfinding in the Memorial Union.
Memorial Union-Graphic and Wayfinding-Improvements
Construction
Scope number: PS01
Construction Budget: $93,000
Begin construction: 02/13/2023
Occupancy / completion: 04/14/2023
Prime contractor: Multiple Constructors
Project manager: Hayley Sandholm
Construction manager: Hayley Sandholm
Contract description of work:
This project includes, but is not limited to, improving the signage, graphical identification, and wayfinding in the Memorial Union.
Bid Date: 01/13/2023
Memorial Union-Life Cycle Improvements
CP number: CP002642
Total Construction Budget: $450,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO: PAINTING, CARPET REPLACEMENT, AND REFINISHING WOOD FLOORS.
Memorial Union-Life Cycle Improvements
Construction
Scope number: PS01
Begin construction: 07/31/2021
Occupancy / completion: 03/31/2022
Prime contractor: Multiple Constructors
Project manager: Kelly Kalvelage
Construction manager: Kelly Kalvelage
Contract description of work:
This project includes, but is not limited to, painting, carpet replacement, and refinishing wood floors.
Bid Date: 02/28/2022
Memorial Union-Roof Replacement
CP number: CP002749
Total Construction Budget: $705,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, replacement of roof sections D, F, H, L M, N, O, P, Q, R, S, T, and U.
Memorial Union-Roof Replacement
Construction
Scope number: PS01
Construction Budget: $1,059,700
Begin construction: 04/03/2023
Occupancy / completion: 06/17/2023
Gross sq.ft.: 19500
Prime contractor: CENTRAL STATES ROOFING INC
Project manager: Kelly Kalvelage
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, full replacement of roof sections D, F, H, L, M, N, O, P, Q, R, S, T and U.
Bid Date: 05/05/2022
Memorial Union-Soults Family Visitor Center-Remodel
CP number: CP002747
Total Construction Budget: $877,273
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will expand and remodel the existing Soults Family Visitor Center to improve the campus visitor experience. The project includes, but is not limited to, expanded office spaces, updated finishes, new technology, equipment, furniture, and restroom modernization.
Memorial Union-Soults Family Visitor Center-Remodel
Post Construction
Scope number: PS01
Construction Budget: $964,000
Begin construction: 12/03/2021
Occupancy / completion: 06/15/2022
Gross sq.ft.: 3000
Net sq.ft.: 2700
Prime contractor: BREIHOLZ CONSTRUCTION COMPANY
Project manager: Kelly Kalvelage
Construction manager: Danelda Allen
Contract description of work:
This project will expand and remodel the existing Soults Family Visitor Center to improve the campus visitor experience. The project consists of, but is not limited to, expanded office spaces; updated finishes; new technology, equipment, and furniture; and restroom modernization.
Bid Date: 11/18/2021

Subcontractors (16)

Memorial Union-Third and Second Floor-Remodel
CP number: CP002643
Total Construction Budget: $4,459,110
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel approximately 12,500 square feet of the third floor of the Memorial Union for use by student service organizations. Approximately 5,000 square feet of existing lounge space on the second floor of the Memorial Union will also be remodeled to provide an updated lounge and common areas for students.
Memorial Union-Third and Second Floor-Remodel
Construction
Scope number: PS01
Construction Budget: $4,263,000
Begin construction: 08/08/2023
Occupancy / completion: 08/02/2024
Gross sq.ft.: 20000
Net sq.ft.: 20000
Prime contractor: HPC LLC
Project manager: Hayley Sandholm
Construction manager: Barton Dobson
Contract description of work:
Remodeling existing office space on third floor to create new office suites, conference spaces, and student lounge. Remodeling second floor lounge for updated lounge and collaboration space as well as two tenant spaces. This project includes but is not limited to a full remodel of each space including, new layout, new walls, ceilings, and flooring, new casework and finishes, mechanical and electrical upgrades, plumbing upgrades, fires system upgrades, and new lighting.

Subcontractors (15)

Molecular Biology Building-Elevator Repairs
CP number: CP1085447
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the evaluation of existing conditions of both Molecular Biology elevator systems and reporting of those conditions and recommended scope of work for repairs including budget estimates.
Molecular Biology Building-Elevator Repairs
Pre-Design
Scope number: PS01
Project manager: Christine Maduro
Construction manager: Christine Maduro
Contract description of work:
Bid Date: TBD
Molecular Biology Building-Room 0121-Remodel
CP number: CP941665
Total Construction Budget: $322,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing space. The project includes, but is not limited to, replacement of interior finishes, lighting and controls, mechanical system components, plumbing lines, fixed casework, and the addition of a fume hood.
Molecular Biology Building-Room 0121-Remodel
Post Construction
Scope number: PS01
Construction Budget: $322,100
Begin construction: 08/15/2022
Occupancy / completion: 01/04/2023
Gross sq.ft.: 1500
Net sq.ft.: 1500
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager: Jennifer Evans
Construction manager: Kasi Province
Contract description of work:
The project consists of, but is not limited to, remodeling an existing animal holding room into a laboratory. The project includes replacement of interior finishes, lighting and controls, mechanical system components, plumbing lines, fixed casework, and the addition of a fume hood.
Bid Date: 06/28/2022

Subcontractors (10)

Oak-Elm Residence Hall-Window Replacement
CP number: CP002486
Total Construction Budget: $1,651,470
includes the bid estimate and contingency for this scope of work
Overall project description of work:
PROJECT SCOPE AS FOLLOWS: REMOVE AND REPLACE WINDOWS, REPLACE BLINDS, REMOVE AND REPLACE ASSOCIATED WINDOW SEALANTS, PROVIDE ABATEMENT AND MONITORING SERVICES.
Oak-Elm Residence Hall-Window Replacement
On Hold
Scope number: PS01
Prime contractor: TBD
Project manager: Mark Huss
Construction manager:
Contract description of work:
Project scope as follows: remove and replace windows, replace blinds, remove and replace associated window sealants, provide abatement and monitoring services.
Bid Date: TBD
Oak-Elm Residence-Life Cycle Improvements
CP number: CP002473
Total Construction Budget: $1,055,840
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THE STUDENT ROOMS WITH HARDWOOD WILL BE REFINISHED. THE STUDENT ROOMS WITH VCT FLOORING WILL BE REPLACED WITH LVT (WOOD-LOOK VINYL TILE). STUDENT ROOMS, HALLWAYS AND COMMON AREAS WILL BE PATCHED AND PAINTED. HALLWAY AND COMMON AREA CARPET WILL BE REPLACED WITH CARPET SQUARES. LIGHTING THROUGOUT THE BUILDING WILL BE REPLACED WITH LED LIGHTING.
Oak-Elm Residence-Life Cycle Improvements
On Hold
Scope number: PS01
Construction Budget: $1,055,840
Gross sq.ft.: 137120
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager: Mark Huss
Contract description of work:
The student rooms with hardwood will be refinished. The student rooms with VCT flooring will be replaced with LVT (wood-look vinyl tile). Student rooms, hallways and common areas will be patched and painted. Hallway and common area carpet will be replaced with carpet squares. Lighting throughout the building will be replaced with LED lighting.
Bid Date: TBD
Parking Lot G7-RV Parking Construction
CP number: CP002741
Total Construction Budget: $7,425,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will construct a parking lot with dedicated pads for use by recreational vehicles (RVs) in the existing grass G7 parking area for football games. A new pedestrian path from the grass football parking lots adjacent to S. 16th Street to the new East Gateway pedestrian bridge will also be installed. Work will include, but is not limited to, gravel paving, RV concrete pads, electric service for each RV, a small pedestrian bridge across Worle Creek, a pedestrian trail and lighting improvements.
Parking Lot G7-RV Parking Construction
Post Construction
Parking Lot G7-RV Parking Construction-Worle Creek Bridge
Complete
Parking Lots 2021-Special Maintenance
CP number: CP002750
Total Construction Budget: $255,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL PROVIDE ASPHALT PATCHING, CRACK-FILLING, SEALCOATING AND PAINTING OF APPROXIMATELY 16 LOTS IDENTIFIED ON THE 5-YEAR SEAL COATING PLAN FOR WORK IN 2021. THE WORK WILL BE COMPLETED USING CONTRACTS THAT HAVE BEEN COMPETITIVELY BID THROUGH PROCUREMENT SERVICES.
Parking Lots 2021-Special Maintenance
Complete
Scope number: PS01
Occupancy / completion: 07/31/2021
Prime contractor: Multiple Constructors
Project manager: Angela Solberg
Construction manager: Barton Dobson
Contract description of work:
THIS PROJECT WILL PROVIDE ASPHALT PATCHING, CRACK-FILLING, SEALCOATING AND PAINTING OF APPROXIMATELY 16 LOTS IDENTIFIED ON THE 5-YEAR SEAL COATING PLAN FOR WORK IN 2021. THE WORK WILL BE COMPLETED USING CONTRACTS THAT HAVE BEEN COMPETITIVELY BID THROUGH PROCUREMENT SERVICES.
Bid Date: TBD
Parking Lots 2022-Special Maintenance
CP number: CP1000670
Total Construction Budget: $300,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide asphalt patching, crack filling, seal coating, and painting of approximately 15 lots identified on the 5-year seal coating plan for work in 2022. The work will be completed using contracts that have been competitively bid through Procurement Services.
Parking Lots 2022-Special Maintenance
Complete
Scope number: PS01
Occupancy / completion: 07/31/2022
Prime contractor: Multiple Constructors
Project manager: Angela Solberg
Construction manager: Kasi Province
Contract description of work:
Bid Date: TBD
Parking Lots 2023-Special Maintenance
CP number: CP1146234
Total Construction Budget: $325,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide asphalt patching, crack filling, seal coating, and painting of approximately 16 lots identified on the 5-year seal coating plan for work in 2023.
Parking Lots 2023-Special Maintenance
Construction
Scope number: PS01
Construction Budget: $331,500
Prime contractor: Multiple Constructors
Project manager: Angela Solberg
Construction manager: Ben Haywood
Contract description of work:
This project will provide asphalt patching, crack filling, seal coating, and painting of approximately 16 lots identified on the 5-year seal coating plan for work in 2023.
Bid Date: TBD
Parking Lots B1 and F-Resurfacing and Expansion
CP number: CP002742
Total Construction Budget: $4,360,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will reconstruct and expand the area of Parking Lot B1, north of the Scheman Building and Fisher Theater. Parking Lot F will also be expanded, west of Fisher Theater and north of Stephens Auditorium. Work will include, but is not limited to, lot reconfiguration and expansion, paving, utilities, sidewalks and lighting improvements.
Parking Lots B1 and F-Resurfacing and Expansion
Scope number: PS01
Construction Budget: $4,360,400
Begin construction: 02/02/2022
Occupancy / completion: 09/02/2022
Prime contractor: MANATTS INC
Project manager: Angela Solberg
Construction manager: Barton Dobson
Contract description of work:
The project consists of, but is not limited to, removal of existing concrete and asphalt pavement, structural demolition, new asphalt and concrete pavement with concrete curb and gutter, concrete sidewalks, storm sewer structures, piping and subsurface detention, parking lot lighting, pavement markings, concrete retaining wall, compactor enclosure and finish grading/topsoil.
Bid Date: 02/01/2022

Subcontractors (9)

Parks Library-Rooms 440 and 450-Remodel
CP number: CP930313
Total Construction Budget: $107,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to removal of study carrels, removal and abatement of carpet tile, seal and polish concrete floor, installation of whiteboards and lockers, and HVAC duct modifications. Cameras and access control will be installed, windows will be tinted, lights replaced, and a new door installed to secure the space.
Parks Library-Rooms 440 and 450-Remodel
Complete
Scope number: PS01
Construction Budget: $107,400
Prime contractor: Multiple Constructors
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
This project includes, but is not limited to, removal of study carrels, removal and abatement of carpet tile, seal and polish concrete floor, installation of whiteboards and lockers, and HVAC duct modifications. Cameras and access control will be installed, windows will be tinted, lights replaced, and a new door installed to secure the space.
Bid Date: TBD
Parks Library-Second Floor-Improvements
CP number: CP1146553
Total Construction Budget: $62,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of furniture, carpet, and the addition of electrical wiring.
Parks Library-Second Floor-Improvements
Scope number: PS01
Construction Budget: $62,100
Begin construction: 05/15/2023
Occupancy / completion: 06/11/2023
Gross sq.ft.: 4524
Net sq.ft.: 4524
Project manager: Jennifer Warrick
Construction manager: Jennifer Warrick
Contract description of work:
This project includes, but is not limited to, the replacement of furniture, carpet, and the addition of electrical wiring.
Parks Library-Wayfinding Improvements
CP number: CP921835
Total Construction Budget: $114,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the addition of building directories, wayfinding signage (approximately 140 locations), and amenity identification signage throughout Parks Library. Applications include a stand-alone building directory, vinyl signage applied to wall surfaces and at selected columns, vinyl signage over new frosted glass covering on specific glazed openings, projecting signage from walls, and surface-mounted acrylic lettering.
Parks Library-Wayfinding Improvements
Construction
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Jennifer Evans
Construction manager:
Contract description of work:
Bid Date: TBD
Patterson Hall-Rooms 1365D & 1385G Surgical Lights-Replacement
CP number: CP1188276
Total Construction Budget: $32,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will purchase and install 19 new LED surgical lights in the Junior Surgery Lab. This project includes, but is not limited to, architectural and electrical work.
Patterson Hall-Rooms 1365D & 1385G Surgical Lights-Replacement
Quote
Scope number: PS01
Construction Budget: $32,600
Prime contractor: Multiple Constructors
Project manager: Josef Biechler
Construction manager: Josef Biechler
Contract description of work:
This project will purchase and install 19 new LED surgical lights in the Junior Surgery Lab. This project includes, but is not limited to, architectural and electrical work.
Bid Date: TBD
Pearson Hall-Accessibility, Wayfinding, and Signage-Improvements
CP number: CP1003356
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, a survey of existing interior room signage to determine the exact quantity, correct numbering, and notable space labeling for the installation of new room signage. Existing room signage will be removed and wall surfaces will be patched and repaired for installation of new accessible room signage.
Pearson Hall-Accessibility, Wayfinding, and Signage-Improvements
Construction
Scope number: PS01
Construction Budget: $128,800
Prime contractor: Iowa State University
Project manager: Jennifer Evans
Construction manager: Jennifer Evans
Contract description of work:
This project includes, but is not limited to, a survey of existing interior room signage to determine the exact quantity, correct numbering, and notable space labeling for the installation of new room signage. Existing room signage will be removed and wall surfaces will be patched and repaired for installation of new accessible room signage.
Bid Date: TBD
Physics Hall-Accessibility Improvements 2022
CP number: CP1000419
Total Construction Budget: $192,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will modify interior and exterior ramps to provide compliant access into and throughout the lower level and replace various sections of the guardrail, handrails, and doors.
Physics Hall-Accessibility Improvements 2022
Scope number: PS01
Construction Budget: $171,300
Begin construction: 05/15/2023
Occupancy / completion: 06/30/2023
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager: Angela Solberg
Construction manager: John Boehmer
Contract description of work:
The project consists of, but is not limited to, modifications to the interior and exterior accessible ramps at the lower level of Physics Hall to provide compliant access into and throughout the lower level. The project also includes replacement of various sections of guardrail, handrail, and doors along the accessible routes undergoing modifications.
Bid Date: 11/10/2022

Subcontractors (5)

Poultry Farm-Teaching and Research Facilities
CP number: CP002490
Total Construction Budget: $7,948,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project replaces several poultry buildings that were over 70 years old, in unusable condition, and did not represent facilities needed for current chicken and turkey teaching and research industry needs. The project includes a 28,300 gsf chicken building and a 19,850 sf turkey building with research penning, automated ventilation, feeding, and lighting controls to support industry needs of Iowa and the nation with modern teaching and research facilities.
Poultry Farm-Teaching and Research Facilities-Turkey Facility
Complete
Poultry Farm-Teaching and Research Facilities-Turkey Facility-Phase 2
Complete
Reiman Gardens Conservatory-Argus Control System-Replacement
CP number: CP1166947
Total Construction Budget: $149,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace the current Argus control system. This project includes, but is not limited to, mechanical work.
Reiman Gardens Conservatory-Argus Control System-Replacement
Bid
Scope number: PS01
Construction Budget: $65,500
Begin construction: 03/11/2024
Occupancy / completion: 05/31/2024
Project manager: Josef Biechler
Construction manager: Josef Biechler
Contract description of work:
This project will replace the current Argus control system. This project includes, but is not limited to, mechanical work.
Reiman Gardens-Conservatory Chiller-Replacement
CP number: CP1110586
Total Construction Budget: $261,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace an existing air-conditioning chiller with a new chiller and downsize the breaker to match the new chiller electrical load. This project includes, but is not limited to mechanical and electrical work.
Reiman Gardens-Conservatory Chiller-Replacement
Construction
Scope number: PS01
Construction Budget: $181,500
Prime contractor: Multiple Constructors
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will replace an existing air-conditioning chiller with a new chiller and downsize the breaker to match the new chiller electrical load. This project includes, but is not limited to mechanical and electrical work.
Bid Date: TBD
Reiman Gardens-Dunlap Courtyard-Pavement Improvements
CP number: CP1166074
Total Construction Budget: $355,300
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the removal and replacement of existing exposed aggregate and brick paving with colored concrete and concrete pavers, and installation of a new colored concrete sidewalk. Work also includes installation of perforated drain tile, final grading, and seeding.
Reiman Gardens-Dunlap Courtyard-Pavement Improvements
Construction
Scope number: PS01
Construction Budget: $284,815
Begin construction: 09/05/2023
Occupancy / completion: 10/06/2023
Prime contractor: HOLZWORTH CONSTRUCTION LLC
Project manager: Angela Solberg
Construction manager: John Boehmer
Contract description of work:
The project consists of, but is not limited to, removal of existing gravel walks; installation of new PCC paving and concrete pavers, installation of perforated tiles, irrigation, and finish grading/topsoil.

Subcontractors (1)

Reiman Gardens-Southwest Corner Improvements
CP number: CP002363
Total Construction Budget: $2,653,550
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THE PROJECT RECONSTRUCTED THE SOUTHWEST CORNER OF REIMAN GARDENS. THE WORK INCLUDED TERRACING THE EXISTING HILLSIDE TO CREATE A SERIES OF WATER POOLS THAT CASCADE OVER HARDSCAPE WALLS AND COLLECT IN A CIRCULAR POOL SURROUNDED BY A WALKWAY. LIGHTING AND PLANTINGS ENHANCE THE WATER FEATURE FLOW LINES, THE HARDSCAPE, AND THE LANDFORM. AN ADDITIONAL STEEL AND WOOD TOWER WAS CONSTRUCTED AS AN ICONIC LANDMARK AND DESTINATION FOR THE GARDENS.
Reiman Gardens-Southwest Corner Improvements-Landscaping
Complete
Scope number: PS01
Construction Budget: $2,653,550
Begin construction: 03/06/2018
Occupancy / completion: 12/23/2018
Gross sq.ft.: 55000
Prime contractor: GRAPHITE CONSTRUCTION GROUP INC
Project manager: Mark Huss
Construction manager: John Boehmer
Contract description of work:
The project consists of, but is not limited to, construction of plant gardens, connecting paths, water features, a single restroom building with mechanical space, a 40-foot-tall steel and wood tower, and associated earth work and utility services.
Bid Date: 03/01/2018

Subcontractors (25)

Roberts Residence Hall-Patio Repairs
CP number: CP1001602
Total Construction Budget: $823,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the repair and replacement of the patio structure, surface, stairs, and railings on the west exterior patio at Roberts Residence Hall. Asbestos abatement of existing waterproofing on adjacent building walls beneath the patio will be included. Interior patio walls below the surface will be repointed and waterproofed. The current patio crawlspace will be regraded, filled with geofoam, and topped with a new concrete base and patio surface. New subdrainage, downspouts, and patio surface drains will be connected to the existing storm drain. Limestone railings and stairs are to be salvaged, repaired, and reinstalled. Also included is the preparation of construction documents for similar repairs to the east patio at Roberts Residence Hall. Bidding and construction of the east patio are to occur at a later, undetermined date.
Roberts Residence Hall-Patio Repairs-West
Construction
Scope number: PS01
Construction Budget: $749,000
Begin construction: 06/19/2023
Occupancy / completion: 09/07/2023
Gross sq.ft.: 1455
Net sq.ft.: 1455
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager: Jennifer Evans
Construction manager: Kasi Province
Contract description of work:
The project consists of, but is not limited to, the repair and replacement of the patio structure, surface, stairs, and railings on the west exterior patio at Roberts Residence Hall. Interior patio walls below the surface will be repointed and waterproofed. The current patio crawlspace will be regraded, filled with geofoam, and topped with a new concrete base and patio surface. New subdrainage, downspouts, and patio surface drains will be connected to the existing storm drain.

Subcontractors (2)

ROTC Obstacle Course
CP number: CP988030
Total Construction Budget: $401,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the construction of a Marine Corps Obstacle Course (O-Course) to support the education and training of the University midshipmen, cadets, and active-duty personnel. The standard 40 ft x 400 ft course consists of seven obstacles and requires a relatively flat site with fencing for security and wood chip mulch ground cover for safety. Course obstacles will be constructed from wood and rope materials with a maximum height of 20 feet. Signage will indicate the nature and purpose of the O-Course.
ROTC Obstacle Course
Construction
Scope number: PS01
Construction Budget: $365,000
Begin construction: 03/01/2023
Occupancy / completion: 06/30/2023
Prime contractor: GTG CONSTRUCTION LLC
Project manager: Angela Solberg
Construction manager: Nathan Graves
Contract description of work:
The project consists of, but is not limited to, site grading, obstacle course equipment and footings, mulch, drainage, fencing, finish grading and topsoil.
Bid Date: 11/03/2022

Subcontractors (2)

Roy J. Carver Co-Laboratory-Room 0027-Remodel
CP number: CP1044309
Total Construction Budget: $79,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing space for testing and demonstration of robotic instrumentation. This project includes, but is not limited to, architectural, mechanical, and electrical modifications.
Roy J. Carver Co-Laboratory-Room 0027-Remodel
Complete
Scope number: PS01
Construction Budget: $68,600
Occupancy / completion: 01/01/2023
Gross sq.ft.: 676
Net sq.ft.: 676
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will remodel the existing space for testing and demonstration of robotic instrumentation. This project includes, but is not limited to, architectural, mechanical, and electrical work.
Bid Date: 10/26/2022
Schilletter Village-Exterior Improvements-Phase 2
CP number: CP002499
Total Construction Budget: $649,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
CURRENT MAIN ENTRANCE DECKS WILL BE REMOVED, BUILDING FRAMING AND SIDING WILL BE REPAIRED AS NEEDED, AND THE DECKS WILL BE REPLACED. SECTIONS OF CONCRETE SIDEWALKS THAT HAVE SETTLED OVER TIME WILL BE REPLACED AS NEEDED. WINDOWS AND SOME EXTERIOR DOORS WILL BE REPLACED. THE SITE WILL BE REGRADED TO ROUTE WATER AWAY FROM THE WINDOW WELLS OF BUILDINGS WHERE THE BASEMENT FLOODS CONSISTENTLY.
Schilletter Village-Exterior Improvements-Phase 2
Construction
Scope number: PS01
Construction Budget: $650,000
Occupancy / completion: 08/31/2022
Prime contractor: Multiple Constructors
Project manager: Mark Huss
Construction manager: Mark Huss
Contract description of work:
CURRENT MAIN ENTRANCE DECKS WILL BE REMOVED, BUILDING FRAMING AND SIDING WILL BE REPAIRED AS NEEDED, AND THE DECKS WILL BE REPLACED. SECTIONS OF CONCRETE SIDEWALKS THAT HAVE SETTLED OVER TIME WILL BE REPLACED AS NEEDED. WINDOWS AND SOME EXTERIOR DOORS WILL BE REPLACED. THE SITE WILL BE REGRADED TO ROUTE WATER AWAY FROM THE WINDOW WELLS OF BUILDINGS WHERE THE BASEMENT FLOODS CONSISTENTLY.
Bid Date: TBD
SCIENCE- 4th Floor-223825-Corridor Remodel
CP number: PR1043509
Total Construction Budget: $73,300
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Science I Hall 4th Floor, Psychology area led lighting, ceiling tile, new flooring, paint, built in benches or matching chairs See Project Specifics in attachment; G Drive Project Folder and Lucernex Project Folder. DD16098 created today 9.14.2022 so not showing up in the system
Science Hall-4th Floor Corridor-Remodel
Construction
Scope number: PS01
Construction Budget: $73,300
Begin construction: 06/14/2023
Occupancy / completion: 08/20/2023
Project manager: Jordan Babler
Construction manager: Jordan Babler
Contract description of work:
This project will remodel the fourth-floor corridor in Science Hall. This project includes, but is not limited to architectural, mechanical, electrical and fixed equipment.
Science Hall 2-Accessibility, Wayfinding, and Signage-Improvements
CP number: CP1003358
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the survey of existing interior room signage to determine the exact quantity, correct numbering, and notable space labeling for the installation of new room signage. Any existing room signage and existing tackboards adjacent to door openings will be removed and wall surfaces will be patched and repaired for the installation of new accessible room signage.
Science Hall 2-Accessibility, Wayfinding, and Signage-Improvements
Construction
Scope number: PS01
Construction Budget: $126,300
Prime contractor: Iowa State University
Project manager: Jennifer Evans
Construction manager: Jennifer Evans
Contract description of work:
This project includes, but is not limited to, evaluation of existing signage conditions, room count, numbering and specific space allocations; and design and documentation for new wayfinding and accessible signage/
Bid Date: TBD
Science Hall-AHU 2-Replacement
CP number: CP1006645
Total Construction Budget: $823,830
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, installation of Air Handling Unit 2 (AHU 2) in Room 0061 to supply ventilation to the east portion of the building, remove existing supply and return ductwork and install new supply air ductwork and dampers to existing supply air grilles. Remove and replace the relief/exhaust fan on the roof, install a 60-amp breaker in the existing Motor Control Center, remove the existing disconnect and install a new disconnect to the new motor.
Science Hall-AHU 2-Replacement
Construction
Scope number: PS01
Construction Budget: $784,600
Begin construction: 05/15/2023
Occupancy / completion: 03/26/2024
Gross sq.ft.: 897
Net sq.ft.: 897
Prime contractor: DAHL AIR COND & HEATING LLC
Project manager: Mark Grief
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, the replacement of AHU 2, in Room 061, minor demolition of existing plaster bulkheads, repair and replacement of existing acoustical tile ceilings, in corridors C0101, C0155, C0255, and C0355 and electrical work associated with AHU 2 and ceilings in corridors C0101, C0155, C0255, and C0355.
Bid Date: 12/01/2022

Subcontractors (10)

Science Hall-AHU 3-Replacement
CP number: CP1006655
Total Construction Budget: $392,570
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to replacement of Air Handling Unit 3 (AHU 3) in Room 0074A, including associated plumbing, ductwork, electrical service, insulation, controls, and removal and reconstruction of interior walls and doors as required.
Science Hall-AHU 3-Replacement
Construction
Scope number: PS01
Construction Budget: $362,000
Begin construction: 03/13/2023
Occupancy / completion: 08/21/2024
Gross sq.ft.: 513
Net sq.ft.: 513
Prime contractor: STEIN HEATING & COOLING INC
Project manager: Mark Grief
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, the removal and replacement of Air Handling Unit 3 in Room 0074A of Science Hall. This work includes minor demolition of a masonry wall for a new door opening, demolition of existing piping, and demolition of existing ductwork associated with the demolition of the existing Air Handling Unit 3. Work also includes installing a new door and frame, insulating an existing wall, and installing a new air handling unit, ductwork, controls and associated piping with the installation of the unit.
Bid Date: 12/08/2022

Subcontractors (5)

Science Hall-Rooms 0102 & 0152-Ventilation Improvements
CP number: CP942926
Total Construction Budget: $303,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of two air handling units and the installation of two new energy recovery ventilators.
Science Hall-Rooms 0102 & 0152-Ventilation Improvements
Construction
Scope number: PS01
Construction Budget: $282,192
Begin construction: 09/05/2023
Occupancy / completion: 11/27/2023
Prime contractor: AIR CON MECHANICAL INC
Project manager: Elizabeth Clarke
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, the replacement of two air handling units and the installation of two new energy recovery ventilators.

Subcontractors (5)

SEED-Room 128-Vacuum Pump System
CP number: PR024332
Total Construction Budget: $72,930
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Seed Sci Rrom 128 - Vacuum Pump System
Seed Science Building-Room M0260-Vacuum Pump System
Construction
Scope number: PS01
Construction Budget: $72,930
Begin construction: 08/01/2022
Occupancy / completion: 10/14/2022
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will disconnect, remove, and install a new vacuum pump in Room M0260 at the Seed Science Building. The scope of work will include but not be limited to: general construction, electrical, and Owner provided control work.
Snedecor Hall-Rooms 1108, 2101, and 3105-Remodel
CP number: CP986791
Total Construction Budget: $44,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, renovation of a restroom, lounge and seminar room, including replacement of countertops, plumbing fixtures and furniture, and minor electrical work.
Snedecor Hall-Rooms 1108, 2101, and 3105-Remodel
Complete
Scope number: PS01
Construction Budget: $64,200
Begin construction: 04/17/2022
Occupancy / completion: 07/31/2022
Project manager: Christine Reinders-Caron
Construction manager: Christine Reinders-Caron
Contract description of work:
This project includes, but is not limited to, renovation of a restroom, lounge, and seminar room, including replacement of countertops, plumbing fixtures and furniture, and minor electrical work.
Bid Date: 04/11/2022
Sports Performance Center & Jack Trice Stadium Improvements North
CP number: CP002505
Total Construction Budget: $71,650,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
A NEW FACILITY WILL BE CONSTRUCTED ON THE EAST SIDE OF THE BERGSTROM FOOTBALL COMPLEX THAT WILL BE USED BY ALL STUDENT-ATHLETES. THIS FACILITY WILL PROVIDE AN EXPANDED ACADEMIC AND STUDENT AFFAIRS CENTER, COMMONS AREA FOR STUDENTS TO GATHER AND INTERACT WITH FELLOW STUDENT-ATHLETES, AND A FULL SERVICE SPORTS NUTRITION CENTER INCLUDING FUELING STATIONS AND A DINING FACILITY THAT WILL BE STAFFED BY REGISTERED DIETICIANS. THE FACILITY WILL ALSO INCLUDE EXPANDED SERVICE AREAS INCLUDING SPORTS MEDICINE, STRENGTH AND CONDITIONING, AND LOCKER ROOMS FOR MULTIPLE VARSITY SPORTS.
Sports Performance Center & Jack Trice Stadium Improvements North-Bergstrom Football Complex-Rooms 2050, 2054, and 2056 Remodel
Sports Performance Center & Jack Trice Stadium Improvements North-Jacobson & Concourse
Complete
Sports Performance Center & Jack Trice Stadium Improvements North-Sports Performance Center
Post Construction
STADIUM- GENERAL-232264-Press Box Cooling 2nd Level
CP number: PR1096978
Total Construction Budget: $87,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Eric Ohrt Can you have the guys get a quote for installing AC on the 2nd floor of the tower and the hallways of the 3rd floor? Requested by Miles Pankonen
Jack Trice Stadium-2nd Level Press Box-Cooling Units
Bid
Scope number: PS01
Construction Budget: $87,100
Occupancy / completion: 08/01/2023
Prime contractor: TBD
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project will install seven (7) new fan coil units on the 2nd floor of the press box at Jack Trice Stadium. The project includes, but is not limited to, general construction, mechanical, and engineering work.
Stephens Auditorium-Main Lobby Carpet-Replacement
CP number: CP1097770
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of the existing carpet in the main lobby.
Stephens Auditorium-Main Lobby Carpet-Replacement
Construction
Scope number: PS01
Construction Budget: $167,400
Prime contractor: Multiple Constructors
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project includes, but is not limited to, the replacement of the existing carpet in the main lobby.
Bid Date: TBD
Stephens Auditorium-Restrooms-Remodel
CP number: CP999526
Total Construction Budget: $620,050
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will convert storage space on the main floor into eight single user accessible restrooms and remodel one existing multiple user mens room and one existing multiple user womens room on the ground floor. The project includes, but is not limited to new bathroom fixtures, plumbing, finishes and partitions in existing restrooms and constructing complete new accessible restrooms.
Stephens Auditorium-Restrooms-Remodel
Construction
Scope number: PS01
Construction Budget: $624,800
Begin construction: 08/01/2023
Occupancy / completion: 12/15/2023
Gross sq.ft.: 2000
Net sq.ft.: 2000
Prime contractor: EDGE COMMERCIAL LLC
Project manager: Hayley Sandholm
Construction manager: Ben Haywood
Contract description of work:
This project will convert storage space on the main floor into eight single user accessible restrooms. The project consists of, but is not limited to, new bathroom fixtures, plumbing, and finishes.

Subcontractors (12)

Stephens Auditorium-Roof Replacement-Section A
CP number: CP002745
Total Construction Budget: $412,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, REMOVAL AND REPLACEMENT OF THE NORTH PORTION, SECTION A, OF STEPHENS AUDITORIUM ROOF THAT WAS DAMAGED BY HAIL. THIS INCLUDES REMOVAL OF EXISTING ROOF MEMBRANE AND INSTALLATION, INSTALLATION OF NEW 5 INCH RIGID INSULATION, MOISTURE RESISTANT BACKER BOARD, 90 MIL EPDM-30 YEAR MEMBRANE, AND NEW PREFINISHED METAL FLASHING.
Stephens Auditorium-Roof Replacement-Section A
Post Construction
Scope number: PS01
Construction Budget: $412,500
Begin construction: 08/22/2022
Occupancy / completion: 10/30/2022
Gross sq.ft.: 23550
Net sq.ft.: 23550
Prime contractor: BLACK HAWK ROOF CO INC
Project manager: Jonathan Harvey
Construction manager: Steven Nelson
Contract description of work:
The project consists of, but is not limited to, installing new fully adhered 90 mil EPDM roof membrane and insulation system over the existing roof membrane and insulation. Provide and install new flashings and roof expansion covers.
Bid Date: 04/28/2022
Stephens Auditorium-Roof Replacement-Section B
CP number: CP1177101
Total Construction Budget: $210,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the removal and replacement of the portion section B of Stephens Auditorium roof that was damaged by hail. This includes the removal of the existing roof membrane and installation, of new 5 inch rigid insulation, moisture resistant backer board, 90 mil EPDM-30 Year membrane, and new prefinished metal flashing.
Stephens Auditorium-Roof Replacement-Section B
Construction
Scope number: PS01
Construction Budget: $210,000
Prime contractor: Multiple Constructors
Project manager: Eric Ohrt
Construction manager: Eric Ohrt
Contract description of work:
This project includes, but is not limited to, the removal and replacement of the portion section B of Stephens Auditorium roof that was damaged by hail. This includes the removal of the existing roof membrane and installation, of new 5 inch rigid insulation, moisture resistant backer board, 90 mil EPDM-30 Year membrane, and new prefinished metal flashing.
Bid Date: TBD
Student Innovation Center
CP number: CP002225
Total Construction Budget: $60,575,494
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL CONSTRUCT A NEW STUDENT-FOCUSED FACILITY THAT WILL PROVIDE A HIGH-QUALITY, CENTRALIZED SPACE TO SUPPORT A STUDENT-DRIVEN CULTURE OF INNOVATION THAT EXEMPLIFIES THE CONVERGENT FUTURE OF PRACTICES AND LEADERS. THE CENTER WILL BE A HIGHLY FLEXIBLE, DYNAMIC SPACE THAT ENCOURAGES EXPERIMENTATION, INNOVATION AND INTERDISCIPLINARY INVESTIGATION BY PROVIDING SPACE FOR PROTOTYPING, FABRICATION AND SMALL SCALE SPACES FOR BENCH-TOP SIZED PROJECTS ALONGSIDE STATE OF THE ART CLASSROOMS WITH EASY ACCESS TO SPECIALIZED EQUIPMENT, MATERIALS, TOOLS, AS WELL AS SPACE FOR COMPUTER-AIDED DESIGN AND VIRTUAL REALITY FACILITIES.
Student Innovation Center-Dust Collection System
Complete
Scope number: PS02
Construction Budget: $312,000
Begin construction: 10/09/2020
Occupancy / completion: 04/02/2021
Prime contractor: ACI MECHANICAL INC
Project manager: Elizabeth Clarke
Construction manager: Nathan Graves
Contract description of work:
The project consists of, but is not limited to, installation of a new dust collection system serving the level 1 fabrication space in the Student Innovation Center. Work requires selective demolition, installation of a full dust collection system including controls, fire suppression, compressed air, and all other items to support the full system, and integration with existing building systems.
Bid Date: 12/17/2020

Subcontractors (5)

Student Innovation Center-Administration Suite-Remodel
CP number: CP1119386
Total Construction Budget: $385,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the remodeling of rooms 2117, 2119, and 2120 to accommodate the expansion of the existing administration office suite currently located in rooms 2118 and 2118A of the Student Innovation Center. Work includes demolition of interior space including existing walls and finishes. New work to include new walls, finishes and modified mechanical and electrical work to support the remodel.
Student Innovation Center-Administration Suite-Remodel
Bid
Scope number: PS01
Construction Budget: $320,000
Occupancy / completion: 03/15/2024
Gross sq.ft.: 2600
Net sq.ft.: 2574
Prime contractor: TBD
Project manager: Elizabeth Clarke
Construction manager: Kasi Province
Contract description of work:
The project consists of, but is not limited to, the remodeling of rooms 2117, 2119, and 2120 to accommodate the expansion of the existing administration office suite currently located in rooms 2118 and 2118A of the Student Innovation Center. Work includes demolition of interior space including walls and finishes. New work includes new walls, finishes, and modified mechanical and electrical work to support the remodel.
Bid Date: 10/19/2023
Student Innovation Center-Room 1858-Modifications
CP number: CP1105833
Total Construction Budget: $308,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the removal of the metal screen partition and track system used to enclosure the Innovate 1858 shop, and replacement with a glass sliding door panel system. Work also includes the relocation of existing ductwork and junction box at the northwest corner to accommodate the new panel system.
Student Innovation Center-Room 1858-Modifications
Construction
Scope number: PS01
Construction Budget: $266,420
Begin construction: 12/15/2023
Occupancy / completion: 01/12/2024
Gross sq.ft.: 548
Net sq.ft.: 548
Prime contractor: BOONE GLASS COMPANY
Project manager: Elizabeth Clarke
Construction manager: Nathan Graves
Contract description of work:
The project consists of, but is not limited to, the removal of the metal screen partition and track system used to enclose the Innovate 1858 shop, and replacement with a glass sliding door panel system. Work also includes the relocation of existing ductwork and junction box at the northwest corner to accommodate the new panel system.

Subcontractors (1)

Sukup Basketball Complex-Rooms 1124 & 1125-Renovation
CP number: CP964890
Total Construction Budget: $715,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to new lockers, new flooring, new wall finishes, new ceilings and lighting, demolition and new wall construction, renovated shower and restroom fixtures, and updated graphics.
Sukup Basketball Complex-Rooms 1124 & 1125-Renovation
Construction
Scope number: PS01
Construction Budget: $720,164
Begin construction: 05/26/2023
Occupancy / completion: 09/11/2023
Gross sq.ft.: 2860
Net sq.ft.: 2680
Prime contractor: BREIHOLZ CONSTRUCTION COMPANY
Project manager: Jonathan Harvey
Construction manager: Nathan Graves
Contract description of work:
The project consists of, but is not limited to, demolition of existing finishes and walls; installation of new stud walls, flooring, finishes, and ceilings; new lighting; and modifications to existing mechanical system.

Subcontractors (15)

Surplus Warehouse
CP number: CP1000965
Total Construction Budget: $423,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the construction of a new 6,600 sf warehouse, north of the existing Surplus Facility.
Surplus Warehouse
Construction
Scope number: PS01
Construction Budget: $385,000
Begin construction: 06/26/2023
Occupancy / completion: 09/05/2023
Gross sq.ft.: 6600
Net sq.ft.: 6600
Prime contractor: GTG CONSTRUCTION LLC
Project manager: Jennifer Evans
Construction manager: Ben Haywood
Contract description of work:
This project includes, but is not limited to, the construction of a new 6,600 sf warehouse, north of the existing Surplus Facility.

Subcontractors (7)

Therkildsen Industrial Engineering Building
CP number: CP002619
Total Construction Budget: $54,928,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will build a new facility for the Department of Industrial and Manufacturing Systems Engineering (IMSE) of the College of Engineering. The new building will provide space for teaching and research labs, classrooms, and office space. Parking will also be provided to replace that displaced by the new building
Therkildsen Industrial Engineering Building
Construction
Therkildsen Industrial Engineering Building-Parking Lot 1 Expansion
Post Construction
Therkildsen Industrial Engineering Building-Parking Lot 10 Expansion
Post Construction
Town Engineering Building-Facility and Infrastructure-Improvements
CP number: CP1001182
Total Construction Budget: $360,360
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the purchase of a 3D concrete printer and electrohydraulic pump system, as well as mechanical, electrical, ventilation, storage, and other facility improvements to support the equipment and other analytical instrumentation for instructional and research laboratory needs. Dock improvements to support storage and access for materials handling equipment; renovations to rooms that support the geotechnical and materials engineering, environmental engineering, and water resources engineering research and instruction will be designed and implemented as feasible.
Town Engineering Building-Facility and Infrastructure-Improvements-480V Electric and Chilled Water
Construction
Scope number: PS01
Construction Budget: $234,750
Begin construction: 09/11/2023
Occupancy / completion: 02/16/2024
Prime contractor: PROCTOR MECHANICAL
Project manager: Angela Solberg
Construction manager: Kasi Province
Contract description of work:
This project consists of, but is not limited to, tap existing chilled water mains in basement and install chilled water piping to new heat exchanger in the basement mechanical room. Install pump, air/dirt separator, expansion tank and process water loop piping for two electrohydraulic pumps. Tap existing 480V service, install new disconnect, two new panels, conduit, wiring and hook-ups for concrete robot, two stud welders, two hydraulic pumps and one process chilled water pump and VFD.

Subcontractors (3)

Town Engineering Building-Wireless Card Access-Improvements
CP number: CP1001624
Total Construction Budget: $105,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, installation of new wireless card access readers on approximately 44 doors in the Town Engineering Building.
Town Engineering Building-Wireless Card Access-Improvements
Complete
Scope number: PS01
Construction Budget: $165,000
Project manager: Angela Solberg
Construction manager: Angela Solberg
Contract description of work:
This project includes, but is not limited to, installation of new wireless card access readers on approximately 44 doors in the Town Engineering Building.
Bid Date: TBD
Union Drive Community Center-Union Drive Marketplace-Renovation
CP number: CP002589
Total Construction Budget: $3,992,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project is a renovation of approximately 16,000 sf of student dining and food service areas to improve the dining experience through new seating; improved serving lines; updated finishes of the ceilings, floor, and walls; and new lighting.
Union Drive Community Center-Union Drive Marketplace-Renovation-Venues
Union Drive Community Center-Union Drive Marketplace-Renovation-Venues and Seating
Union Drive Community Center-Various Repairs
CP number: CP941101
Total Construction Budget: $244,570
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The Union Drive Community Center building continually has challenges keeping a positive building pressure. The negative building pressure swings are causing cold air infiltration, which has caused pipes to freeze within the building. This project includes, but is not limited to modify existing dryer exhaust system, clean VAV/AHU coils and associated ductwork, steam condensate vent modifications, replacement of glycol heating water pumps and VFD pumps serving AHU1 and AHU2, replace heating water pumps that serve VAV reheat coils and perimeter radiation, and add VFDs and associated controls, and add a cooling system and additional pipe insulation to Mechanical Room M180 for heat mitigation.
Union Drive Community Center-Various Repairs
Construction
Scope number: PS01
Construction Budget: $88,000
Occupancy / completion: 10/04/2023
Prime contractor: Multiple Constructors
Project manager: David Blum
Construction manager:
Contract description of work:
This project includes, but is not limited to, modification of existing dryer exhaust system, cleaning of VAV/AHU coils and associated ductwork, steam condensate vent modifications, replacement of glycol heating water pumps and VFD pumps serving AHU-1 and AHU-2, replacement of heating water pumps that serve VAV reheat coils and perimeter radiation, and addition of VFDs and associated controls.
Bid Date: TBD
Union Drive Community Center-Water Heater Replacements
CP number: CP926435
Total Construction Budget: $284,730
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to remove and replace two domestic water heaters, piping, and accessories in room M180.
Union Drive Community Center-Water Heater Replacements
Complete
Scope number: PS01
Occupancy / completion: 07/15/2022
Prime contractor: Multiple Constructors
Project manager: David Blum
Construction manager: Darrell Reeves
Contract description of work:
This project includes, but is not limited to, removing and replacing two domestic water heaters, piping, and accessories in Room M180.
Bid Date: TBD
Utilities-Campus Sidewalk Lighting Improvements
CP number: CP002671
Total Construction Budget: $325,130
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL INSTALL NEW SIDEWALK POLE LIGHTS IN VARIOUS AREAS AROUND CAMPUS TO IMPROVE LIGHT LEVELS AND SAFETY WHEN WALKING ON CAMPUS IN THE EVENING.
Utilities-Campus Sidewalk Lighting Improvements-Phase 2
Complete
Scope number: PS02
Construction Budget: $325,130
Begin construction: 06/11/2021
Occupancy / completion: 08/15/2021
Prime contractor: JASPERING ELECTRIC INC
Project manager: Caleb Barduson
Construction manager: Caleb Barduson
Contract description of work:
The project consists of, but is not limited to, improving lighting on campus sidewalks by installing new poles and light fixtures, relocating existing sidewalk poles, installing solar-powered sidewalk lights, and adding/replacing building mounted lights.
Bid Date: 06/10/2021

Subcontractors (2)

Utilities-Pearson Substation-13.8kV Feeder Cable Replacement
CP number: CP923004
Total Construction Budget: $341,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, removal and replacement of the existing original 1970 portion of 13.8kV cable feeder with new medium voltage cable. The original portion of cable in service is routed from Power Plant switchgear to an underground vault east of Parks Library, approximately 2500 feet.
Utilities-Pearson Substation-13.8kV Feeder Cable Replacement
Post Construction
Scope number: PS02
Construction Budget: $277,500
Begin construction: 05/15/2023
Occupancy / completion: 08/11/2023
Prime contractor: TRI CITY ELECTRIC CO OF IA
Project manager: Travis Van Dyke
Construction manager: Travis Van Dyke
Contract description of work:
The project consists of, but is not limited to, removal and replacement of 13,800V cable in existing conduits between underground vaults and above ground switchgear, cable splices in existing underground vaults, and cable terminations in above ground switchgear. Perform hi-pot cable tests on installed cable, splices, and terminations.
Bid Date: 07/19/2022
Utilities-Power Plant-ABB Software and SCADA Upgrades
CP number: CP002626
Total Construction Budget: $363,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL UPGRADE EXISTING POWER PLANT OPERATOR CONSOLES AND SCADA SYSTEM.
Utilities-Power Plant-ABB Software and SCADA Upgrades
Scope number: PS01
Construction Budget: $
Begin construction: 12/01/2019
Prime contractor: Multiple Constructors
Project manager: Mark Kruse
Construction manager: Nicholas Kolbet
Contract description of work:
This project will upgrade existing Power Plant operator consoles and SCADA System.
Bid Date: TBD
Utilities-Power Plant-Balance of Plant Programmable Logic Controller
CP number: CP002629
Total Construction Budget: $195,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace increasingly dated controls for power plant auxiliary equipment, including service water pumps, feed water pumps, pressure reducing station controls, and condensate tank level controls
Utilities-Power Plant-Balance of Plant Programmable Logic Controller
Complete
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Mark Kruse
Construction manager: Mark Kruse
Contract description of work:
This project will replace increasingly dated controls for power plant auxiliary equipment, including service water pumps, feed water pumps, pressure reducing station controls, and condensate tank level controls.
Bid Date: TBD
Utilities-Power Plant-Boiler Makeup Reverse Osmosis 4 Installation
CP number: CP1164013
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will add a 4th reverse osmosis (RO) water filter unit to fully satisfy boiler feedwater requirements during peak winter heating months.
Utilities-Power Plant-Boiler Makeup Reverse Osmosis 4 Installation
Scope number: PS01
Construction Budget: $233,000
Prime contractor: Multiple Constructors
Project manager: Lee Mason
Construction manager: Lee Mason
Contract description of work:
This project will add a 4th reverse osmosis (RO) water filter unit to fully satisfy boiler feedwater requirements during peak winter heating months.
Bid Date: TBD
Utilities-Power Plant-Chiller 1 Turbine Overhaul FY23
CP number: CP1015183
Total Construction Budget: $325,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, opening, cleaning, and inspecting the steam turbine on Chiller 1. Any turbine components found worn or damaged will be repaired or replaced.
Utilities-Power Plant-Chiller 1 Turbine Overhaul FY23
Complete
Scope number: PS01
Construction Budget: $218,110
Occupancy / completion: 05/01/2023
Prime contractor: Multiple Constructors
Project manager: Matthew Shriver
Construction manager: Matthew Shriver
Contract description of work:
This project includes, but is not limited to, opening, cleaning, and inspecting the steam turbine on Chiller 1. Any turbine components found worn or damaged will be repaired or replaced.
Bid Date: TBD
Utilities-Power Plant-Chiller 5 Compressor Overhaul FY23
CP number: CP1044984
Total Construction Budget: $320,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, opening, cleaning, and inspecting the refrigerant compressor on Chiller 5. Compressor components found worn or damaged will be repaired or replaced.
Utilities-Power Plant-Chiller 5 Compressor Overhaul FY23
On Hold
Scope number: PS01
Construction Budget: $320,000
Project manager: Matthew Shriver
Construction manager: Matthew Shriver
Contract description of work:
This project includes, but is not limited to, opening, cleaning, and inspecting the refrigerant compressor on Chiller 5. Compressor components found worn or damaged will be repaired or replaced.
Bid Date: TBD
Utilities-Power Plant-Coal Boilers Natural Gas Conversion
CP number: CP002712
Total Construction Budget: $13,600,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will convert the two remaining coal fired boilers (boilers #1 & #2) in the university central cogeneration plant to natural gas-fired boilers, ending the use of coal by Iowa State University. The conversion includes modifying the boiler existing burners and fans along with removing the auxiliary coal handling systems. In addition, the project will restore two coal storage sites (east of Haber road and adjacent to the plant).
Utilities-Power Plant-Coal Boilers Natural Gas Conversion
Construction
Scope number: PS01
Construction Budget: $13,600,000
Begin construction: 04/18/2022
Occupancy / completion: 09/28/2023
Prime contractor: BOWEN ENGINEERING CORP
Project manager: Mark Kruse
Construction manager: Lee Mason
Contract description of work:
This project will convert the two remaining coal-fired boilers (Boilers #1 & #2) in the University's central cogeneration plant to natural gas-fired boilers, ending the use of coal by Iowa State University. The conversion includes modifying the boiler's existing burners and fans along with removing the auxiliary coal handling systems. In addition, the project will restore two coal storage sites (east of Haber Road and adjacent to the Power Plant).
Bid Date: TBD

Subcontractors (5)

Utilities-Power Plant-Condenser Water Piping-Repairs
CP number: CP002753
Total Construction Budget: $210,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to: Emergency excavation and repair of buried condenser water pipes between the Utility Plant and Cooling Towers upon discovery of significant surface level water leaks.
Utilities-Power Plant-Condenser Water Piping-Repairs
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Mark Kruse
Construction manager: Mark Kruse
Contract description of work:
This project includes, but is not limited to, emergency excavation and repair of buried condenser water pipes between the Utility Plant and Cooling Towers upon discovery of significant surface level water leaks.
Bid Date: TBD
Utilities-Power Plant-External Stack Repairs
CP number: CP002607
Total Construction Budget: $960,730
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL REPLACE EXISTING PLATFORMS, INSTALL A NEW STACK FALL PROTECTION SYSTEM, REPLACE CONDUITS, AND CLEAN AND PAINT THE EXTERIOR OF THE STACK.
Utilities-Power Plant-External Stack Repairs
On Hold
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager: Lee Mason
Construction manager: Lee Mason
Contract description of work:
This project will replace existing platforms, install a new stack fall protection system, replace conduits, and clean and paint the exterior of the stack.
Bid Date: TBD
Utilities-Power Plant-Station Power Improvements
CP number: CP002466
Total Construction Budget: $7,040,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL REPLACE AND RECONFIGURE THE STATION POWER SYSTEM WITHIN THE UNIVERSITY POWER PLANT. THE STATION POWER SYSTEM CONSISTS OF THE INTERNAL 15,000 AND 5,000 VOLT SWITCHGEAR, INTERNAL SUBSTATIONS, 480 VOLT LOAD CENTERS, MOTOR CONTROL CENTERS, AND ESSENTIAL POWER SYSTEMS. THE PROJECT WILL TAKE PLACE IN MULTIPLE PHASES OVER MULTIPLE YEARS IN ORDER TO MAINTAIN PLANT OPERATIONS.
Utilities-Power Plant-Station Power Improvements-Phase 1
Complete
Utilities-Power Plant-Station Power Improvements-Phase 2
Complete
Utilities-Power Plant-Station Power Improvements-Phase 4
Utilities-Power Plant-Turbine Generator #6 Overhaul FY24
CP number: CP1176045
Total Construction Budget: $697,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will inspect, overhaul and repair/replace damaged components within Turbine Generator #6 which may include, but is not limited to, steam turbine, rotor speed reduction gearbox, and electric generator.
Utilities-Power Plant-Turbine Generator #6 Overhaul FY24
Scope number: PS01
Construction Budget: $697,000
Prime contractor: Multiple Constructors
Project manager: Nicholas Kolbet
Construction manager: Nicholas Kolbet
Contract description of work:
This project will inspect, overhaul and repair/replace damaged components within Turbine Generator #6 which may include, but is not limited to, steam turbine, rotor speed reduction gearbox, and electric generator.
Bid Date: TBD
Utilities-Square Lid Vault Top-Replacements
CP number: CP921822
Total Construction Budget: $198,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to: • Replace eight (8) existing underground electrical and telecom vault top concrete slabs square manhole lids with new concrete slabs that have ISU standard round manhole lids. This project will involve excavating around the central campus electrical/telecom vaults, sidewalk removal and replacement, re-grading around vaults, concrete removal, and new cast-in-place concrete and rebar work
Utilities-Square Lid Vault Top-Replacements
Complete
Scope number: PS01
Construction Budget: $212,400
Begin construction: 03/04/2022
Occupancy / completion: 09/12/2022
Prime contractor: C GREEN CONTRACTOR INC
Project manager: Travis Van Dyke
Construction manager: Travis Van Dyke
Contract description of work:
The project consists of, but is not limited to, the replacement of eight (8) existing underground electrical and telecom vault top concrete slabs that have square manhole lids, with new concrete slabs with ISU standard round manhole lids. This project will involve excavating around the central campus electrical/telecom vaults, sidewalk removal and replacement, re-grading around vaults, concrete removal, and new cast-in-place concrete and rebar work.
Bid Date: 03/03/2022
Utilities-Various Buildings-Fire Detection System
CP number: CP002667
Total Construction Budget: $193,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL INSTALL A FIRE ALARM AND DETECTION SYSTEM FOR AUXILIARY BUILDINGS THAT SUPPORT THE POWER PLANT. THESE BUILDINGS INCLUDE COOLING TOWER SERVICE BUILDING, COOLING TOWER CONTROL BUILDING AND THE VET MED PUMP HOUSE. THE PROJECT WILL CONNECT THE NEW ALARM AND DETECTION SYSTEMS TO EXISTING MASTER FIRE ALARM PANELS LOCATED IN THE MAIN AND VET MED POWER PLANTS.
Utilities-Various Buildings-Fire Detection System
On Hold
Scope number: PS01
Prime contractor: TBD
Project manager: Lee Mason
Construction manager: Lee Mason
Contract description of work:
This project will install a fire alarm and detection system for auxiliary buildings that support the Power Plant. These buildings include Cooling Tower Service Building, Cooling Tower Control Building and the Veterinary Medicine Pump House. The project will connect the new alarm and detection systems to existing master fire alarm panels located in the main and Veterinary Medicine power plants.
Bid Date: TBD
Utilities-Veenker Memorial Golf Course-Well Installation
CP number: CP1161151
Total Construction Budget: $409,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will install a water well and associated small pump house on Veenker Memorial Golf Course to provide water for course irrigation. The new well will replace a recently failed water line running between the main campus and the golf course irrigation pond.
Utilities-Veenker Memorial Golf Course-Well Installation
Design-CD
Scope number: PS01
Construction Budget: $356,000
Prime contractor: TBD
Project manager: Laramie Heuser
Construction manager: Laramie Heuser
Contract description of work:
The project consists of, but is not limited to, the installation of an irrigation well, pump, electrical service and associated piping.
Various Building Automation Improvements FY22
CP number: CP898550
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide for a number of building automation system upgrades for controlling our heating, ventilation, and air conditioning (HVAC) systems.
Various Building Automation Improvements FY22
Complete
Scope number: PS01
Construction Budget: $234,800
Prime contractor: Iowa State University
Project manager: John Netwal
Construction manager: John Netwal
Contract description of work:
This project will provide for a number of building automation system upgrades for controlling our heating, ventilation, and air conditioning (HVAC) systems.
Bid Date: TBD
Various Building Automation Improvements FY23
CP number: CP1087290
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, building automation upgrades for controlling HVAC systems.
Various Building Automation Improvements FY23
Complete
Scope number: PS01
Project manager: John Netwal
Construction manager: John Netwal
Contract description of work:
Bid Date: TBD
Various Building Automation Improvements FY24
CP number: CP1176342
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, building automation upgrades for controlling HVAC systems.
Various Building Automation Improvements FY24
Construction
Scope number: PS01
Construction Budget: $257,666
Prime contractor: Iowa State University
Project manager: John Netwal
Construction manager: John Netwal
Contract description of work:
This project includes, but is not limited to, building automation upgrades for controlling HVAC systems.
Bid Date: TBD
Various Building Safety Improvements FY22
CP number: CP898531
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Various Building Safety Improvements FY22
Complete
Scope number: PS01
Construction Budget: $100,000
Prime contractor: Iowa State University
Project manager: John Netwal
Construction manager: John Netwal
Contract description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Bid Date: TBD
Various Building Safety Improvements FY23
CP number: CP1017209
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Various Building Safety Improvements FY23
Construction
Scope number: PS01
Construction Budget: $100,000
Prime contractor: Multiple Constructors
Project manager: John Netwal
Construction manager: John Netwal
Contract description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Bid Date: TBD
Various Building Safety Improvements FY24
CP number: CP1176353
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Various Building Safety Improvements FY24
Construction
Scope number: PS01
Construction Budget: $90,000
Prime contractor: Iowa State University
Project manager: John Netwal
Construction manager: John Netwal
Contract description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Bid Date: TBD
Various Campus Locations-Ash Tree Removal and Replacement
CP number: CP1105518
Total Construction Budget: $113,330
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the removal of over 100 remaining ash trees and the installation of replacement trees of various varieties on campus. The trees must be removed as all will eventually be killed by the invasive emerald ash borer. The project will allow removal of dying ash trees in areas that are in general-fund maintained areas of campus and the responsibility of the Department of Residence and the Athletic Department.
Various Campus Locations-Ash Tree Removal and Replacement
Complete
Scope number: PS01
Construction Budget: $121,480
Prime contractor: Multiple Constructors
Project manager: Rhonda Martin
Construction manager:
Contract description of work:
This project includes, but is not limited to, the removal of approximately 73 remaining ash trees and the installation of approximately 120 replacement trees of various varieties in general fund maintained areas of central campus.
Bid Date: TBD
Veterinary Medicine-Core Lab-Remodel
CP number: CP987945
Total Construction Budget: $600,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel rooms 1086, 1090, 1092, 1094, 1096, 1234, and 1236 into one Core Lab. This project includes, but is not limited to, replacement of interior finishes, ceiling, electrical power, lighting, mechanical system components, fixed casework, and a new fire alarm system.
Veterinary Medicine-Core Lab-Remodel
Scope number: PS01
Construction Budget: $582,000
Begin construction: 11/16/2022
Occupancy / completion: 06/08/2023
Gross sq.ft.: 1841
Net sq.ft.: 1841
Prime contractor: HPC LLC
Project manager: Mark Grief
Construction manager: Kasi Province
Contract description of work:
The project consists of, but is not limited to, the remodeling of existing laboratory and office space, into a Core Laboratory. This project includes minor demolition, new walls, new doors, finishes and equipment to create the new Core laboratory.
Bid Date: 10/27/2022

Subcontractors (12)

Veterinary Medicine-Domestic Water Line Replacement-Phases 5 and 6
CP number: CP002621
Total Construction Budget: $306,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, removing the old piping system, replacing it with copper piping, and adding additional gate valves to provide for improved zoning of the domestic water service.
Veterinary Medicine-Domestic Water Line Replacement-Phases 5 and 6
Construction
Scope number: PS01
Construction Budget: $266,900
Begin construction: 08/07/2023
Occupancy / completion: 02/24/2024
Prime contractor: ACI MECHANICAL INC
Project manager: Mark Grief
Construction manager: Mick McBride
Contract description of work:
The project consists of, but is not limited to, the extensions to the domestic waterlines and additional piping to facilitate future phases of this project. Provide piping, valves, piping accessories, insulation and other items to complete the system.

Subcontractors (4)

Veterinary Medicine-Room 1330-Remodel
CP number: CP002761
Total Construction Budget: $220,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel an underutilized existing storage space into a kenneling room. This project includes, but is not limited to reconfigure room layout, finish updates, modification of mechanical equipment, piping, and ductwork, and new light fixtures, receptacles, and fire alarm devices.
Veterinary Medicine-Room 1330-Remodel
Scope number: PS01
Construction Budget: $227,700
Begin construction: 02/09/2022
Occupancy / completion: 07/24/2022
Gross sq.ft.: 890
Net sq.ft.: 890
Prime contractor: GTG CONSTRUCTION LLC
Project manager: Mark Grief
Construction manager: Nathan Graves
Contract description of work:
This project will remodel an underutilized existing storage space into a kenneling room. This project includes, but is not limited to, reconfiguration of the room layout, finish updates, modification of mechanical equipment, piping, and ductwork, new light fixtures, receptacles, and fire alarm devices.
Bid Date: 02/03/2022

Subcontractors (6)

Veterinary Medicine-Room 1351-Remodel
CP number: CP930111
Total Construction Budget: $1,557,510
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to demolition of the existing interior horse stalls, new LED lighting and electrical outlets, new finishes, including impervious surfaces, floor, walls, and ceiling in specified areas, mechanical upgrades to maintain a minimum required air changes, and biosafety Level 2 Lab requirement in a small portion of the lab.
Veterinary Medicine-Room 1351-Remodel
Construction
Scope number: PS01
Construction Budget: $1,497,598
Begin construction: 04/24/2023
Occupancy / completion: 02/10/2024
Gross sq.ft.: 2651
Net sq.ft.: 2651
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager: Mark Grief
Construction manager: John Boehmer
Contract description of work:
This project includes, but is not limited to the demolition of the existing interior horse stalls, new LED lighting and electrical outlets, new finishes, including impervious surfaces, floor, walls, and ceiling in specified areas, mechanical upgrades to maintain a minimum required air changes, and biosafety Level 2 Lab requirement in a small portion of the lab.

Subcontractors (15)

Veterinary Medicine-Room 2280-Improvements
CP number: CP998648
Total Construction Budget: $17,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will add new furniture to the Veterinary Medicine Library. The project includes, but is not limited to, electrical work, acoustic screens, dividing panels, booth/banquette seating, tables, and lounge furniture.
Veterinary Medicine-Room 2280-Improvements
Complete
Scope number: PS01
Construction Budget: $17,800
Gross sq.ft.: 5265
Net sq.ft.: 2565
Prime contractor: Multiple Constructors
Project manager: Leigh Wiand
Construction manager: Leigh Wiand
Contract description of work:
This project will add new furniture to the Veterinary Medicine Library. The project includes, but is not limited to, electrical work, acoustic screens, dividing panels, booth/banquette seating, tables, and lounge furniture.
Bid Date: TBD
Veterinary Medicine-Rooms 1222J, 1222K and 1222L-Remodel
CP number: CP1161009
Total Construction Budget: $95,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, remodeling the existing laboratory space. Work to include asbestos abatement, architectural, mechanical, electrical, and fixed equipment.
Veterinary Medicine-Rooms 1222J, 1222K and 1222L-Remodel
Construction
Scope number: PS01
Construction Budget: $95,400
Begin construction: 06/01/2023
Occupancy / completion: 09/01/2023
Gross sq.ft.: 980
Net sq.ft.: 980
Project manager: Josef Biechler
Construction manager: Josef Biechler
Contract description of work:
Veterinary Medicine-Veterinary Diagnostic Laboratory
CP number: CP002554
Total Construction Budget: $56,800,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL CONSTRUCT A NEW TWO-STORY STAND-ALONE VDL ON THE COLLEGE OF VETERINARY MEDICINE CAMPUS TO SERVE THE DIAGNOSTIC MEDICINE NEEDS OF THE IOWA LIVESTOCK AND POULTRY INDUSTRIES, PETS AND WILDLIFE, AND PROTECT HUMAN HEALTH AND IOWA ECONOMY. THE NEW FACILITY WILL ADDRESS THE MOST URGENT SPACE REQUIREMENTS FOR THE LABORATORY, IMPROVE BIOCONTAINMENT, AND ENHANCE BIOSAFETY STANDARDS TO PROTECT EMPLOYEE AND STUDENT HEALTH AS THEY WORK TO PROCESS OVER 90,000 CASES EACH YEAR.
Veterinary Medicine-Veterinary Diagnostic Laboratory
Construction
Scope number: PS01
Construction Budget: $56,800,000
Begin construction: 10/06/2020
Occupancy / completion: 09/21/2023
Gross sq.ft.: 68624
Net sq.ft.: 41200
Prime contractor: WEITZ COMPANY INC
Project manager: David Blum
Construction manager: Nathan Graves
Contract description of work:
The Project consists of, but is not limited to, the design and construction of a new two story stand-alone Veterinary Diagnostic Laboratory (VDL) building on the College of Veterinary Medicine campus. This new facility will serve the diagnostic medicine needs of Iowa livestock and poultry, pets and wildlife, and in the process, protect human health and grow Iowa economy. In addition, the facility will address the most urgent space requirements for the laboratory, improve biocontainment, and enhance biosafety standards to protect employee and student health.
Bid Date: 10/02/2020

Subcontractors (60)

VMRI Building 62-AHU Modifications
CP number: CP1121905
Total Construction Budget: $225,630
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of an additional air handling unit with an outdoor condenser and an exhaust fan system to serve Room 1100.
VMRI Building 62-AHU Modifications
Construction
Scope number: PS01
Construction Budget: $196,200
Begin construction: 08/14/2023
Occupancy / completion: 01/01/2024
Prime contractor: ACI MECHANICAL INC
Project manager: David Blum
Construction manager: John Boehmer
Contract description of work:
This project includes, but is not limited to, the installation of an additional air handling unit with an outdoor condenser and an exhaust fan system to serve Room 1100.

Subcontractors (3)