Current Projects
Loading project list, please wait...
Administrative Services Building-First and Second Floor-Remodel
CP number: CP1260883
Total Construction Budget: $968,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel approximately 42,500 square feet of office and conference room space on the first and second levels of the Administrative Services Building, as well as replace furniture in more than half of the building. The scope of the remodel work includes, but is not limited to, the removal of existing pendant light fixtures, drywall partitions, doors, and transom windows, as well as the removal of the existing ceiling systems. New improvements include creating three additional offices, six team/collaboration rooms, and a dedicated lactation room; updating finishes and furniture; and modifying mechanical, electrical, plumbing, and technology [MEPT] systems as required.
This project will remodel approximately 42,500 square feet of office and conference room space on the first and second levels of the Administrative Services Building, as well as replace furniture in more than half of the building. The scope of the remodel work includes, but is not limited to, the removal of existing pendant light fixtures, drywall partitions, doors, and transom windows, as well as the removal of the existing ceiling systems. New improvements include creating three additional offices, six team/collaboration rooms, and a dedicated lactation room; updating finishes and furniture; and modifying mechanical, electrical, plumbing, and technology [MEPT] systems as required.
Administrative Services Building-First and Second Floor-Remodel
Bid
Scope number: PS01
Construction Budget: $924,000
Begin construction: 03/13/2025
Occupancy / completion: 06/30/2025
Gross sq.ft.: 49465
Net sq.ft.: 42200
Project manager:
Mark Grief
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will remodel approximately 42,500 square feet of office and conference room space on the first and second levels of the Administrative Services Building, as well as replace furniture in more than half of the building. The scope of the remodel work includes, but is not limited to, the removal of existing pendant light fixtures, drywall partitions, doors, and transom windows, as well as the removal of the existing ceiling systems. New improvements include creating three additional offices, six team collaboration rooms, and a dedicated lactation room; updating finishes and furniture; and modifying mechanical, electrical, plumbing, and technology MEPT systems as required.
Administrative Services Building-First and Second Floor-Remodel Bid Date: 02/25/2025
Administrative Services Building-Flood Damage-Repair
CP number: CP1232683
Total Construction Budget: $612,972
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Administrative Services Building-Flood Damage-Repair
Construction
Scope number: PS01
Construction Budget: $723,160
Begin construction: 08/26/2024
Occupancy / completion: 01/19/2025
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will provide clean-up, drying, demolition of damaged materials, and extensive repairs to the existing building. This project includes, but is not limited to, cleaning and dehumidifying the building, removal of damaged materials, and architectural, electrical, and mechanical work. Additional minor alterations will be accomplished concurrently, taking advantage of the opportunity to work in the now vacant spaces.
Administrative Services Building-Flood Damage-Repair Bid Date: TBD
Subcontractors (6)
Administrative Services Building-HVAC System Conversion
CP number: CP002721
Total Construction Budget: $2,301,295
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace the building roof and HVAC system. The HVAC system will be relocated from the roof, replaced in a new mechanical room, and connected to the campus chilled water system. This project includes, but is not limited to: removal of the existing building boilers and roof-top HVAC system, connection to the campus chilled water loop, construction of a mechanical room on the west side of the building, installation of new air handling equipment, boilers, and associated components, and replacement of the existing roof system.
This project will replace the building roof and HVAC system. The HVAC system will be relocated from the roof, replaced in a new mechanical room, and connected to the campus chilled water system. This project includes, but is not limited to: removal of the existing building boilers and roof-top HVAC system, connection to the campus chilled water loop, construction of a mechanical room on the west side of the building, installation of new air handling equipment, boilers, and associated components, and replacement of the existing roof system.
Administrative Services Building-HVAC System Conversion
Scope number: PS01
Construction Budget: $2,356,489
Begin construction: 10/01/2022
Occupancy / completion: 03/05/2024
Gross sq.ft.: 1420
Net sq.ft.: 1420
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Mark Grief
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Contract description of work:
The project consists of, but is not limited to, the replacement of the building roof and removal of the underperforming HVAC system from the roof, replacing it with a new mechanical room building, new energy efficient air handling system, and connection to the adjacent campus chilled water system. This project includes removal of the existing HVAC system, connection to the campus chilled water loop, construction of a new two-story mechanical room on the west side of the building, installation of new air handling equipment, cooling coils and associated components, replacement of the existing ASB roof system, relocation of the existing emergency generator. All the work associated with this will require a phased approach and the new system must be operational prior to the removal of the existing HVAC systems.
Administrative Services Building-HVAC System Conversion Bid Date: 06/23/2022
Subcontractors (15)
Agronomy Hall-Room 1026-Remodel
CP number: CP1237140
Total Construction Budget: $91,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing classroom. The project includes, but is not limited to, removing drapery, projection screen, blackboard, casework, eye wash, lab sinks, piping under cabinets, and flooring. Also included is patching and painting the walls, installing new half inch Gypsum board for the entire north wall and portion of the west wall, new floor tile, and constructing a box to cover the existing pipe.
This project will remodel the existing classroom. The project includes, but is not limited to, removing drapery, projection screen, blackboard, casework, eye wash, lab sinks, piping under cabinets, and flooring. Also included is patching and painting the walls, installing new half inch Gypsum board for the entire north wall and portion of the west wall, new floor tile, and constructing a box to cover the existing pipe.
Agronomy Hall-Room 1026-Remodel
Post Construction
Scope number: PS01
Construction Budget: $80,000
Begin construction: 04/12/2024
Occupancy / completion: 07/19/2024
Gross sq.ft.: 1102
Net sq.ft.: 1102
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Steven Nelson
Construction manager:
Steven Nelson
Design Professional: ISU - FDC
Contract description of work:
Subcontractors (4)
Agronomy Hall-Room 2050-Remodel
CP number: CP1146627
Total Construction Budget: $436,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, remodeling of flooring, lighting, walls, ceilings, and furniture in the existing classroom. Also included are new diffusers, ductwork, and technology upgrades. The classroom is outdated and does not provide adequate seating, electrical outlets, or technology for the users.
This project includes, but is not limited to, remodeling of flooring, lighting, walls, ceilings, and furniture in the existing classroom. Also included are new diffusers, ductwork, and technology upgrades. The classroom is outdated and does not provide adequate seating, electrical outlets, or technology for the users.
Agronomy Hall-Room 2050-Remodel
Scope number: PS01
Construction Budget: $444,234
Begin construction: 12/20/2023
Occupancy / completion: 08/02/2024
Gross sq.ft.: 1800
Net sq.ft.: 1800
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Hayley Sandholm
Construction manager:
Steven Nelson
Design Professional: FREVERT-RAMSEY-KOBES ARCHITECT
Contract description of work:
This project includes, but is not limited to, remodeling of flooring, lighting, walls, ceilings, and furniture in the existing classroom. Also included are new diffusers, ductwork, and technology upgrades.
Subcontractors (11)
Agronomy Hall-Room B0515-Dehumidification Unit-Replacement
CP number: CP1201187
Total Construction Budget: $100,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Agronomy Hall-Room B0515-Dehumidification Unit-Replacement
Post Construction
Scope number: PS01
Construction Budget: $80,450
Begin construction: 03/27/2024
Occupancy / completion: 08/09/2024
Gross sq.ft.: 1626
Net sq.ft.: 1626
Prime contractor: MECHANICAL COMFORT INC
Project manager:
Hayley Sandholm
Construction manager:
Mick McBride
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the replacement of the existing single dehumidification unit with two new dehumidification units to provide a 100% redundant system. Dehumidifiers will be racked on the floor in a similar arrangement to the condensing units on the third floor.
Subcontractors (4)
Armstrong Memorial Research and Demonstration Farm-Machine Storage Building
CP number: CP1164931
Total Construction Budget: $319,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, design and construction of a machine storage building. The building will be approximately 7200 gsf and have metal roofing and siding.
This project includes, but is not limited to, design and construction of a machine storage building. The building will be approximately 7200 gsf and have metal roofing and siding.
Armstrong Memorial Research and Demonstration Farm-Machine Storage Building
Post Construction
Scope number: PS01
Construction Budget: $254,000
Begin construction: 10/30/2023
Occupancy / completion: 04/27/2024
Gross sq.ft.: 7200
Net sq.ft.: 7200
Prime contractor: PRO LINE BUILDING COMPANY
Project manager:
Mark Huss
Construction manager:
Mick McBride
Design Professional: I&S GROUP INC
Contract description of work:
The project consists of, but is not limited to, design and construction of a machine storage building. The building will be approximately 7,200 gsf, will be post frame construction, and will have metal roofing and siding.
Subcontractors (1)
Barton Residence Hall-Window Replacement
CP number: CP002483
Total Construction Budget: $580,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Project scope as follows: provide abatement and monitoring services, remove and replace windows, remove and replace associated window sealants and replace blinds.
Project scope as follows: provide abatement and monitoring services, remove and replace windows, remove and replace associated window sealants and replace blinds.
Barton Residence Hall-Window Replacement
On Hold
Scope number: PS01
Construction Budget: $549,900
Begin construction: 03/13/2020
Occupancy / completion: 02/28/2020
Prime contractor: WILSON GROUP INC
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
The project consists of, but is not limited to, the replacement of approximately 118 windows.
Barton Residence Hall-Window Replacement Bid Date: 02/27/2019
Subcontractors (2)
Beardshear Hall-Room 1350-Remodel
CP number: CP1095296
Total Construction Budget: $790,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, remodeling the existing office suite and adjacent treasurer's office. The existing conference room will be expanded, individual office spaces will be created, and the interior finishes updated.
This project includes, but is not limited to, remodeling the existing office suite and adjacent treasurer's office. The existing conference room will be expanded, individual office spaces will be created, and the interior finishes updated.
Beardshear Hall-Room 1350-Remodel
Post Construction
Scope number: PS01
Construction Budget: $713,350
Begin construction: 08/17/2023
Occupancy / completion: 01/26/2024
Gross sq.ft.: 4000
Net sq.ft.: 4000
Prime contractor: GREINER CONSTRUCTION INC
Project manager:
Hayley Sandholm
Construction manager:
Barton Dobson
Design Professional: BROOKS BORG SKILES ARCH ENGR
Contract description of work:
This project includes, but is not limited to, remodeling the existing office suite and adjacent treasurer's office. The existing conference room will be expanded, individual office spaces will be created, and the interior finishes updated.
Subcontractors (12)
Beardshear Hall-Room 3150-Conference Room Furniture and AV
CP number: CP1258948
Total Construction Budget: $25,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Beardshear Hall-Room 3150-Conference Room Furniture and AV
Construction
Scope number: PS01
Begin construction: 11/05/2024
Occupancy / completion: 05/05/2025
Gross sq.ft.: 706
Net sq.ft.: 706
Prime contractor: Multiple Constructors
Project manager:
Mitchell Hlavacek
Construction manager:
Mitchell Hlavacek
Design Professional: ISU - FDC
Contract description of work:
This project will renovate the conference room in Beardshear 3150. The scope includes, but is not limited to, replacing carpet, purchasing a new conference table and chairs, and new audio/visual equipment.
Beardshear Hall-Room 3150-Conference Room Furniture and AV Bid Date:
Beardshear Hall-Window Repairs-Phase 1
CP number: CP1119832
Total Construction Budget: $327,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Beardshear Hall-Window Repairs-Phase 1
Post Construction
Scope number: PS01
Construction Budget: $173,050
Begin construction: 03/28/2024
Occupancy / completion: 10/10/2024
Prime contractor: MTP SOLUTIONS LLC
Project manager:
Jennifer Evans
Construction manager:
Ben Haywood
Design Professional: BROOKS BORG SKILES ARCH ENGR
Contract description of work:
This project includes, but is not limited to, the restoration of existing wood windows and door frames at Beardshear Hall. All loose paint will be scraped off and any holes, splits, and damage to the existing wood frames will be patched and repaired to match existing shapes and sizes. The restoration includes professional repainting with premium exterior wood primer and paint. The existing original paint on the frames contains lead so all contractors working on this project will be required to adhere to the EPA Renovation, Repair, and Painting rule, which requires Lead Safe Work Practices.
Subcontractors (1)
Bergstrom Indoor Training Facility-LED Lighting Upgrades
CP number: CP002599
Total Construction Budget: $464,630
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Bergstrom Indoor Training Facility-LED Lighting Upgrades
Final Reporting
Scope number: PS01
Begin construction: 02/28/2020
Occupancy / completion: 03/31/2020
Prime contractor: Multiple Constructors
Project manager:
Jonathan Harvey
Construction manager:
John Boehmer
Design Professional: ISU
Contract description of work:
This project will convert the indoor lighting of Bergstrom indoor practice facility to led. Project will remove the existing lighting and replace with new color changing led lights. This will increase the overall light levels to an average of 70 fc (foot candles).
Bergstrom Indoor Training Facility-LED Lighting Upgrades Bid Date:
Beyer Hall-Room 2500-Remodel
CP number: CP942796
Total Construction Budget: $224,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, removal of existing partial 5 foot high raised floor, installation of a new 6 foot high raised floor, constructing landing pits deep enough to help prevent injuries, and providing stairs and a ramp to existing doors.
This project includes, but is not limited to, removal of existing partial 5 foot high raised floor, installation of a new 6 foot high raised floor, constructing landing pits deep enough to help prevent injuries, and providing stairs and a ramp to existing doors.
Beyer Hall-Room 2500-Remodel
Design-CD
Scope number: PS01
Construction Budget: $204,000
Begin construction: 05/25/2023
Occupancy / completion: 09/29/2023
Gross sq.ft.: 1324
Net sq.ft.: 1324
Project manager:
Jonathan Harvey
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Contract description of work:
The project consists of, but is not limited to, demolition of partial raised floor; installation of new raised floor, stairs, and ramp; new electrical; and renovation of existing mechanical duct system.
Beyer Hall-Swimming Pool Repairs-Phase 2
CP number: CP1250785
Total Construction Budget: $583,440
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Beyer Hall-Swimming Pool Repairs-Phase 2
Construction
Scope number: PS01
Construction Budget: $541,576
Begin construction: 01/03/2025
Occupancy / completion: 08/11/2025
Gross sq.ft.: 135537
Net sq.ft.: 135537
Prime contractor: PLEVA PLUMBING & HEATING INC
Project manager:
Mark Grief
Construction manager:
Steven Nelson
Contract description of work:
This project includes, but is not limited to, repairs to the existing Beyer Hall swimming pool equipment. Work includes capping the surge tank to prevent chloramine gas from entering the equipment room, and the replacement of the above-ground pool piping, circulation and drain pumps, and the sand filtration system.
Beyer Hall-Swimming Pool-Electrical Repairs
CP number: CP1200878
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Beyer Hall-Swimming Pool-Electrical Repairs
Design-CD
Scope number: PS01
Begin construction: 11/30/2024
Project manager:
Mark Grief
Construction manager:
Steven Nelson
Design Professional: BROOKS BORG SKILES ARCH ENGR
Contract description of work:
This project includes, but is not limited to, the replacement of conduits, electrical panels, and components that service Beyer Hall and Theilen Student Health Center. The first phase will involve rebuilding conduits and rerouting them in mechanical rooms away from the chlorine gas with PVC/EMT conduit and replacing the M2 panel. Phase 2 will entail replacing conduits that cannot be redirected and will stay in regions affected by chlorine gas with a PVC/RMC conduit and replacing the panel that serves Thielen Student Health Center. Additional work not connected to either phase will replace electrical panels LH and DP-2.
Beyer Hall-Swimming Pool-Electrical Repairs Bid Date: 03/27/2025 (Tentative)
BioCentury Research Farm-AHU1-Modifications
CP number: CP002759
Total Construction Budget: $36,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
BioCentury Research Farm-AHU1-Modifications
Construction
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Design Professional: RESOURCE CONSULTING ENGINEERS
Contract description of work:
This project includes, but is not limited to, modifications to air handler unit 1 (AHU1) serving the main building for the BioCentury Research Farm.
BioCentury Research Farm-AHU1-Modifications Bid Date:
Birch, Welch, and Roberts Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
CP number: CP1001532
Total Construction Budget: $46,200
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of a new sub-drain along the south exterior wall of Welch Hall and the west exterior wall of Birch Hall within the south courtyard, which will be connected to a new area intake. There will be an additional storm pipe connecting the new intake to an existing manhole. On the west side of the courtyard, the area of an existing intake will be regraded and the intake itself removed and replaced at a lower elevation to help move water away from the sidewalk. Additional work to include tree trimming and removal and the site grading for improved drainage.
This project includes, but is not limited to, the installation of a new sub-drain along the south exterior wall of Welch Hall and the west exterior wall of Birch Hall within the south courtyard, which will be connected to a new area intake. There will be an additional storm pipe connecting the new intake to an existing manhole. On the west side of the courtyard, the area of an existing intake will be regraded and the intake itself removed and replaced at a lower elevation to help move water away from the sidewalk. Additional work to include tree trimming and removal and the site grading for improved drainage.
Birch, Welch, and Roberts Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
Construction
Scope number: PS01
Construction Budget: $48,300
Begin construction: 03/19/2024
Occupancy / completion: 07/26/2024
Prime contractor: LENZ CONSTRUCTION LLC
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
This project includes, but is not limited, to installation of new sub drain along the south exterior wall of Welch Hall and west exterior wall of Birch Hall, within the south courtyard. This new sub drain will be connected to a new area intake. There will be additional storm pipe connecting the new intake to an existing manhole. On the west side of the courtyard, the area of an existing intake will be regraded, the intake itself removed and replaced at a lower elevation to help move water away from the sidewalk. The entire site will be regraded for improved drainage.
Black Engineering-Emergency Power Transfer Switch-Replacement
CP number: CP002649
Total Construction Budget: $234,890
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Black Engineering-Emergency Power Transfer Switch-Replacement
Construction
Scope number: PS01
Construction Budget: $216,820
Begin construction: 01/03/2024
Occupancy / completion: 07/26/2024
Prime contractor: JASPERING ELECTRIC INC
Project manager:
David Blum
Construction manager:
Steven Nelson
Design Professional: MODUS ENGINEERING LTD
Contract description of work:
This project will install one or more new emergency and standby power transfer switches, associated cabling, and new electrical distribution equipment to replace the existing transfer switch and existing electrical distribution equipment in their current location in the basement main electrical room of Black Engineering.
Black Engineering-Room 1056-Remodel
CP number: CP1232074
Total Construction Budget: $368,280
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel room 1056 in Black Engineering to remove obsolete equipment and install the air handler unit being removed from LeBaron Hall. The project includes, but is not limited to, new ductwork and electrical, a new exhaust fan, gas connections, a toxic gas cabinet, and refinishing the floor.
This project will remodel room 1056 in Black Engineering to remove obsolete equipment and install the air handler unit being removed from LeBaron Hall. The project includes, but is not limited to, new ductwork and electrical, a new exhaust fan, gas connections, a toxic gas cabinet, and refinishing the floor.
Black Engineering-Room 1056-Remodel
On Hold
Scope number: PS01
Construction Budget: $334,800
Begin construction: 11/14/2024
Gross sq.ft.: 1000
Net sq.ft.: 1000
Project manager:
Joshua Dank
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Contract description of work:
This project will remodel room 1056 in Black Engineering to remove obsolete equipment and install a new air handler unit. The project includes, but is not limited to, new ductwork and electrical, a new exhaust fan, gas connections, a toxic gas cabinet, and refinishing the floor.
BLACK-Room 2103-Fume Hood
CP number: PR897963
Total Construction Budget: $78,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Install new fume hood with acid and flammables base cabinet
Install new fume hood with acid and flammables base cabinet
Black Engineering-Room 2103-Fume Hood Installation
Bid
Scope number: PS01
Construction Budget: $78,700
Occupancy / completion: 03/31/2025
Gross sq.ft.: 649
Net sq.ft.: 649
Project manager:
Mitchell Hlavacek
Construction manager:
Mitchell Hlavacek
Design Professional: ISU - FDC
Contract description of work:
Scope of work includes the installation of a new fume hood and ductwork. Includes, but not limited to: architecture, electrical, mechanical, and controls work. See design documents for full scope of work.
Black Engineering-Room 2103-Fume Hood Installation Bid Date: 01/27/2025
Bruce McKee Indoor Tennis Complex-Remodel
CP number: CP1105475
Total Construction Budget: $3,300,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The McKee Indoor Tennis Complex will become available with the relocation of the Tennis program to a new location. Through renovation, this space will meet the needs of the Volleyball program with two practice courts, locker room, coaches and staff offices, team room, and training room. The project will relocate the building entrance from the northwest corner of the building to the west side. The mechanical and electrical systems, graphics and wayfinding will be upgraded to meet the needs of the new occupants.
The McKee Indoor Tennis Complex will become available with the relocation of the Tennis program to a new location. Through renovation, this space will meet the needs of the Volleyball program with two practice courts, locker room, coaches and staff offices, team room, and training room. The project will relocate the building entrance from the northwest corner of the building to the west side. The mechanical and electrical systems, graphics and wayfinding will be upgraded to meet the needs of the new occupants.
Bruce McKee Indoor Tennis Complex-Remodel
Construction
Scope number: PS01
Construction Budget: $3,140,000
Begin construction: 05/22/2024
Occupancy / completion: 03/18/2025
Gross sq.ft.: 18400
Net sq.ft.: 16105
Prime contractor: ESTES CONSTRUCTION
Project manager:
Jonathan Harvey
Construction manager:
Ben Haywood
Design Professional: SUBSTANCE ARCHITECTURE
Contract description of work:
The McKee Indoor Tennis Complex will become available with the relocation of the Tennis program to a new location. Through renovation, this space will meet the needs of the Volleyball program with two practice courts, locker room, coaches and staff offices, team room, and training room. The project will relocate the building entrance from the northwest corner of the building to the west side. The mechanical and electrical systems, graphics and wayfinding will be upgraded to meet the needs of the new occupants.
Subcontractors (30)
Carver Hall-Fire System Standpipes-Improvements
CP number: CP917640
Total Construction Budget: $538,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of four Class 1 fire system standpipes to serve the building, a new fire hydrant, and a new fire department connection on the east side of the building. The northwest standpipe will have tamper switch valves for a future sprinkler system.
This project includes, but is not limited to, the installation of four Class 1 fire system standpipes to serve the building, a new fire hydrant, and a new fire department connection on the east side of the building. The northwest standpipe will have tamper switch valves for a future sprinkler system.
Carver Hall-Fire System Standpipes-Improvements
Post Construction
Scope number: PS01
Construction Budget: $494,927
Begin construction: 08/04/2023
Occupancy / completion: 06/11/2024
Gross sq.ft.: 133500
Net sq.ft.: 133500
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Hayley Sandholm
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Contract description of work:
The project consists of, but is not limited to, the installation of four Class 1 fire system standpipes to serve the building, a new fire hydrant, and a new fire department connection on the east side of the building. The northwest standpipe will have tamper switch valves for a future sprinkler system.
Subcontractors (3)
Carver Hall-Room 0060-Remodel
CP number: CP1226572
Total Construction Budget: $159,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Carver Hall-Room 0060-Remodel
Scope number: PS01
Construction Budget: $314,165
Begin construction: 05/15/2024
Occupancy / completion: 08/15/2024
Gross sq.ft.: 1620
Net sq.ft.: 1480
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Jonathan Harvey
Construction manager:
Ben Haywood
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, remodeling the current space including new finishes, lighting, and testing tables.
Subcontractors (9)
Central Receiving Facility-University Museums Compact Storage Unit-Improvements
CP number: CP1261323
Total Construction Budget: $118,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Central Receiving Facility-University Museums Compact Storage Unit-Improvements
Construction
Scope number: PS01
Begin construction: 01/17/2025
Occupancy / completion: 07/18/2025
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU
Contract description of work:
This project will remove existing shelves, install two new light fixtures, and install new space saver storage unit. The scope of work includes, but is not limited to architectural and electrical work.
Central Receiving Facility-University Museums Compact Storage Unit-Improvements Bid Date:
College of Design-Faculty Offices-Remodel
CP number: CP990455
Total Construction Budget: $574,780
includes the bid estimate and contingency for this scope of work
Overall project description of work:
College of Design-Faculty Offices-Remodel
Scope number: PS01
Construction Budget: $590,595
Begin construction: 04/12/2024
Occupancy / completion: 07/31/2024
Gross sq.ft.: 13100
Net sq.ft.: 13100
Prime contractor: DSM PROPERTY SERVICES LLC
Project manager:
David Blum
Construction manager:
Ben Haywood
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the improvement of faculty office utilization in the College of Design. This project would provide for remodeling of faculty working environments and improve the types of spaces that could support faculty through single offices, double offices, and collaboration spaces. Architectural and interior design services will be provided to review office furniture configurations and interior finish updates at these spaces.
Subcontractors (5)
Communications Building-Suite 1200-Remodel
CP number: CP1253073
Total Construction Budget: $224,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel approximately 4,100 GSF in Communications Building Suite 1200, including rooms 1211, 1226, and 1227. Work includes, but is not limited to, demolition, construction, mechanical and electrical improvements, paint, carpet, lighting, and furniture.
This project will remodel approximately 4,100 GSF in Communications Building Suite 1200, including rooms 1211, 1226, and 1227. Work includes, but is not limited to, demolition, construction, mechanical and electrical improvements, paint, carpet, lighting, and furniture.
Communications Building-Suite 1200-Remodel
Design-CD
Scope number: PS01
Project manager:
Angela Solberg
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Contract description of work:
Communications Building-Suite 1200-Remodel Bid Date: 02/2025 (Upcoming)
Coover Hall-Common Area Improvements
CP number: CP1175190
Total Construction Budget: $460,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Coover Hall-Common Area Improvements
Construction
Scope number: PS01
Construction Budget: $468,185
Begin construction: 11/08/2024
Occupancy / completion: 03/08/2025
Gross sq.ft.: 5000
Net sq.ft.: 5000
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Joshua Dank
Construction manager:
Mick McBride
Design Professional: OFFICE OF HARTMAN SPILLER TRAPP
Contract description of work:
This project includes, but is not limited to, updating finishes, lighting, wall graphics, and spatial configuration to improve visitor and occupant perceptions of the space.
Subcontractors (9)
Curtiss Farm-Feed Mill and Grain Science Complex
CP number: CP002509
Total Construction Budget: $24,810,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project is constructing a feed mill and grain science facility with all associated site work, site utilities, grain storage, and feed processing equipment. The project also includes educational and warehouse space. This facility will replace three existing, outdated feed mills. The complex will help address significant needs of the Iowa agricultural industry. There is a shortfall of skilled employees for grain and feed facilities, which this complex will help address with new educational programs, as well as research and extension programs. This complex will enhance education and research, while concurrently providing the custom, diverse feeds required for university livestock. The project is located on the university Curtiss Farm, south of US Highway 30 in Ames.
The project is constructing a feed mill and grain science facility with all associated site work, site utilities, grain storage, and feed processing equipment. The project also includes educational and warehouse space. This facility will replace three existing, outdated feed mills. The complex will help address significant needs of the Iowa agricultural industry. There is a shortfall of skilled employees for grain and feed facilities, which this complex will help address with new educational programs, as well as research and extension programs. This complex will enhance education and research, while concurrently providing the custom, diverse feeds required for university livestock. The project is located on the university Curtiss Farm, south of US Highway 30 in Ames.
Curtiss Farm-Feed Mill and Grain Science Complex
Curtiss Farm-Feed Mill and Grain Science Complex-Grain Center Control Building-Build-Out
Post Construction
Curtiss Farm-Plant and Seed Facility-Remodel
CP number: CP002660
Total Construction Budget: $320,870
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Curtiss Farm-Plant and Seed Facility-Remodel
Construction
Scope number: PS01
Construction Budget: $320,861
Begin construction: 08/23/2024
Occupancy / completion: 01/20/2025
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Joshua Dank
Construction manager:
Troy Chandler
Design Professional: CANNON MOSS BRYGGER & ASSOC
Contract description of work:
This project will consist of an addition to or partitioning of space currently used by the Plant Sciences Institute in order to separate critical drying activities for research. The project includes, but is not limited to, finish, mechanical, and equipment upgrades as needed.
Subcontractors (11)
CYTown-Parking and Infrastructure Improvements
CP number: CP1004288
Total Construction Budget: $25,000,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, construction of replacement parking with new lighting and installation of underground infrastructure, which would include new water, power, gas, telecommunications, storm sewer, and sanitary lines to support future development. The project would also relocate the CyRide Transit Hub and raise a portion of the site above 100-year flood plain of Ioway Creek.
This project includes, but is not limited to, construction of replacement parking with new lighting and installation of underground infrastructure, which would include new water, power, gas, telecommunications, storm sewer, and sanitary lines to support future development. The project would also relocate the CyRide Transit Hub and raise a portion of the site above 100-year flood plain of Ioway Creek.
CYTown-Parking and Infrastructure Improvements
CYTown-Parking and Infrastructure Improvements-CyRide Transit Hub
Design-CD
CYTown-Parking and Infrastructure Improvements-Parking Lot B5
Bid
CYTown-Parking and Infrastructure-Phase 2
Construction
Department of Residence-Freight Elevator Decommissioning 2024
CP number: CP1236156
Total Construction Budget: $150,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Department of Residence-Freight Elevator Decommissioning 2024
Construction
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Design Professional: ISU - Department of Residence
Contract description of work:
This project includes, but is not limited to, the decommissioning of six freight elevators in the Department of Residence buildings and the removal of the equipment. The freight elevators are located in Oak-Elm, Barton, Lyon, Freeman, and two in Linden.
Department of Residence-Freight Elevator Decommissioning 2024 Bid Date:
Design-Rooms 503, 507, 511, 516, and 516A-323907-Remodel
CP number: PR1201601
Total Construction Budget: $62,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Design 5th floor Studio; rooms 503,507,511,516 Most important in order Patched flooring (some tripping hazards) Exit signage, lights and crashbars Sprinkling (if required) Headers rebuilt Drywall patched Cabinets replaced (may be able to cut down on the number of sinks and cabinets…add tub type sinks with traps) This project began in Famis Classic under PR018876-Design 5th floor Studio
Design 5th floor Studio; rooms 503,507,511,516 Most important in order Patched flooring (some tripping hazards) Exit signage, lights and crashbars Sprinkling (if required) Headers rebuilt Drywall patched Cabinets replaced (may be able to cut down on the number of sinks and cabinets…add tub type sinks with traps) This project began in Famis Classic under PR018876-Design 5th floor Studio
College of Design-Rooms 503, 507, 511, 516, and 516A-Remodel
Construction
Scope number: PS01
Construction Budget: $62,000
Begin construction: 06/04/2024
Occupancy / completion: 08/02/2024
Gross sq.ft.: 4400
Net sq.ft.: 4400
Prime contractor: BOONE CONSTRUCTION INC
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Contract description of work:
Subcontractors (5)
East of University Boulevard Site Improvements-Recreation Services
CP number: CP002439
Total Construction Budget: $7,506,320
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL RENOVATE THE EXISTING SOUTHEAST RECREATION COMPLEX LOCATED EAST OF UNIVERSITY BOULEVARD BETWEEN SOUTH 4TH AND SOUTH 16TH STREETS. THIS RENOVATION OF THE EXISTING COMPLEX WILL ILLUMINATE THE PLAYING FIELDS TO LIGHTING LEVELS RECOMMENDED FOR SPORT CLUBS AND AMATEUR FACILITIES, PROVIDE IRRIGATION, IMPROVE FIELD DRAINAGE, PLAYING SURFACE DURABILITY, AND MAINTAINABILITY.
THIS PROJECT WILL RENOVATE THE EXISTING SOUTHEAST RECREATION COMPLEX LOCATED EAST OF UNIVERSITY BOULEVARD BETWEEN SOUTH 4TH AND SOUTH 16TH STREETS. THIS RENOVATION OF THE EXISTING COMPLEX WILL ILLUMINATE THE PLAYING FIELDS TO LIGHTING LEVELS RECOMMENDED FOR SPORT CLUBS AND AMATEUR FACILITIES, PROVIDE IRRIGATION, IMPROVE FIELD DRAINAGE, PLAYING SURFACE DURABILITY, AND MAINTAINABILITY.
East of University Boulevard Site Improvements-Recreation Services-Foot Wash
Design-CD
Scope number: PS05
Construction Budget: $78,000
Gross sq.ft.: 140
Net sq.ft.: 140
Project manager:
Hayley Sandholm
Construction manager:
Troy Chandler
Design Professional: ISU - FDC
Contract description of work:
Project scope includes adding a foot wash station to the sand volleyball courts.
Family Resource Center-Remodel
CP number: CP1008443
Total Construction Budget: $304,350
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the replacement of heating and cooling units, removal of vinyl floor tile and replace with new flooring, removal of plastic laminate countertops and replacement with solid surface countertops, replace damaged base cabinet doors, modification of kitchen cabinets for a new oven range and hood, installation of a garbage disposal, replacement of fiberglass reinforced panels in room 1053, refinishing wood windowsills, painting rooms, repairs to EIFS and miscellaneous masonry damage, cleaning the exterior, and replacement of exterior sealant joints.
This project includes, but is not limited to, the replacement of heating and cooling units, removal of vinyl floor tile and replace with new flooring, removal of plastic laminate countertops and replacement with solid surface countertops, replace damaged base cabinet doors, modification of kitchen cabinets for a new oven range and hood, installation of a garbage disposal, replacement of fiberglass reinforced panels in room 1053, refinishing wood windowsills, painting rooms, repairs to EIFS and miscellaneous masonry damage, cleaning the exterior, and replacement of exterior sealant joints.
Family Resource Center-Remodel
Final Reporting
Family Resource Center-Remodel-Life Cycle Improvements
Construction
Frederiksen Court Community Center-RTU-Replacement
CP number: CP1243665
Total Construction Budget: $224,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Frederiksen Court Community Center-RTU-Replacement
Construction
Scope number: PS01
Construction Budget: $218,880
Begin construction: 07/16/2024
Occupancy / completion: 12/13/2024
Prime contractor: MECHANICAL COMFORT INC
Project manager:
Mark Huss
Construction manager:
Danelda Allen
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the replacement of six RTUs at the Frederiksen Court Community Center.
Subcontractors (5)
Frederiksen Court-Buildings 71 and 74-Life Cycle Improvements
CP number: CP1238119
Total Construction Budget: $580,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Frederiksen Court-Buildings 71 and 74-Life Cycle Improvements
Final Reporting
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Design Professional: ISU - Department of Residence
Contract description of work:
This project includes, but is not limited to, replacing the carpet and VCT in the apartment bedrooms, living rooms, and kitchens. The VCT and/or sheet vinyl in the bathrooms will be replaced with sheet vinyl. The carpet and VCT in the corridors will be replaced with carpet tile and rubber tile. The stairway flooring will be replaced with rubber tile and treads. Some plumbing fixtures will be replaced. The apartments, corridors, and stairways walls and ceilings will be patched and painted.
Frederiksen Court-Buildings 71 and 74-Life Cycle Improvements Bid Date:
Friley Residence Hall-Bathroom Improvements
CP number: CP002724
Total Construction Budget: $13,300,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL REMODEL THE BATHROOMS IN FRILEY RESIDENCE HALL, CONVERTING THEM TO PRIVATE, MORE ACCESSIBLE SPACES. THE WORK WILL ALSO INCLUDE MECHANICAL, ELECTRICAL AND PLUMBING SYSTEMS ALONG WITH INTERIOR FINISHES.THIS PROJECT WILL BE COMPLETED IN PHASES OVER THE NEXT FOUR CONSECUTIVE SUMMERS.
THIS PROJECT WILL REMODEL THE BATHROOMS IN FRILEY RESIDENCE HALL, CONVERTING THEM TO PRIVATE, MORE ACCESSIBLE SPACES. THE WORK WILL ALSO INCLUDE MECHANICAL, ELECTRICAL AND PLUMBING SYSTEMS ALONG WITH INTERIOR FINISHES.THIS PROJECT WILL BE COMPLETED IN PHASES OVER THE NEXT FOUR CONSECUTIVE SUMMERS.
Friley Residence Hall-Bathroom Improvements-Locations 7 & 8
Friley Residence Hall-Bathroom Improvements-Stack A
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack B
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack C
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack D
Design-CD
Friley Residence Hall-Bathroom Improvements-Stack E, Stack F & Stack G
Construction
Friley Residence Hall-Bathroom Improvements-Stack H
Design-CD
Friley Residence Hall-Courtyard Roof-Improvements
CP number: CP1000679
Total Construction Budget: $990,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The Friley Residence Hall courtyard is both an outdoor seating area and a structural roof over food service and dining areas below the courtyard. The courtyard consists of a concrete deck, which is now deteriorated. This project includes, but is not limited to, repairs to the deck and installing a new protective waterproof membrane. A new pedestal-mounted paver system will be installed over the membrane to provide a courtyard walking surface.
The Friley Residence Hall courtyard is both an outdoor seating area and a structural roof over food service and dining areas below the courtyard. The courtyard consists of a concrete deck, which is now deteriorated. This project includes, but is not limited to, repairs to the deck and installing a new protective waterproof membrane. A new pedestal-mounted paver system will be installed over the membrane to provide a courtyard walking surface.
Friley Residence Hall-Courtyard Roof-Improvements
Post Construction
Scope number: PS01
Construction Budget: $1,055,000
Begin construction: 02/29/2024
Occupancy / completion: 07/26/2024
Prime contractor: BALL TEAM LLC
Project manager:
Angela Solberg
Construction manager:
Mick McBride
Design Professional: SCHEMMER ASSOC INC
Contract description of work:
The Friley Residence Hall courtyard area is both an outdoor seating area and a structural roof over food service and dining areas below the courtyard. The courtyard consists of a concrete deck, which is now deteriorated. This project includes, but is not limited to, repairs to the deck and the installation of a new protective waterproof membrane. A new pedestal mounted paver system will be installed over the membrane to provide a courtyard walking surface.
Subcontractors (13)
General Services Building-AHU12-Replacement
CP number: CP1191717
Total Construction Budget: $205,130
includes the bid estimate and contingency for this scope of work
Overall project description of work:
General Services Building-AHU12-Replacement
Bid
Scope number: PS01
Construction Budget: $165,000
Occupancy / completion: 08/03/2025
Gross sq.ft.: 1000
Net sq.ft.: 1000
Project manager:
Hayley Sandholm
Construction manager:
Troy Chandler
Design Professional: RESOURCE CONSULTING ENGINEERS
Contract description of work:
This project includes but is not limited to the replacement of Air Handling Unit 12 (AHU12), including associated plumbing, ductwork, electrical service, insulation, and controls. This unit provides heating, cooling, and limited ventilation to several workspaces.
General Services Building-AHU12-Replacement Bid Date: 02/20/2025
Gilman Hall-Electrical Panel Replacement-Phase 2
CP number: CP002651
Total Construction Budget: $436,610
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Gilman Hall-Electrical Panel Replacement-Phase 2
Construction
Scope number: PS01
Construction Budget: $436,620
Begin construction: 10/28/2024
Occupancy / completion: 07/31/2025
Gross sq.ft.: 0
Net sq.ft.: 0
Prime contractor: VAN MAANEN ELECTRIC INC
Project manager:
David Blum
Construction manager:
Steven Nelson
Design Professional: MODUS ENGINEERING LTD
Contract description of work:
The project will replace outdated electrical panels in Gilman Hall with serviceable fully supported equipment and install new electrical distribution equipment and feeders. This project will also begin to remove and replace electrical equipment feeder sources that cross between original Gilman Hall and 1964 Gilman Addition.
Subcontractors (1)
Gilman Hall-Wayfinding and Signage-Improvements
CP number: CP1010532
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Gilman Hall-Wayfinding and Signage-Improvements
On Hold
Scope number: PS01
Construction Budget: $208,000
Prime contractor: Multiple Constructors
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to evaluation of existing building signage to determine exact quantity, correct numbering and notable space labeling for installation of new room signage. At applicable locations, existing room signage will be removed and wall surfaces will be patched and repaired ready for installation of new, accessible room signage.
Gilman Hall-Wayfinding and Signage-Improvements Bid Date:
HACH-0204-356387-Lab Equipment Relocation & Electric
CP number: PR1241449
Total Construction Budget: $63,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Modifications to both the 3rd floor lab (minimal, if any) and the basement lab regarding equipment that needs to be relocated from one floor to another at Hach Hall. The basement lab room 0204 spare electrical circuit availability in panels R2BF and R2BF (sec2) is very limited (8 open circuits total) for future use.
Modifications to both the 3rd floor lab (minimal, if any) and the basement lab regarding equipment that needs to be relocated from one floor to another at Hach Hall. The basement lab room 0204 spare electrical circuit availability in panels R2BF and R2BF (sec2) is very limited (8 open circuits total) for future use.
Hach Hall-Room 0204-Remodel
Construction
Scope number: PS01
Construction Budget: $63,900
Begin construction: 12/03/2024
Occupancy / completion: 02/01/2025
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Contract description of work:
Subcontractors (2)
Heady Hall-Room 0382-Remodel
CP number: CP1250226
Total Construction Budget: $121,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Heady Hall-Room 0382-Remodel
Construction
Scope number: PS01
Construction Budget: $126,635
Begin construction: 10/18/2024
Occupancy / completion: 03/17/2025
Gross sq.ft.: 640
Net sq.ft.: 640
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Joshua Dank
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Contract description of work:
This project will remodel rooms 0382, 0382A, 0382B and 0382C. The project includes, but is not limited to architectural, mechanical, electrical, technology, equipment, finishes, and furniture.
Subcontractors (10)
Helser Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
CP number: CP1001574
Total Construction Budget: $82,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, exterior regrading, waterproofing, and sidewalk repair on the northwest corner of Helser Residence Hall between Helser and Eaton Hall. This will include some interior wall repairs. Smaller areas around the building will have regrading and sidewalk repair completed.
This project includes, but is not limited to, exterior regrading, waterproofing, and sidewalk repair on the northwest corner of Helser Residence Hall between Helser and Eaton Hall. This will include some interior wall repairs. Smaller areas around the building will have regrading and sidewalk repair completed.
Helser Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
Construction
Scope number: PS01
Construction Budget: $78,750
Begin construction: 03/20/2024
Occupancy / completion: 07/26/2024
Prime contractor: ELDER CORP
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
This project includes, but is not limited to, installation of additional area drains and new storm pipe to help divert water away from the north west entrance door of Helser Hall and lower level window wells along the north side of the building. A portion of an existing sidewalk will be removed and replaced to meet ADA slope requirements and to prevent water from ponding. Rock bed will be used for erosion protection and to keep water from collecting against face of the building. The area of Work will be regraded for overall improved
Subcontractors (2)
Hilton Coliseum-Rooms 0176, 0176A, 0188, and 0188A-Renovation
CP number: CP964884
Total Construction Budget: $810,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to new lockers, new flooring, new wall finishes, new ceilings and lighting, demolition and new stud wall construction, and updated graphics.
This project includes, but is not limited to new lockers, new flooring, new wall finishes, new ceilings and lighting, demolition and new stud wall construction, and updated graphics.
Hilton Coliseum-Rooms 0176, 0176A, 0188, and 0188A-Renovation
Post Construction
Scope number: PS01
Construction Budget: $737,330
Begin construction: 05/01/2023
Occupancy / completion: 10/06/2023
Gross sq.ft.: 3280
Net sq.ft.: 2740
Prime contractor: NEUMANN BROTHERS INC
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
The project consists of, but is not limited to, demolition of existing finishes and walls; installation of new stud walls, flooring, finishes, and ceilings; new lighting; and modifications to existing mechanical system.
Subcontractors (8)
Hilton Coliseum-South Stairwell-Repairs
CP number: CP1195000
Total Construction Budget: $115,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Hilton Coliseum-South Stairwell-Repairs
Post Construction
Scope number: PS01
Construction Budget: $110,100
Gross sq.ft.: 400
Net sq.ft.: 400
Prime contractor: Multiple Constructors
Project manager:
Josef Biechler
Construction manager:
Josef Biechler
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, repairs to the stairs and landings and placement of shoring under the stair landing and walkway of the south stairway and Hilton Coliseum.
Hilton Coliseum-South Stairwell-Repairs Bid Date:
Hixson-Lied Student Success Center-Rooms 2242 and 2280-Remodel
CP number: CP1201476
Total Construction Budget: $198,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the remodeling of rooms 2242 and 2280 of the Hixson-Lied Student Success Center to accommodate the relocation of the Center for Excellence in Learning and Teaching (CELT) testing center. Work includes demolition of interior space including existing casework, chair rails, doors, flooring, and wall base. New work includes patching and repairing walls, new paint, doors, lockers, security cameras, testing station furniture, and mechanical and electrical work to support the remodel. New office furniture for the staff is also included.
This project includes, but is not limited to, the remodeling of rooms 2242 and 2280 of the Hixson-Lied Student Success Center to accommodate the relocation of the Center for Excellence in Learning and Teaching (CELT) testing center. Work includes demolition of interior space including existing casework, chair rails, doors, flooring, and wall base. New work includes patching and repairing walls, new paint, doors, lockers, security cameras, testing station furniture, and mechanical and electrical work to support the remodel. New office furniture for the staff is also included.
Hixson-Lied Student Success Center-Rooms 2242 and 2280-Remodel
Post Construction
Scope number: PS01
Construction Budget: $198,000
Begin construction: 04/04/2024
Occupancy / completion: 07/26/2024
Gross sq.ft.: 2570
Net sq.ft.: 2300
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Elizabeth Clarke
Construction manager:
Mick McBride
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the remodeling of rooms 2242 and 2280 of the Hixson-Lied Student Success Center to accommodate the relocation of the Center for Excellence in Learning and Teaching (CELT) testing center. Work includes demolition of interior space including existing casework, chair rails, doors, flooring, and wall base. New work includes patching and repairing walls, new paint, doors, lockers, security cameras, testing station furniture, and mechanical and electrical work to support the remodel. New office furniture for the staff is also included.
Subcontractors (9)
Horticulture Research Station-Machine Storage Building
CP number: CP1053242
Total Construction Budget: $143,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Horticulture Research Station-Machine Storage Building
Design-CD
Scope number: PS01
Construction Budget: $143,000
Project manager:
Mark Huss
Construction manager:
Mick McBride
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited to, the design and construction of a 6000 square feet post frame storage building. The building will be uninsulated and not heated. The building will have a concrete floor, a metal roof, and metal siding.
Horticulture Research Station-Machine Storage Building Bid Date: TBD
Howe Hall-Fire Panels-Replacement
CP number: CP1239915
Total Construction Budget: $258,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Howe Hall-Fire Panels-Replacement
Construction
Scope number: PS01
Construction Budget: $262,777
Begin construction: 09/24/2024
Occupancy / completion: 01/22/2025
Prime contractor: NIKKEL & ASSOC INC
Project manager:
Joshua Dank
Construction manager:
Danelda Allen
Design Professional: RESOURCE CONSULTING ENGINEERS
Contract description of work:
This project will replace the existing fire alarm control panels and building transponders with current, supported technology. This includes, but is not limited to, control and annunciator panels, building transponders, and incompatible devices.
Subcontractors (1)
Howe Hall-Roof Replacement-Section M
CP number: CP1187632
Total Construction Budget: $852,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remove the existing roof system down to the deck and replace with a new roofing system. The scope of work includes, but is not limited to, an EPDM (ethylene propylene diene monomer rubber) system designed for a minimum life expenctancy of 25 years; new roof insulation to meet current energy codes; and roof access improvements to meet university standards.
This project will remove the existing roof system down to the deck and replace with a new roofing system. The scope of work includes, but is not limited to, an EPDM (ethylene propylene diene monomer rubber) system designed for a minimum life expenctancy of 25 years; new roof insulation to meet current energy codes; and roof access improvements to meet university standards.
Howe Hall-Roof Replacement-Section M
Bid
Scope number: PS01
Construction Budget: $775,000
Occupancy / completion: 10/30/2025
Gross sq.ft.: 54000
Net sq.ft.: 30600
Project manager:
Joshua Dank
Construction manager:
John Boehmer
Design Professional: I&S GROUP INC
Contract description of work:
This project will remove the existing roof system down to the deck and replace with a new roofing system. The scope of work includes, but is not limited to, an EPDM (ethylene propylene diene monomer rubber) system designed for a minimum life expectancy of 25 years; new roof insulation to meet current energy codes; and roof access improvements to meet university standards.
Human Nutritional Sciences Building-Research Labs-Remodel
CP number: CP1015970
Total Construction Budget: $1,625,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel existing teaching laboratory spaces in the Human Nutritional Sciences Building to accommodate textile science research laboratories relocating from LeBaron Hall. Work will consist of interior demolition and construction of new walls, casework, fume hoods, and finishes. The mechanical and electrical systems will also be updated to support the remodeled laboratories. An existing environmental chamber and 3-D body scanner will be relocated to the new laboratories.
This project will remodel existing teaching laboratory spaces in the Human Nutritional Sciences Building to accommodate textile science research laboratories relocating from LeBaron Hall. Work will consist of interior demolition and construction of new walls, casework, fume hoods, and finishes. The mechanical and electrical systems will also be updated to support the remodeled laboratories. An existing environmental chamber and 3-D body scanner will be relocated to the new laboratories.
Human Nutritional Sciences Building-Research Labs-Remodel
Scope number: PS01
Construction Budget: $1,457,474
Begin construction: 06/19/2023
Occupancy / completion: 03/18/2024
Gross sq.ft.: 2677
Net sq.ft.: 2399
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Elizabeth Clarke
Construction manager:
Barton Dobson
Design Professional: BROOKS BORG SKILES ARCH ENGR
Contract description of work:
The project consists of, but is not limited to, remodel of existing teaching laboratory space to accommodate textile science research laboratories. Work includes demolition of interior space including existing walls, casework, equipment, and finishes. New work includes, but is not limited to, new walls, casework, fume hoods, doors, finishes, and infill of existing wall openings and roof patching to accommodate new mechanical rooftop equipment. Mechanical scope includes new supply and exhaust ductwork, new building automation controls, and new plumbing to support lab equipment in the space. Electrical scope incudes a new panel, new power services to support lab equipment, new lighting, and new fire alarm devices. Fire protection scope includes removal and re-installation of sprinkler piping and heads in the space.
Subcontractors (11)
I.S.U. Airport Hangar 2-Door-Replacement
CP number: CP1197697
Total Construction Budget: $236,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
I.S.U. Airport Hangar 2-Door-Replacement
Post Construction
Scope number: PS01
Construction Budget: $166,900
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the removal of the existing hangar door system, reworking the metal building panels and structure for wider opening, and installing new concrete footings.
I.S.U. Airport Hangar 2-Door-Replacement Bid Date:
Information Technology Services-Animal Science Teaching Farms-Fiber Expansion
CP number: CP1170264
Total Construction Budget: $164,650
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Information Technology Services-Animal Science Teaching Farms-Fiber Expansion
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Travis Van Dyke
Construction manager:
Travis Van Dyke
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
This project includes, but is not limited to, the installation of conduit, ground boxes, and a vault for the future expansion of ISUs data network to the Animal Science Research Farms.
Information Technology Services-Animal Science Teaching Farms-Fiber Expansion Bid Date:
Information Technology Services-Central Campus-Fiber and Wireless Expansion
CP number: CP1118671
Total Construction Budget: $126,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Information Technology Services-Central Campus-Fiber and Wireless Expansion
Pre-Design
Scope number: PS01
Construction Budget: $133,000
Prime contractor: Iowa State University
Project manager:
Caleb Barduson
Construction manager:
Caleb Barduson
Design Professional: ISU - Utilities
Contract description of work:
This project includes, but is not limited to, the installation of conduit, vaults, and ground boxes for future fiber and wireless internet expansion of central campus.
Information Technology Services-Central Campus-Fiber and Wireless Expansion Bid Date:
Institutional Roads 2023-Pavement Preservation
CP number: CP1160447
Total Construction Budget: $236,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Institutional Roads 2023-Pavement Preservation
Construction
Scope number: PS01
Construction Budget: $236,500
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Design Professional: ISU
Contract description of work:
Planned work includes, but is not limited to, asphalt and concrete road patching in several locations across campus.
Institutional Roads 2023-Pavement Preservation Bid Date:
Institutional Roads 2023-State Avenue and Mortensen Road-Traffic Signal Installation
CP number: CP1168159
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Institutional Roads 2023-State Avenue and Mortensen Road-Traffic Signal Installation
Post Construction
Scope number: PS01
Construction Budget: $180,000
Begin construction: 05/24/2024
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Design Professional: ISU
Contract description of work:
This project includes, but is not limited to, the installation of a permanent traffic signal at the intersection of State Avenue and Mortensen Road in partnership with the City of Ames.
Institutional Roads 2023-State Avenue and Mortensen Road-Traffic Signal Installation Bid Date:
Institutional Roads 2024-S. 16th Street and S. Riverside Drive-Traffic Signal Installation
CP number: CP1238577
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Institutional Roads 2024-S. 16th Street and S. Riverside Drive-Traffic Signal Installation
On Hold
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Angela Solberg
Design Professional: ISU
Contract description of work:
This project includes, but is not limited to, installing a new traffic signal at the intersection of S. 16th Street and S. Riverside Drive in coordination with the City of Ames S. 16th Street widening project.
Institutional Roads 2024-S. 16th Street and S. Riverside Drive-Traffic Signal Installation Bid Date:
Institutional Roads 2024-Scholl Road-Reconstruction
CP number: CP1168167
Total Construction Budget: $737,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Institutional Roads 2024-Scholl Road-Reconstruction
On Hold
Scope number: PS01
Construction Budget: $737,000
Project manager:
Angela Solberg
Construction manager:
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
Scholl Road is owned by the university and provides access to the Applied Science complex northwest of the main campus. This project includes, but is not limited to, the reconstruction of the southern portion of Scholl Road, from Ontario Street to north of the railroad tracks, including drainage improvements and sidewalks. The project is included in the Institutional Road program funded by the Iowa Department of Transportation.
Institutional Roads 2024-Scholl Road-Reconstruction Bid Date: TBD
Institutional Roads 2024-University Boulevard and 6th Street-Signal Replacement
CP number: CP1226590
Total Construction Budget: $786,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Institutional Roads 2024-University Boulevard and 6th Street-Signal Replacement
Construction
Scope number: PS01
Construction Budget: $748,551
Begin construction: 07/02/2024
Occupancy / completion: 08/08/2025
Prime contractor: VAN MAANEN ELECTRIC INC
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SNYDER & ASSOC INC
Contract description of work:
This project will replace the existing traffic signals with new signals that meet current traffic control standards. Scope of work includes, but is not limited to, new signal poles, heads, controllers, countdown timers on the crosswalks, radar-based vehicle and bicycle detection, left turn flashing arrows, leading pedestrian interval phasing, ADA compliant crosswalk controls, and concrete patching in the intersection.
Institutional Roads 2025-Stange Road-Reconstruction
CP number: CP1226581
Total Construction Budget: $2,909,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Multiple road sections across campus have deteriorated and need full-depth concrete patching, asphalt patching, and mill and overlay work. This project includes, but is not limited to, repairs on Mortensen Road and Stange Road.
Multiple road sections across campus have deteriorated and need full-depth concrete patching, asphalt patching, and mill and overlay work. This project includes, but is not limited to, repairs on Mortensen Road and Stange Road.
Institutional Roads 2025-Stange Road-Reconstruction
Construction
Scope number: PS01
Construction Budget: $1,977,639
Begin construction: 12/03/2024
Occupancy / completion: 08/04/2025
Prime contractor: CONCRETE TECHNOLOGIES INC
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SNYDER & ASSOC INC
Contract description of work:
Multiple road sections across campus have deteriorated and need full-depth concrete patching, asphalt patching, and mill and overlay work. This project includes, but is not limited to, repairs on Mortensen Road and Stange Road.
Subcontractors (7)
ISU Child Care Center at Veterinary Medicine-Improvements
CP number: CP1008416
Total Construction Budget: $463,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
ISU Child Care Center at Veterinary Medicine-Improvements
Scope number: PS01
Construction Budget: $445,711
Begin construction: 09/14/2023
Occupancy / completion: 03/14/2024
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Elizabeth Clarke
Construction manager:
Ben Haywood
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited to, the replacement of heating and cooling units, installation of a switch for garbage disposal, and updating of HVAC controls.
Subcontractors (5)
ISU Child Care Center at Veterinary Medicine-Remodel
CP number: CP1175069
Total Construction Budget: $221,730
includes the bid estimate and contingency for this scope of work
Overall project description of work:
ISU Child Care Center at Veterinary Medicine-Remodel
Scope number: PS01
Construction Budget: $193,500
Begin construction: 06/10/2024
Occupancy / completion: 10/02/2024
Gross sq.ft.: 6500
Net sq.ft.: 5610
Prime contractor: HPC LLC
Project manager:
Elizabeth Clarke
Construction manager:
Ben Haywood
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, replacement of flooring and wall base, countertops, and an exterior door. Work also includes replacing wood trim at five windows and replacement of thirteen window units.
Subcontractors (4)
Jack Trice Stadium-East Gateway Bridge
CP number: CP002683
Total Construction Budget: $8,163,750
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THE PROJECT WILL CONSTRUCT A BRIDGE OVER SOUTH UNIVERSITY BOULEVARD TO CONNECT THE EAST CONCOURSE OF JACK TRICE STADIUM AND FOOTBALL GAME DAY PARKING EAST OF SOUTH UNIVERSITY BOULEVARD. A SIDEWALK WILL BE CONSTRUCTED ALONG THE EAST SIDE OF THE EXISTING STADIUM RING ROAD AND A FENCE MATCHING THE EXISTING REIMAN GARDENS FENCING WILL BE CONTINUED ALONG THE WEST SIDE OF UNIVERSITY BOULEVARD.
THE PROJECT WILL CONSTRUCT A BRIDGE OVER SOUTH UNIVERSITY BOULEVARD TO CONNECT THE EAST CONCOURSE OF JACK TRICE STADIUM AND FOOTBALL GAME DAY PARKING EAST OF SOUTH UNIVERSITY BOULEVARD. A SIDEWALK WILL BE CONSTRUCTED ALONG THE EAST SIDE OF THE EXISTING STADIUM RING ROAD AND A FENCE MATCHING THE EXISTING REIMAN GARDENS FENCING WILL BE CONTINUED ALONG THE WEST SIDE OF UNIVERSITY BOULEVARD.
Jack Trice Stadium-East Gateway Bridge
Post Construction
Scope number: PS01
Construction Budget: $8,163,750
Begin construction: 06/04/2021
Occupancy / completion: 09/01/2022
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Jonathan Harvey
Construction manager:
Design Professional: SUBSTANCE ARCHITECTURE
Contract description of work:
The project consists of, but is not limited to, the construction of an elevated gateway bridge over South University Boulevard to connect the east concourse of Jack Trice Stadium and game day parking east of South University Boulevard. A sidewalk will be added along the east side of the existing stadium ring road. The existing Reiman Gardens fencing on the north will be continued along the west side of University Boulevard.
Jack Trice Stadium-East Gateway Bridge Bid Date: 05/27/2021
Subcontractors (15)
Jack Trice Stadium-Press Box Elevator-Improvements
CP number: CP965420
Total Construction Budget: $408,270
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Jack Trice Stadium-Press Box Elevator-Improvements
Construction
Scope number: PS01
Construction Budget: $408,270
Begin construction: 03/08/2024
Occupancy / completion: 03/31/2025
Prime contractor: EDGE COMMERCIAL LLC
Project manager:
Kelly Kalvelage
Construction manager:
Steven Nelson
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited to, modernizing the elevator controller, hoisting equipment, and door operations.
Subcontractors (3)
Jack Trice Stadium-Press Box-Roof Replacement
CP number: CP002611
Total Construction Budget: $110,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Jack Trice Stadium-Press Box-Roof Replacement
Final Reporting
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Jonathan Harvey
Construction manager:
Jonathan Harvey
Design Professional: ISU
Contract description of work:
REPLACE ROOF ON THE EXISTING PRESS BOX TOWER AT JACK TRICE STADIUM.
Jack Trice Stadium-Press Box-Roof Replacement Bid Date:
Jacobson Athletic Building-Elevator-Improvements
CP number: CP965428
Total Construction Budget: $214,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will modernize one passenger elevator in the Jacobson Athletic Building. The modernization includes new controller, door operating equipment, and signal fixtures.
This project will modernize one passenger elevator in the Jacobson Athletic Building. The modernization includes new controller, door operating equipment, and signal fixtures.
Jacobson Athletic Building-Elevator-Improvements
Construction
Scope number: PS01
Construction Budget: $142,442
Begin construction: 09/26/2024
Occupancy / completion: 05/30/2025
Prime contractor: MOHR CONSTRUCTION SERVICES LLC
Project manager:
Kelly Kalvelage
Construction manager:
Steven Nelson
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited to, modernizing one passenger elevator controller and door operating equipment.
Subcontractors (6)
Jacobson Athletic Building-Room 2035-Remodel
CP number: CP942806
Total Construction Budget: $260,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will remodel the existing Hunziker Auditorium and create a level floor that will replace the existing stepped floor. The existing unused storage space will be removed, and that space captured within the auditorium.
The project will remodel the existing Hunziker Auditorium and create a level floor that will replace the existing stepped floor. The existing unused storage space will be removed, and that space captured within the auditorium.
Jacobson Athletic Building-Room 2035-Remodel
Final Reporting
Scope number: PS01
Construction Budget: $237,000
Begin construction: 05/19/2022
Occupancy / completion: 09/11/2022
Gross sq.ft.: 1470
Net sq.ft.: 1470
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Jonathan Harvey
Construction manager:
Danelda Allen
Design Professional: ISU - FDC
Contract description of work:
The project consists of, but is not limited to, demolition of existing flooring, stairs, walls, and doors. Construction of new glass partition walls, raised floor platform, new doors, electrical and mechanical modifications to existing, and new lighting.
Jacobson Athletic Building-Room 2035-Remodel Bid Date: 05/12/2022
Subcontractors (9)
Kildee Hall-AHU2 and UVU4-Replacement
CP number: CP002632
Total Construction Budget: $1,762,959
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace Air Handling Unit (AHU) 2 and Unit Ventilator Unit (UVU) 4 with a semi-custom design unit to serve the west laboratory spaces in the building. Additionally, Mechanical Room M0026 will be prepared for future AHU replacements and improved maintenance access. This project includes, but is limited to replacement of AHU 2 and UVU 4 with a new AHU, ductwork and pipe reconfiguration, motor control center and control panel relocation and upgrade, improved access, and relocation of the existing electrical transformer.
This project will replace Air Handling Unit (AHU) 2 and Unit Ventilator Unit (UVU) 4 with a semi-custom design unit to serve the west laboratory spaces in the building. Additionally, Mechanical Room M0026 will be prepared for future AHU replacements and improved maintenance access. This project includes, but is limited to replacement of AHU 2 and UVU 4 with a new AHU, ductwork and pipe reconfiguration, motor control center and control panel relocation and upgrade, improved access, and relocation of the existing electrical transformer.
Kildee Hall-AHU2 and UVU4-Replacement
Construction
Scope number: PS01
Construction Budget: $1,726,393
Begin construction: 06/20/2023
Occupancy / completion: 04/16/2025
Gross sq.ft.: 183971
Net sq.ft.: 183971
Prime contractor: MANNING SEIVERT MECHANICAL CONTRACTORS INC
Project manager:
Mark Grief
Construction manager:
John Boehmer
Design Professional: RESOURCE CONSULTING ENGINEERS
Contract description of work:
The project includes, but is not limited to, the replacement of Air Handling Unit (AHU) 2 and Unit Ventilator Unit (UVU) 4 with a semi-custom design unit to serve the west laboratory spaces in the building, new ductwork and pipe reconfiguration, along with improved access and relocation of the existing electrical transformer. Additionally, Mechanical Room M0026 will be prepared for future AHU replacements and improved maintenance access.
Subcontractors (8)
Kildee Hall-AHU4 and AHU5-Replacement
CP number: CP1173440
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Kildee Hall-AHU4 and AHU5-Replacement
Design-CD
Scope number: PS01
Begin construction: 10/31/2024
Project manager:
Mark Grief
Construction manager:
John Boehmer
Design Professional: RESOURCE CONSULTING ENGINEERS
Contract description of work:
This project includes, but is not limited to, replacement of Air Handling Units (AHU4 & AHU5) due to the frequency of service requests for repairs which is also negatively affecting the building occupants. It was determined after a comprehensive evaluation that both the existing air handling units could not be repaired and needed to be replaced.
Kildee Hall-AHU4 and AHU5-Replacement Bid Date: 04/17/2025 (Tentative)
Kildee Hall-Common Area Improvements
CP number: CP1017060
Total Construction Budget: $58,767
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the installation of graphic wall paneling along various first and third floor corridor walls of the original Kildee Hall building. Also included is the reconfiguration of the door swing into Suite 0119.
This project includes, but is not limited to, the installation of graphic wall paneling along various first and third floor corridor walls of the original Kildee Hall building. Also included is the reconfiguration of the door swing into Suite 0119.
Kildee Hall-Common Area Improvements
Final Reporting
Scope number: PS01
Construction Budget: $59,000
Begin construction: 08/16/2023
Occupancy / completion: 01/12/2024
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Jennifer Evans
Construction manager:
Ben Haywood
Design Professional: CANNON MOSS BRYGGER & ASSOC
Contract description of work:
This project includes, but is not limited to, updating finishes, wayfinding, space and door reconfiguration, new furniture, and additional power outlets/technology.
Lagomarcino Hall-Restrooms-Remodel
CP number: CP002661
Total Construction Budget: $204,210
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel two sets of first floor restrooms in Lagomarcino Hall to provide accessible facilities in the building and increase fixture count. This project includes, but is not limited to, new doors and accessories in existing North end restrooms and a complete remodel of existing East end restrooms to create a new and larger accessible women's restroom and a new accessible single-user restroom.
This project will remodel two sets of first floor restrooms in Lagomarcino Hall to provide accessible facilities in the building and increase fixture count. This project includes, but is not limited to, new doors and accessories in existing North end restrooms and a complete remodel of existing East end restrooms to create a new and larger accessible women's restroom and a new accessible single-user restroom.
Lagomarcino Hall-Restrooms-Remodel
Design-SD
Scope number: PS01
Project manager:
Hayley Sandholm
Construction manager:
Design Professional: I&S GROUP INC
Contract description of work:
Lagomarcino Hall-Restrooms-Remodel Bid Date: TBD
LeBaron Hall-Replacement
CP number: CP002668
Total Construction Budget: $29,040,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will demolish the current LeBaron Hall and replace it with a new building. The project will also renovate the circulation corridor connecting LeBaron Hall, MacKay Hall, and the Human Nutritional Sciences Building. The new building will offer a contemporary learning environment designed to encourage independent learning and leadership development, to create a sense of community and inclusiveness, and better prepare students by facilitating industry-based and experiential learning. The project will include cutting-edge instructional spaces and a new general university classroom. New teaching laboratories will meet industry standards and program enrollment needs. Also included is a new commons area that will serve as a teaching and research space for the event management program, and act as a student-centered collaborative working space for students, staff, and faculty.
This project will demolish the current LeBaron Hall and replace it with a new building. The project will also renovate the circulation corridor connecting LeBaron Hall, MacKay Hall, and the Human Nutritional Sciences Building. The new building will offer a contemporary learning environment designed to encourage independent learning and leadership development, to create a sense of community and inclusiveness, and better prepare students by facilitating industry-based and experiential learning. The project will include cutting-edge instructional spaces and a new general university classroom. New teaching laboratories will meet industry standards and program enrollment needs. Also included is a new commons area that will serve as a teaching and research space for the event management program, and act as a student-centered collaborative working space for students, staff, and faculty.
LeBaron Hall-Replacement
Construction
Scope number: PS01
Construction Budget: $29,040,000
Begin construction: 03/14/2024
Occupancy / completion: 07/01/2026
Prime contractor: NEUMANN BROTHERS INC
Project manager:
Elizabeth Clarke
Construction manager:
Barton Dobson
Design Professional: S-L-A-M COLLABORATIVE INC
Contract description of work:
This project will demolish the current LeBaron Hall and replace it with a new building. The project will also renovate the circulation corridor connecting LeBaron Hall, MacKay Hall, and the Human Nutritional Sciences Building. The new building will offer a contemporary learning environment designed to encourage independent learning and leadership development, to create a sense of community and inclusiveness, and better prepare students by facilitating industry-based and experiential learning. The project will include cutting-edge instructional spaces and a new general university classroom. New teaching laboratories will meet industry standards and program enrollment needs. Also included is a new commons area that will serve as a teaching and research space for the event management program, and act as a student-centered collaborative working space for students, staff, and faculty.
Subcontractors (10)
LIBRARY-0198-315915-Improvements
CP number: PR1195646
Total Construction Budget: $65,200
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Please start a project request to add sound dampening acoustic panels to room 198. This is the original building and would be attaching to original plaster. Please consult with university architect as well making sure these changes are approved. Use PG103216 for worktag for project. Scope Increase: Paint & Carpet
Please start a project request to add sound dampening acoustic panels to room 198. This is the original building and would be attaching to original plaster. Please consult with university architect as well making sure these changes are approved. Use PG103216 for worktag for project. Scope Increase: Paint & Carpet
Parks Library-Room 0198-Improvements
Post Construction
Scope number: PS01
Construction Budget: $65,000
Begin construction: 06/04/2024
Occupancy / completion: 08/23/2024
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Contract description of work:
Subcontractors (2)
Lied Recreation Fields-Field Lights-Replacement
CP number: CP1264746
Total Construction Budget: $268,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Lied Recreation Fields-Field Lights-Replacement
Quote
Scope number: PS01
Begin construction: 12/11/2024
Occupancy / completion: 06/11/2024
Prime contractor: Multiple Constructors
Project manager:
Mitchell Hlavacek
Construction manager:
Mitchell Hlavacek
Design Professional: ISU
Contract description of work:
This project will replace existing metal halide luminaire assemblies at the Lied Recreation Center fields with LED luminaires. This project will utilize existing light poles and electrical infrastructure.
Lied Recreation Fields-Field Lights-Replacement Bid Date:
Lloyd Veterinary Medical Center-Large Animal Ward 3-Expansion
CP number: CP1044573
Total Construction Budget: $9,752,280
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will add 13,644 gross sq. ft. space for a third Ward to the Large Animal Hospital. This third Ward would expand current large animal reproductive services to the State of Iowa and enhance professional student and resident training opportunities in advanced equine sports medicine and large animal reproductive service areas.
This project will add 13,644 gross sq. ft. space for a third Ward to the Large Animal Hospital. This third Ward would expand current large animal reproductive services to the State of Iowa and enhance professional student and resident training opportunities in advanced equine sports medicine and large animal reproductive service areas.
Lloyd Veterinary Medical Center-Large Animal Ward 3-Expansion
Bid
Scope number: PS01
Construction Budget: $8,690,000
Begin construction: 04/30/2025
Occupancy / completion: 10/05/2026
Gross sq.ft.: 22043
Net sq.ft.: 15403
Project manager:
Mark Grief
Construction manager:
Troy Chandler
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
This project will add 22,043 square feet of space to the existing facility. The project includes four building extensions and one free-standing structure. The additions are enhanced reproduction, critical care, horse rehabilitation, theriogenology, and a free-standing feeding and bedding facility. The new building will comprise of modest demolition of the existing wards and large animal hospital, as well as the construction of three expansions and infill between wards one and two, using materials and structures that are compatible with the current facilities. To support the additions, new services such as plumbing, HVAC, electrical power, lighting, fire protection, telecommunications, and security will be implemented. The present hospital and wards will continue to operate during the construction period, and any disruptions to services, deliveries, and daily operations must be managed with the ISU construction manager and the College of Veterinary Medicine Staff.
Lloyd Veterinary Medical Center-Large Animal Ward 3-Expansion Bid Date: 02/20/2025
MacKay Hall-Roof Replacement-Section F and Parapet Wall Repair
CP number: CP1118937
Total Construction Budget: $583,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace roof Section F and repair the parapet wall at MacKay Hall. This section of the roof is a built-up roof (BUR) and is over 25 years old with a history of leaks. This project includes, but is not limited to: • Replacement of the roof with a system designed for a minimum life expectancy of 30 years • Roof insulation to meet current energy codes • Roof safety improvements as needed to meet current university standards • Repair, tuckpointing, or caulking of all features, roof curbs, and parapet walls above the roofline to prevent water infiltration through these critical connections • Addition of a roof access door
This project will replace roof Section F and repair the parapet wall at MacKay Hall. This section of the roof is a built-up roof (BUR) and is over 25 years old with a history of leaks. This project includes, but is not limited to: • Replacement of the roof with a system designed for a minimum life expectancy of 30 years • Roof insulation to meet current energy codes • Roof safety improvements as needed to meet current university standards • Repair, tuckpointing, or caulking of all features, roof curbs, and parapet walls above the roofline to prevent water infiltration through these critical connections • Addition of a roof access door
MacKay Hall-Roof Replacement-Section F and Parapet Wall Repair
Post Construction
Scope number: PS01
Construction Budget: $441,430
Begin construction: 01/02/2024
Occupancy / completion: 06/30/2024
Gross sq.ft.: 8000
Prime contractor: ACADEMY ROOFING & SHEET METAL
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: I&S GROUP INC
Contract description of work:
This project will replace roof Section F and repair the parapet wall at MacKay Hall. This section of the roof is a built-up roof (BUR) and is over 25 years old with a history of leaks. This project includes, but is not limited to, replacement of the roof with a system designed for a minimum life expectancy of 30 years, roof insulation to meet current energy codes, roof safety improvements as needed to meet current university standards, repair, tuckpointing, or caulking of all features, roof curbs, and parapet walls above the roofline to prevent water infiltration through these critical connections, addition of a roof access door.
Subcontractors (1)
MacKay Hall-Roof Replacement-Sections A-E and G-I
CP number: CP1166619
Total Construction Budget: $1,430,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will replace roof sections A, B, C, D, E, G, H, and I at MacKay Hall. These sections of the roof are 18-year-old EPDM systems. This project includes, but is not limited to, replacement of the roof with a system designed for a minimum life expectancy of 30 years, roof insulation to meet current energy codes, roof safety improvements as needed to meet current university standards, skylight replacement, masonry repairs, tuckpointing, caulking of all features, roof curbs and parapet walls above the roofline to prevent water infiltration through these critical connections, and roof access improvements as needed to meet current university standards.
This project will replace roof sections A, B, C, D, E, G, H, and I at MacKay Hall. These sections of the roof are 18-year-old EPDM systems. This project includes, but is not limited to, replacement of the roof with a system designed for a minimum life expectancy of 30 years, roof insulation to meet current energy codes, roof safety improvements as needed to meet current university standards, skylight replacement, masonry repairs, tuckpointing, caulking of all features, roof curbs and parapet walls above the roofline to prevent water infiltration through these critical connections, and roof access improvements as needed to meet current university standards.
MacKay Hall-Roof Replacement-Sections A-E and G-I
Construction
Scope number: PS01
Construction Budget: $1,228,613
Begin construction: 04/15/2024
Occupancy / completion: 10/18/2024
Gross sq.ft.: 17700
Net sq.ft.: 0
Prime contractor: HOPKINS ROOFING INC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: I&S GROUP INC
Contract description of work:
This project will replace roof sections A, B, C, D, E, G, H and I at MacKay Hall. These sections of the roof are 18 year old EPDM systems. This project includes, but is not limited to replacement of the roof with a system designed for a minimum life expectancy of 30 years, roof insulation to meet current energy codes, roof safety improvements as needed to meet current university standards, repair, tuckpointing, or caulking of all features, roof curbs, and parapet walls above the roofline to prevent water infiltration through these critical connections, and roof access improvements as needed to meet current university standards.
Subcontractors (2)
Maple Willow Larch Commons-Seasons Marketplace-Remodel
CP number: CP1159926
Total Construction Budget: $4,646,460
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will remodel portions of the back of house in the Seasons Marketplace dining facility at the Maple Willow Larch Commons. Back of house restrooms and food preparation areas will be updated due to deteriorating finishes, code and standards compliance, equipment upgrades, and improved workflows.
The project will remodel portions of the back of house in the Seasons Marketplace dining facility at the Maple Willow Larch Commons. Back of house restrooms and food preparation areas will be updated due to deteriorating finishes, code and standards compliance, equipment upgrades, and improved workflows.
Maple Willow Larch Commons-Seasons Marketplace-Remodel
Maple Willow Larch Commons-Seasons Marketplace-Remodel-Venues
Bid
Meats Laboratory-Cooler-Repairs
CP number: CP1175478
Total Construction Budget: $825,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Meats Laboratory-Cooler-Repairs
Scope number: PS01
Construction Budget: $832,675
Begin construction: 05/02/2024
Occupancy / completion: 09/19/2024
Gross sq.ft.: 1392
Net sq.ft.: 1287
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Jennifer Evans
Construction manager:
Steven Nelson
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited to, the repair of walls (exterior and interior) and ceiling surfaces of three cooler rooms at the Meats Laboratory. Removal of damaged, wet material will expose interior wall conditions and help to locate areas of air leakage. Repairs will be made to prevent moisture build-up. New lighting, insulated walls, and insulated ceiling panels will be installed. The project also includes the demolition and removal of the concrete cooler room floors. New concrete floors, with appropriate insulation beneath, will be installed.
Subcontractors (6)
Memorial Union-Bookstore-Lighting Replacement
CP number: CP1118655
Total Construction Budget: $405,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, replacing the lighting throughout the University Bookstore with new fixtures, LED lighting and controllers, converting to 120 Volts, and adding battery packs.
This project includes, but is not limited to, replacing the lighting throughout the University Bookstore with new fixtures, LED lighting and controllers, converting to 120 Volts, and adding battery packs.
Memorial Union-Bookstore-Lighting Replacement
Construction
Scope number: PS01
Construction Budget: $407,960
Begin construction: 12/12/2023
Occupancy / completion: 10/07/2024
Gross sq.ft.: 21000
Net sq.ft.: 21000
Prime contractor: JASPERING ELECTRIC INC
Project manager:
Hayley Sandholm
Construction manager:
Barton Dobson
Design Professional: BROOKS BORG SKILES ARCH ENGR
Contract description of work:
This project includes, but is not limited to, replacing the lighting throughout the University Bookstore. New fixtures, LED bulbs, and additional lighting solutions are needed throughout the space.
Memorial Union-Fountain of the Four Seasons-Renovation
CP number: CP1017470
Total Construction Budget: $1,343,310
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the renovation of the pool basin, fountainhead well, mechanical pit, tunnel, pool lighting, and upgrades to the mechanical and electrical systems of the Fountain of the Four Seasons at the exterior north courtyard of the Memorial Union. The original limestone sculptures of the four maidens will be removed, conserved, and replicated. The sculpture replications will be placed at the original site within the renovated fountain. The original sculptures will be placed in a location to be determined by the University Museums.
This project includes, but is not limited to, the renovation of the pool basin, fountainhead well, mechanical pit, tunnel, pool lighting, and upgrades to the mechanical and electrical systems of the Fountain of the Four Seasons at the exterior north courtyard of the Memorial Union. The original limestone sculptures of the four maidens will be removed, conserved, and replicated. The sculpture replications will be placed at the original site within the renovated fountain. The original sculptures will be placed in a location to be determined by the University Museums.
Memorial Union-Fountain of the Four Seasons-Renovation
Post Construction
Scope number: PS01
Construction Budget: $1,243,800
Begin construction: 05/02/2023
Occupancy / completion: 10/27/2023
Prime contractor: NEUMANN BROTHERS INC
Project manager:
David Blum
Construction manager:
Barton Dobson
Design Professional: WISS JANNEY ELSTNER ASSOC INC
Contract description of work:
The project consists of, but is not limited to, the renovation of the Memorial Union Fountain of the Four Seasons. Salvage and reinstallation of paving system and limestone units, select limestone unit replacements, select plumbing salvage, demolition and reconstruction of concrete structures, mechanical, electrical, and waterproofing systems. Coordination with Owners representative of installation of limestone sculptures and terra cotta units by others.
Subcontractors (8)
Memorial Union-Roof Sections A, D, F, and X-Replacement
CP number: CP1242463
Total Construction Budget: $1,020,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Memorial Union-Roof Sections A, D, F, and X-Replacement
Construction
Scope number: PS01
Construction Budget: $804,300
Begin construction: 10/23/2024
Occupancy / completion: 07/07/2025
Gross sq.ft.: 27000
Prime contractor: ACADEMY ROOFING & SHEET METAL
Project manager:
Jennifer Evans
Construction manager:
Mick McBride
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited to, the replacement of roof sections A, D, F, and X to meet current energy codes and roof safety standards. These new sections will have a life expectancy of at least 30 years.
Memorial Union-Soults Family Visitor Center-Remodel
CP number: CP002747
Total Construction Budget: $877,273
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will expand and remodel the existing Soults Family Visitor Center to improve the campus visitor experience. The project includes, but is not limited to, expanded office spaces, updated finishes, new technology, equipment, furniture, and restroom modernization.
This project will expand and remodel the existing Soults Family Visitor Center to improve the campus visitor experience. The project includes, but is not limited to, expanded office spaces, updated finishes, new technology, equipment, furniture, and restroom modernization.
Memorial Union-Soults Family Visitor Center-Remodel
Post Construction
Scope number: PS01
Construction Budget: $964,000
Begin construction: 12/03/2021
Occupancy / completion: 06/15/2022
Gross sq.ft.: 3000
Net sq.ft.: 2700
Prime contractor: BREIHOLZ CONSTRUCTION COMPANY
Project manager:
Kelly Kalvelage
Construction manager:
Danelda Allen
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
This project will expand and remodel the existing Soults Family Visitor Center to improve the campus visitor experience. The project consists of, but is not limited to, expanded office spaces; updated finishes; new technology, equipment, and furniture; and restroom modernization.
Memorial Union-Soults Family Visitor Center-Remodel Bid Date: 11/18/2021
Subcontractors (16)
Memorial Union-Third and Second Floor-Remodel
CP number: CP002643
Total Construction Budget: $4,557,720
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel approximately 12,500 square feet of the third floor of the Memorial Union for use by student service organizations. Approximately 5,000 square feet of existing lounge space on the second floor of the Memorial Union will also be remodeled to provide an updated lounge and common areas for students.
This project will remodel approximately 12,500 square feet of the third floor of the Memorial Union for use by student service organizations. Approximately 5,000 square feet of existing lounge space on the second floor of the Memorial Union will also be remodeled to provide an updated lounge and common areas for students.
Memorial Union-Third and Second Floor-Remodel
Post Construction
Scope number: PS01
Construction Budget: $4,263,000
Begin construction: 07/20/2023
Occupancy / completion: 08/02/2024
Gross sq.ft.: 20000
Net sq.ft.: 20000
Prime contractor: HPC LLC
Project manager:
Hayley Sandholm
Construction manager:
Barton Dobson
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
Remodeling existing office space on third floor to create new office suites, conference spaces, and student lounge. Remodeling second floor lounge for updated lounge and collaboration space as well as two tenant spaces. This project includes but is not limited to a full remodel of each space including, new layout, new walls, ceilings, and flooring, new casework and finishes, mechanical and electrical upgrades, plumbing upgrades, fires system upgrades, and new lighting.
Subcontractors (15)
NEWRITE
CP number: CP1230170
Total Construction Budget: $148,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
NEWRITE
Pre-Design
Scope number: PS01
Project manager:
Jennifer Evans
Construction manager:
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
This $14 million, NSF-funded, Phase 1 project focuses on the design and construction of a ~1/15th scaled prototype (s-NEWRITE) in 1380 Howe Hall, and facilitation of site selection, design, and construction documentation for a shovel ready full-scale NEWRITE facility. Concurrently, a research team led by ISU with participation from Clemson, Missouri S&T, Northeastern, Texas Tech, University of Arkansas, University of Florida, University of Washington, and University of Wisconsin will develop a digital twin that will be used in conjunction with scaled physical testing to inform the design of the NEWRITE facility.
NEWRITE Bid Date: TBD
Oak-Elm Residence Hall-First Floor Elm-Remodel
CP number: CP1123016
Total Construction Budget: $750,915
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Oak-Elm Residence Hall-First Floor Elm-Remodel
Post Construction
Scope number: PS01
Construction Budget: $700,760
Begin construction: 01/31/2024
Occupancy / completion: 07/12/2024
Gross sq.ft.: 3463
Net sq.ft.: 2557
Prime contractor: HPC LLC
Project manager:
Jennifer Evans
Construction manager:
Mick McBride
Design Professional: I&S GROUP INC
Contract description of work:
This project includes, but is not limited, to the remodeling of existing bathrooms and an adjacent, vacant, resident assistant suite into an enlarged shared resident bathroom and a single-stall public bathroom. Also included is the redesign of an exterior entrance vestibule to create hallway space to provide integration of student housing areas. Two vacant resident rooms and corridors will also be remodeled to match standard modern dorm room finishes. Mechanical, ventilation, electrical, and plumbing upgrades will be made to accommodate all remodeled spaces.
Subcontractors (12)
Oak-Elm Residence Hall-Window Replacement
CP number: CP002486
Total Construction Budget: $1,651,470
includes the bid estimate and contingency for this scope of work
Overall project description of work:
PROJECT SCOPE AS FOLLOWS: REMOVE AND REPLACE WINDOWS, REPLACE BLINDS, REMOVE AND REPLACE ASSOCIATED WINDOW SEALANTS, PROVIDE ABATEMENT AND MONITORING SERVICES.
PROJECT SCOPE AS FOLLOWS: REMOVE AND REPLACE WINDOWS, REPLACE BLINDS, REMOVE AND REPLACE ASSOCIATED WINDOW SEALANTS, PROVIDE ABATEMENT AND MONITORING SERVICES.
Oak-Elm Residence Hall-Window Replacement
On Hold
Scope number: PS01
Project manager:
Mark Huss
Construction manager:
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
Project scope as follows: remove and replace windows, replace blinds, remove and replace associated window sealants, provide abatement and monitoring services.
Oak-Elm Residence Hall-Window Replacement Bid Date: TBD
Oak-Elm Residence-Life Cycle Improvements
CP number: CP002473
Total Construction Budget: $1,055,840
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Oak-Elm Residence-Life Cycle Improvements
On Hold
Scope number: PS01
Construction Budget: $1,055,840
Gross sq.ft.: 137120
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional: ISU - Department of Residence
Contract description of work:
THE STUDENT ROOMS WITH HARDWOOD WILL BE REFINISHED. THE STUDENT ROOMS WITH VCT FLOORING WILL BE REPLACED WITH LVT (WOOD-LOOK VINYL TILE). STUDENT ROOMS, HALLWAYS AND COMMON AREAS WILL BE PATCHED AND PAINTED. HALLWAY AND COMMON AREA CARPET WILL BE REPLACED WITH CARPET SQUARES. LIGHTING THROUGOUT THE BUILDING WILL BE REPLACED WITH LED LIGHTING.
Oak-Elm Residence-Life Cycle Improvements Bid Date:
Parking Lot 92-Construction
CP number: CP1229849
Total Construction Budget: $590,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Parking Lot 92-Construction
Scope number: PS01
Construction Budget: $395,263
Begin construction: 05/21/2024
Occupancy / completion: 10/28/2024
Prime contractor: CON STRUCT INC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: SNYDER & ASSOC INC
Contract description of work:
This project includes, but is not limited to, the construction of a new parking lot with approximately 65 stalls along the west side of Christensen Drive at the College of Veterinary Medicine. Work will also include parking lot lighting and a sidewalk connection to the existing pedestrian circulation system.
Subcontractors (6)
Parking Lots 2023-Pavement Preservation
CP number: CP1167539
Total Construction Budget: $391,930
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will perform approximately 1,550 SY of concrete patching intended to extend the life of the pavement and improve the overall pavement condition index (PCI) of Parking Lots on the ISU Campus. Improvements are included in the Five-Year Parking Lot Improvement Plan.
This project will perform approximately 1,550 SY of concrete patching intended to extend the life of the pavement and improve the overall pavement condition index (PCI) of Parking Lots on the ISU Campus. Improvements are included in the Five-Year Parking Lot Improvement Plan.
Parking Lots 2023-Pavement Preservation
Scope number: PS01
Construction Budget: $234,941
Begin construction: 12/20/2023
Occupancy / completion: 08/01/2024
Prime contractor: HOLZWORTH CONSTRUCTION LLC
Project manager:
Angela Solberg
Construction manager:
Ben Haywood
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
This project will perform approximately 1,550 SY of concrete patching intended to extend the life of the pavement and improve the overall pavement condition index (PCI) of Parking Lots on the ISU Campus. Improvements are included in the Five-Year Parking Lot Improvement Plan.
Parking Lots 2023-Special Maintenance
CP number: CP1146234
Total Construction Budget: $325,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Parking Lots 2023-Special Maintenance
Post Construction
Scope number: PS01
Construction Budget: $331,500
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Ben Haywood
Design Professional: ISU
Contract description of work:
This project will provide asphalt patching, crack filling, seal coating, and painting of approximately 16 lots identified on the 5-year seal coating plan for work in 2023.
Parking Lots 2023-Special Maintenance Bid Date:
Parking Lots 2024-Special Maintenance
CP number: CP1240079
Total Construction Budget: $540,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Parking Lots 2024-Special Maintenance
Post Construction
Scope number: PS01
Begin construction: 05/01/2024
Occupancy / completion: 09/01/2024
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Ben Haywood
Design Professional: ISU
Contract description of work:
This project will provide asphalt patching, crack filling, seal coating, and painting of lots identified on the 5-year seal coating plan for work in 2024.
Parking Lots 2024-Special Maintenance Bid Date:
Parks Library-Room 0381-Remodel
CP number: CP1233707
Total Construction Budget: $73,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Parks Library-Room 0381-Remodel
Post Construction
Scope number: PS01
Construction Budget: $73,000
Begin construction: 04/23/2024
Occupancy / completion: 08/01/2024
Gross sq.ft.: 2206
Net sq.ft.: 2206
Prime contractor: BOONE CONSTRUCTION INC
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Contract description of work:
This project will remodel the existing staff lounge. This project includes, but is not limited to, removing flooring, cabinets, tack board fabric, painting walls and ceilings, installing surface countertops, carpet tile, vinyl floor tile, and constructing a microwave shelf. Work includes architectural, mechanical, electrical, and furniture.
Subcontractors (5)
Parks Library-Tiers-Lighting Replacement
CP number: CP1241528
Total Construction Budget: $490,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, replacement of ceiling-mounted light fixtures with new light fixtures and replacement of building wiring.
This project includes, but is not limited to, replacement of ceiling-mounted light fixtures with new light fixtures and replacement of building wiring.
Parks Library-Tiers-Lighting Replacement
Construction
Parks Library-Tiers-Lighting Replacement-Grounding Improvements
Construction
Patterson Hall-Hallway C2275-Improvements
CP number: CP1232723
Total Construction Budget: $100,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Hallway C2275-Improvements
Design-DD
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Hayley Sandholm
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will modernize hallway C2275. The project includes, but is not limited to, wayfinding signage, improvements to the block walls, and furniture replacement.
Patterson Hall-Hallway C2275-Improvements Bid Date:
Patterson Hall-Laboratory Speaker Strobe-Installation
CP number: CP1239249
Total Construction Budget: $192,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Laboratory Speaker Strobe-Installation
Design-SD
Scope number: PS01
Project manager:
Joshua Dank
Construction manager:
Design Professional: RESOURCE CONSULTING ENGINEERS
Contract description of work:
This project will update the existing fire alarm system in Patterson Hall. This project includes, but is not limited to, focusing on the speaker and strobe components of the system and upgrading to current technology.
Patterson Hall-Laboratory Speaker Strobe-Installation Bid Date: TBD
Patterson Hall-Roof Replacement-Sections C, D, G, X, and W
CP number: CP1010421
Total Construction Budget: $571,913
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Roof Replacement-Sections C, D, G, X, and W
Post Construction
Scope number: PS01
Construction Budget: $589,913
Begin construction: 02/05/2024
Occupancy / completion: 11/01/2024
Gross sq.ft.: 27740
Net sq.ft.: 27740
Prime contractor: HOPKINS ROOFING INC
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the replacement of the existing roof systems at roof sections C, D, G, X, and W. All existing ballast, membranes, flashings, fiberboards, and insulation will be removed and replaced with a new, fully adhered, EPDM roof system with new insulation below. The new roof system is designed to have a minimum useful life expectancy of 30 years. New walk pads and appropriate safety equipment will also be included to meet university standards. The existing termination bar sealant at the perimeter of roof section D as well as the asphalt layer beneath roof sections X and W contain asbestos and will be properly abated.
Patterson Hall-Room 1371-Remodel
CP number: CP1250060
Total Construction Budget: $70,300
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will remodel the existing laboratory space into office space. The project includes, but is not limited to, architectural, mechanical, electrical, technology, equipment, finishes, and furniture.
This project will remodel the existing laboratory space into office space. The project includes, but is not limited to, architectural, mechanical, electrical, technology, equipment, finishes, and furniture.
Patterson Hall-Room 1371-Remodel
Construction
Scope number: PS01
Construction Budget: $70,300
Begin construction: 09/03/2024
Occupancy / completion: 01/01/2025
Gross sq.ft.: 585
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Amy Tremain
Construction manager:
Amy Tremain
Design Professional: ISU - FDC
Contract description of work:
Subcontractors (7)
Patterson Hall-Room 2225-Remodel
CP number: CP1253306
Total Construction Budget: $122,930
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Room 2225-Remodel
Construction
Scope number: PS01
Construction Budget: $118,030
Begin construction: 09/26/2024
Occupancy / completion: 01/20/2025
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Amy Tremain
Construction manager:
Amy Tremain
Design Professional: ISU - FDC
Contract description of work:
Remodel Restroom 2225 and replace existing sink and countertop. This project includes, but is not limited to, architectural and mechanical work.
Subcontractors (2)
Patterson Hall-Rooms 1034 and 1034A-Remodel
CP number: CP1229699
Total Construction Budget: $89,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Rooms 1034 and 1034A-Remodel
Post Construction
Scope number: PS01
Construction Budget: $89,400
Begin construction: 02/05/2024
Occupancy / completion: 05/15/2024
Gross sq.ft.: 429
Net sq.ft.: 429
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Nathan Graves
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will remodel the existing laboratory space as per standards of an Arthropod Containment Level-2 (ACL-2) lab as per Arthropod Containment Guidelines, Version 3.2, American Committee of Medical Entomology, and American Society of Tropical Medicine and Hygiene. This project includes, but is not limited to, architectural, mechanical, and electrical work.
Subcontractors (3)
Patterson Hall-Rooms 1140, 1142, and 1144-Remodel
CP number: CP1243948
Total Construction Budget: $220,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Rooms 1140, 1142, and 1144-Remodel
Construction
Scope number: PS01
Construction Budget: $242,000
Begin construction: 09/17/2024
Occupancy / completion: 01/28/2025
Gross sq.ft.: 917
Net sq.ft.: 917
Prime contractor: HPC LLC
Project manager:
Mark Grief
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will remodel rooms 1140, 1142, and 1144 into a new lab space. Work includes, but is not limited to, new flooring, cabinetry, lights, and finish upgrades.
Subcontractors (11)
Patterson Hall-Rooms 1365D & 1385G Surgical Lights-Replacement
CP number: CP1188276
Total Construction Budget: $32,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Rooms 1365D & 1385G Surgical Lights-Replacement
Post Construction
Scope number: PS01
Construction Budget: $32,600
Prime contractor: Multiple Constructors
Project manager:
Nathan Graves
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will purchase and install 19 new LED surgical lights in the Junior Surgery Lab. This project includes, but is not limited to, architectural and electrical work.
Patterson Hall-Rooms 1365D & 1385G Surgical Lights-Replacement Bid Date:
Patterson Hall-Rooms 2119 and 2119A-Remodel
CP number: CP1234647
Total Construction Budget: $241,300
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Patterson Hall-Rooms 2119 and 2119A-Remodel
Scope number: PS01
Construction Budget: $255,050
Begin construction: 05/30/2024
Occupancy / completion: 09/20/2024
Gross sq.ft.: 860
Net sq.ft.: 860
Prime contractor: GREINER CONSTRUCTION INC
Project manager:
Hayley Sandholm
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Contract description of work:
This project will remodel an existing research lab to accommodate new equipment for needed research. This project includes, but is not limited to, abatement of the existing floor and replacing it with new floors, replacing existing casework including wall cabinets, new lighting, and updating lab safety features to accommodate the new layout.
Subcontractors (12)
PATTRSN-1074-311908-Casework Replacement
CP number: PR1194986
Total Construction Budget: $48,700
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Please estimate the cost of replacing the casework in this laboratory.
Please estimate the cost of replacing the casework in this laboratory.
Patterson Hall-Room 1074-Casework Replacement
Construction
Scope number: PS01
Construction Budget: $70,300
Begin construction: 08/28/2024
Occupancy / completion: 12/02/2024
Net sq.ft.: 585
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Amy Tremain
Construction manager:
Amy Tremain
Design Professional: ISU - FDC
Contract description of work:
Subcontractors (5)
Pearson Hall-Accessibility, Wayfinding, and Signage-Improvements
CP number: CP1003356
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Pearson Hall-Accessibility, Wayfinding, and Signage-Improvements
Construction
Scope number: PS01
Construction Budget: $128,800
Prime contractor: Iowa State University
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU
Contract description of work:
This project includes, but is not limited to, a survey of existing interior room signage to determine the exact quantity, correct numbering, and notable space labeling for the installation of new room signage. Existing room signage will be removed and wall surfaces will be patched and repaired for installation of new accessible room signage.
Pearson Hall-Accessibility, Wayfinding, and Signage-Improvements Bid Date:
Pearson Hall-Electrical Panel-Replacement
CP number: CP1233198
Total Construction Budget: $358,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Pearson Hall-Electrical Panel-Replacement
Design-SD
Scope number: PS01
Project manager:
David Blum
Construction manager:
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, removing existing electrical panelboards and replacing them with new equipment in different locations. New electrical branch circuit panelboards, panelboard feeders, and branch circuits to be provided. Stairwell and corridor modifications will be provided to secure electrical panel enclosures.
Pearson Hall-Electrical Panel-Replacement Bid Date: 03/04/2025 (Tentative)
Poultry Farm-Teaching and Research Facilities
CP number: CP002490
Total Construction Budget: $7,948,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project replaces several poultry buildings that were over 70 years old, in unusable condition, and did not represent facilities needed for current chicken and turkey teaching and research industry needs. The project includes a 28,300 gsf chicken building and a 19,850 sf turkey building with research penning, automated ventilation, feeding, and lighting controls to support industry needs of Iowa and the nation with modern teaching and research facilities.
The project replaces several poultry buildings that were over 70 years old, in unusable condition, and did not represent facilities needed for current chicken and turkey teaching and research industry needs. The project includes a 28,300 gsf chicken building and a 19,850 sf turkey building with research penning, automated ventilation, feeding, and lighting controls to support industry needs of Iowa and the nation with modern teaching and research facilities.
Poultry Farm-Teaching and Research Facilities-Turkey Facility-Phase 2
Final Reporting
Scope number: PS03
Construction Budget: $898,000
Begin construction: 01/14/2022
Occupancy / completion: 08/10/2022
Gross sq.ft.: 3920
Net sq.ft.: 2940
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Huss
Construction manager:
Troy Chandler
Design Professional: CURRY WILLE & ASSOC
Contract description of work:
The project consists of, but is not limited to, materials and labor to build-out a 3920 square foot work area. This area has all of the under floor utilities installed, has a concrete floor, is in an insulated building enclosure, has drywall ceiling and perimeter walls. The ceiling and walls are not taped or finished. The project shall include constructing interior walls, electrical, mechanical, and plumbing.
Poultry Farm-Teaching and Research Facilities-Turkey Facility-Phase 2 Bid Date: 01/13/2022
Subcontractors (12)
Reiman Gardens Conservatory-Argus Control System-Replacement
CP number: CP1166947
Total Construction Budget: $149,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Reiman Gardens Conservatory-Argus Control System-Replacement
Construction
Scope number: PS01
Construction Budget: $65,500
Begin construction: 09/06/2023
Occupancy / completion: 05/31/2024
Prime contractor: JOHNSON CONTROLS INC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Contract description of work:
This project will replace the current Argus control system. This project includes, but is not limited to, mechanical work.
Reiman Gardens-Conservatory Chiller-Replacement
CP number: CP1110586
Total Construction Budget: $261,900
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Reiman Gardens-Conservatory Chiller-Replacement
Construction
Scope number: PS01
Construction Budget: $181,500
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Contract description of work:
This project will replace an existing air-conditioning chiller with a new chiller and downsize the breaker to match the new chiller electrical load. This project includes, but is not limited to, mechanical and electrical work.
Reiman Gardens-Conservatory Chiller-Replacement Bid Date:
ROTC Obstacle Course
CP number: CP988030
Total Construction Budget: $401,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the construction of a Marine Corps Obstacle Course (O-Course) to support the education and training of the University midshipmen, cadets, and active-duty personnel. The standard 40 ft x 400 ft course consists of seven obstacles and requires a relatively flat site with fencing for security and wood chip mulch ground cover for safety. Course obstacles will be constructed from wood and rope materials with a maximum height of 20 feet. Signage will indicate the nature and purpose of the O-Course.
This project includes, but is not limited to, the construction of a Marine Corps Obstacle Course (O-Course) to support the education and training of the University midshipmen, cadets, and active-duty personnel. The standard 40 ft x 400 ft course consists of seven obstacles and requires a relatively flat site with fencing for security and wood chip mulch ground cover for safety. Course obstacles will be constructed from wood and rope materials with a maximum height of 20 feet. Signage will indicate the nature and purpose of the O-Course.
ROTC Obstacle Course
Post Construction
Scope number: PS01
Construction Budget: $365,000
Begin construction: 12/08/2022
Occupancy / completion: 07/03/2023
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
The project consists of, but is not limited to, site grading, obstacle course equipment and footings, mulch, drainage, fencing, finish grading and topsoil.
ROTC Obstacle Course Bid Date: 11/03/2022
Subcontractors (2)
Scheman Building-Freight Elevators-Improvements
CP number: CP965415
Total Construction Budget: $302,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Scheman Building-Freight Elevators-Improvements
Bid
Scope number: PS01
Construction Budget: $275,000
Occupancy / completion: 07/29/2025
Project manager:
Kelly Kalvelage
Construction manager:
Steven Nelson
Design Professional: I&S GROUP INC
Contract description of work:
This project will upgrade the freight elevators in the Scheman Building. The scope of work includes, but is not limited to replacement of the doors, controllers, and door operating equipment in accordance with current code requirements.
Scheman Building-Renovation
CP number: CP943347
Total Construction Budget: $8,250,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will renovate portions of the ground floor main entrances, entry lobby, and restrooms and the first floor event and circulation spaces, and restrooms. The existing Benton Auditorium will be remodeled into a flexible event space with stage and seating areas. The project will also provide new food and beverage amenities and improvements to wayfinding and signage to improve the guest experience. The project will also upgrade existing mechanical and electrical systems to meet exiting codes and the requirements of the renovated spaces. No existing occupants will be relocated during construction or after the project is completed.
The project will renovate portions of the ground floor main entrances, entry lobby, and restrooms and the first floor event and circulation spaces, and restrooms. The existing Benton Auditorium will be remodeled into a flexible event space with stage and seating areas. The project will also provide new food and beverage amenities and improvements to wayfinding and signage to improve the guest experience. The project will also upgrade existing mechanical and electrical systems to meet exiting codes and the requirements of the renovated spaces. No existing occupants will be relocated during construction or after the project is completed.
Scheman Building-Renovation
Construction
Scope number: PS01
Construction Budget: $6,515,000
Begin construction: 04/08/2024
Occupancy / completion: 01/31/2025
Gross sq.ft.: 6800
Net sq.ft.: 5700
Prime contractor: STAHL CONSTRUCTION COMPANY
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
The project will renovate portions of the ground floor main entrances, entry lobby, and restrooms and the first floor event and circulation spaces, and restrooms. The existing Benton Auditorium will be remodeled into a flexible event space with stage and seating areas. The project will also provide new food and beverage amenities and improvements to wayfinding and signage to improve the guest experience.
The project will also upgrade existing mechanical and electrical systems to meet exiting codes and the requirements of the renovated spaces.
No existing occupants will be relocated during construction or after the project is completed.
Subcontractors (25)
Schilletter Village-Exterior Improvements-Phase 2
CP number: CP002499
Total Construction Budget: $649,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Schilletter Village-Exterior Improvements-Phase 2
Construction
Scope number: PS01
Construction Budget: $650,000
Occupancy / completion: 08/31/2022
Prime contractor: Multiple Constructors
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU - Department of Residence
Contract description of work:
CURRENT MAIN ENTRANCE DECKS WILL BE REMOVED, BUILDING FRAMING AND SIDING WILL BE REPAIRED AS NEEDED, AND THE DECKS WILL BE REPLACED. SECTIONS OF CONCRETE SIDEWALKS THAT HAVE SETTLED OVER TIME WILL BE REPLACED AS NEEDED. WINDOWS AND SOME EXTERIOR DOORS WILL BE REPLACED. THE SITE WILL BE REGRADED TO ROUTE WATER AWAY FROM THE WINDOW WELLS OF BUILDINGS WHERE THE BASEMENT FLOODS CONSISTENTLY.
Schilletter Village-Exterior Improvements-Phase 2 Bid Date:
Science Hall 2-Accessibility, Wayfinding, and Signage-Improvements
CP number: CP1003358
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Science Hall 2-Accessibility, Wayfinding, and Signage-Improvements
Construction
Scope number: PS01
Construction Budget: $126,300
Prime contractor: Iowa State University
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU
Contract description of work:
This project includes, but is not limited to, the survey of existing interior room signage to determine the exact quantity, correct numbering, and notable space labeling for the installation of new room signage. Any existing room signage and existing tackboards adjacent to door openings will be removed and wall surfaces will be patched and repaired for the installation of new accessible room signage.
Science Hall 2-Accessibility, Wayfinding, and Signage-Improvements Bid Date:
Science Hall-AHU 3-Replacement
CP number: CP1006655
Total Construction Budget: $380,883
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to replacement of Air Handling Unit 3 (AHU 3) in Room 0074A, including associated plumbing, ductwork, electrical service, insulation, controls, and removal and reconstruction of interior walls and doors as required.
This project includes, but is not limited to replacement of Air Handling Unit 3 (AHU 3) in Room 0074A, including associated plumbing, ductwork, electrical service, insulation, controls, and removal and reconstruction of interior walls and doors as required.
Science Hall-AHU 3-Replacement
Final Reporting
Scope number: PS01
Construction Budget: $400,000
Begin construction: 12/22/2022
Occupancy / completion: 08/23/2024
Gross sq.ft.: 513
Net sq.ft.: 513
Prime contractor: STEIN HEATING & COOLING INC
Project manager:
Mark Grief
Construction manager:
Steven Nelson
Design Professional: ISU - FDC
Contract description of work:
The project consists of, but is not limited to, the removal and replacement of Air Handling Unit 3 in Room 0074A of Science Hall. This work includes minor demolition of a masonry wall for a new door opening, demolition of existing piping, and demolition of existing ductwork associated with the demolition of the existing Air Handling Unit 3. Work also includes installing a new door and frame, insulating an existing wall, and installing a new air handling unit, ductwork, controls and associated piping with the installation of the unit.
Science Hall-AHU 3-Replacement Bid Date: 12/08/2022
Subcontractors (5)
Seed Science Building-Backup Generator-Installation
CP number: CP1264020
Total Construction Budget: $145,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Seed Science Building-Backup Generator-Installation
Design-SD
Scope number: PS01
Project manager:
Joshua Dank
Construction manager:
Design Professional: RAKER RHODES ENGINEERING LLC
Contract description of work:
This project will provide backup power for the cooling system in the seed storage room. Existing emergency circuits will also be rewired to the new generator. The scope of work includes, but is not limited to, a new generator, rewiring emergency electrical power circuits, new lighting, and any appurtenant work.
Seed Science Building-Backup Generator-Installation Bid Date: 03/13/2025 (Tentative)
Sloss House-Common Area Improvements
CP number: CP1177920
Total Construction Budget: $150,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Sloss House-Common Area Improvements
Post Construction
Scope number: PS01
Construction Budget: $146,300
Begin construction: 05/03/2024
Occupancy / completion: 11/11/2024
Gross sq.ft.: 800
Net sq.ft.: 800
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Hayley Sandholm
Construction manager:
Danelda Allen
Design Professional: CANNON MOSS BRYGGER & ASSOC
Contract description of work:
This project includes, but is not limited to, remodeling the exterior front entry railings, door and frame, side windows, and threshold. Also included is the interior remodeling of the wood trim, doors, flooring and windows, and painting the common spaces throughout the home.
Subcontractors (7)
Sports Performance Center & Jack Trice Stadium Improvements North
CP number: CP002505
Total Construction Budget: $71,650,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
A NEW FACILITY WILL BE CONSTRUCTED ON THE EAST SIDE OF THE BERGSTROM FOOTBALL COMPLEX THAT WILL BE USED BY ALL STUDENT-ATHLETES. THIS FACILITY WILL PROVIDE AN EXPANDED ACADEMIC AND STUDENT AFFAIRS CENTER, COMMONS AREA FOR STUDENTS TO GATHER AND INTERACT WITH FELLOW STUDENT-ATHLETES, AND A FULL SERVICE SPORTS NUTRITION CENTER INCLUDING FUELING STATIONS AND A DINING FACILITY THAT WILL BE STAFFED BY REGISTERED DIETICIANS. THE FACILITY WILL ALSO INCLUDE EXPANDED SERVICE AREAS INCLUDING SPORTS MEDICINE, STRENGTH AND CONDITIONING, AND LOCKER ROOMS FOR MULTIPLE VARSITY SPORTS.
A NEW FACILITY WILL BE CONSTRUCTED ON THE EAST SIDE OF THE BERGSTROM FOOTBALL COMPLEX THAT WILL BE USED BY ALL STUDENT-ATHLETES. THIS FACILITY WILL PROVIDE AN EXPANDED ACADEMIC AND STUDENT AFFAIRS CENTER, COMMONS AREA FOR STUDENTS TO GATHER AND INTERACT WITH FELLOW STUDENT-ATHLETES, AND A FULL SERVICE SPORTS NUTRITION CENTER INCLUDING FUELING STATIONS AND A DINING FACILITY THAT WILL BE STAFFED BY REGISTERED DIETICIANS. THE FACILITY WILL ALSO INCLUDE EXPANDED SERVICE AREAS INCLUDING SPORTS MEDICINE, STRENGTH AND CONDITIONING, AND LOCKER ROOMS FOR MULTIPLE VARSITY SPORTS.
Sports Performance Center & Jack Trice Stadium Improvements North-Bergstrom Football Complex-Rooms 2050, 2054, and 2056 Remodel
Final Reporting
Sports Performance Center & Jack Trice Stadium Improvements North-Sports Performance Center
Final Reporting
Stark Performance Center-Room 4290-Remodel
CP number: CP1252506
Total Construction Budget: $92,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Stark Performance Center-Room 4290-Remodel
Construction
Scope number: PS01
Construction Budget: $92,000
Begin construction: 09/23/2024
Occupancy / completion: 12/20/2024
Prime contractor: BOONE CONSTRUCTION INC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Contract description of work:
This project is remodeling room 4290 (north end of dining hall). Scope of work includes, but is not limited to, architectural and electrical remodeling.
Subcontractors (4)
State Gymnasium-Front Entry-Improvements
CP number: CP1172827
Total Construction Budget: $582,080
includes the bid estimate and contingency for this scope of work
Overall project description of work:
State Gymnasium-Front Entry-Improvements
Bid
Scope number: PS01
Construction Budget: $506,000
Begin construction: 05/19/2025
Occupancy / completion: 08/08/2025
Gross sq.ft.: 1940
Net sq.ft.: 1940
Project manager:
David Blum
Construction manager:
Mick McBride
Design Professional: CANNON MOSS BRYGGER & ASSOC
Contract description of work:
This project includes, but is not limited to, improvements to the front entry lobby, front checkout desk, and associated access control systems serving the east and west buildings of the State Gymnasium.
State Gymnasium-Front Entry-Improvements Bid Date: 02/13/2025
Stephens Auditorium-Roof Replacement-Section A
CP number: CP002745
Total Construction Budget: $412,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, REMOVAL AND REPLACEMENT OF THE NORTH PORTION, SECTION A, OF STEPHENS AUDITORIUM ROOF THAT WAS DAMAGED BY HAIL. THIS INCLUDES REMOVAL OF EXISTING ROOF MEMBRANE AND INSTALLATION, INSTALLATION OF NEW 5 INCH RIGID INSULATION, MOISTURE RESISTANT BACKER BOARD, 90 MIL EPDM-30 YEAR MEMBRANE, AND NEW PREFINISHED METAL FLASHING.
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, REMOVAL AND REPLACEMENT OF THE NORTH PORTION, SECTION A, OF STEPHENS AUDITORIUM ROOF THAT WAS DAMAGED BY HAIL. THIS INCLUDES REMOVAL OF EXISTING ROOF MEMBRANE AND INSTALLATION, INSTALLATION OF NEW 5 INCH RIGID INSULATION, MOISTURE RESISTANT BACKER BOARD, 90 MIL EPDM-30 YEAR MEMBRANE, AND NEW PREFINISHED METAL FLASHING.
Stephens Auditorium-Roof Replacement-Section A
Final Reporting
Scope number: PS01
Construction Budget: $412,500
Begin construction: 05/03/2022
Occupancy / completion: 10/30/2022
Gross sq.ft.: 23550
Net sq.ft.: 23550
Prime contractor: BLACK HAWK ROOF CO INC
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: I&S GROUP INC
Contract description of work:
The project consists of, but is not limited to, installing new fully adhered 90 mil EPDM roof membrane and insulation system over the existing roof membrane and insulation. Provide and install new flashings and roof expansion covers.
Stephens Auditorium-Roof Replacement-Section A Bid Date: 04/28/2022
Student Innovation Center
CP number: CP002225
Total Construction Budget: $60,575,494
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL CONSTRUCT A NEW STUDENT-FOCUSED FACILITY THAT WILL PROVIDE A HIGH-QUALITY, CENTRALIZED SPACE TO SUPPORT A STUDENT-DRIVEN CULTURE OF INNOVATION THAT EXEMPLIFIES THE CONVERGENT FUTURE OF PRACTICES AND LEADERS. THE CENTER WILL BE A HIGHLY FLEXIBLE, DYNAMIC SPACE THAT ENCOURAGES EXPERIMENTATION, INNOVATION AND INTERDISCIPLINARY INVESTIGATION BY PROVIDING SPACE FOR PROTOTYPING, FABRICATION AND SMALL SCALE SPACES FOR BENCH-TOP SIZED PROJECTS ALONGSIDE STATE OF THE ART CLASSROOMS WITH EASY ACCESS TO SPECIALIZED EQUIPMENT, MATERIALS, TOOLS, AS WELL AS SPACE FOR COMPUTER-AIDED DESIGN AND VIRTUAL REALITY FACILITIES.
THIS PROJECT WILL CONSTRUCT A NEW STUDENT-FOCUSED FACILITY THAT WILL PROVIDE A HIGH-QUALITY, CENTRALIZED SPACE TO SUPPORT A STUDENT-DRIVEN CULTURE OF INNOVATION THAT EXEMPLIFIES THE CONVERGENT FUTURE OF PRACTICES AND LEADERS. THE CENTER WILL BE A HIGHLY FLEXIBLE, DYNAMIC SPACE THAT ENCOURAGES EXPERIMENTATION, INNOVATION AND INTERDISCIPLINARY INVESTIGATION BY PROVIDING SPACE FOR PROTOTYPING, FABRICATION AND SMALL SCALE SPACES FOR BENCH-TOP SIZED PROJECTS ALONGSIDE STATE OF THE ART CLASSROOMS WITH EASY ACCESS TO SPECIALIZED EQUIPMENT, MATERIALS, TOOLS, AS WELL AS SPACE FOR COMPUTER-AIDED DESIGN AND VIRTUAL REALITY FACILITIES.
Student Innovation Center-Dust Collection System
Final Reporting
Scope number: PS02
Construction Budget: $312,000
Begin construction: 12/18/2020
Occupancy / completion: 04/02/2021
Prime contractor: ACI MECHANICAL INC
Project manager:
Elizabeth Clarke
Construction manager:
Nathan Graves
Design Professional: SUBSTANCE ARCHITECTURE
Contract description of work:
The project consists of, but is not limited to, installation of a new dust collection system serving the level 1 fabrication space in the Student Innovation Center. Work requires selective demolition, installation of a full dust collection system including controls, fire suppression, compressed air, and all other items to support the full system, and integration with existing building systems.
Student Innovation Center-Dust Collection System Bid Date: 12/17/2020
Subcontractors (5)
Student Services Building-First Floor-Remodel
CP number: CP1235453
Total Construction Budget: $480,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Student Services Building-First Floor-Remodel
Construction
Scope number: PS01
Construction Budget: $480,600
Begin construction: 10/29/2024
Occupancy / completion: 08/01/2025
Prime contractor: HPC LLC
Project manager:
Angela Solberg
Construction manager:
Mick McBride
Design Professional: OFFICE OF HARTMAN SPILLER TRAPP
Contract description of work:
This project will convert two offices into a more centrally located conference room, convert the conference room in the office suite area into three new offices, create an office suite for the Dean of Students, and upgrade finishes in multiple offices and corridors to match other recently completed interior improvements. This project includes, but is not limited to, architectural, mechanical, electrical, technology, equipment, finishes, and furniture.
Subcontractors (10)
Sukup Basketball Complex-Rooms 1110 and 1210-Improvements
CP number: CP1233823
Total Construction Budget: $148,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Sukup Basketball Complex-Rooms 1110 and 1210-Improvements
Scope number: PS01
Project manager:
Jonathan Harvey
Construction manager:
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
This project includes, but is not limited to, updating the existing fueling stations at the Sukup Basketball Complex for both the Men’s and Women’s Basketball teams. The project will include new shelving and cabinets, flooring, and add a new security door to the space and lighting in the team room area.
Sukup Basketball Complex-Rooms 1110 and 1210-Improvements Bid Date: TBD
Sukup Basketball Complex-Rooms 1124 & 1125-Renovation
CP number: CP964890
Total Construction Budget: $740,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to new lockers, new flooring, new wall finishes, new ceilings and lighting, demolition and new wall construction, renovated shower and restroom fixtures, and updated graphics.
This project includes, but is not limited to new lockers, new flooring, new wall finishes, new ceilings and lighting, demolition and new wall construction, renovated shower and restroom fixtures, and updated graphics.
Sukup Basketball Complex-Rooms 1124 & 1125-Renovation
Post Construction
Scope number: PS01
Construction Budget: $720,164
Begin construction: 05/03/2023
Occupancy / completion: 10/01/2023
Gross sq.ft.: 2860
Net sq.ft.: 2680
Prime contractor: BREIHOLZ CONSTRUCTION COMPANY
Project manager:
Jonathan Harvey
Construction manager:
Nathan Graves
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
The project consists of, but is not limited to, demolition of existing finishes and walls; installation of new stud walls, flooring, finishes, and ceilings; new lighting; and modifications to existing mechanical system.
Subcontractors (15)
Surplus Warehouse
CP number: CP1000965
Total Construction Budget: $423,500
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Surplus Warehouse
Final Reporting
Scope number: PS01
Construction Budget: $423,500
Begin construction: 06/07/2023
Occupancy / completion: 09/05/2023
Gross sq.ft.: 6600
Net sq.ft.: 6600
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Jennifer Evans
Construction manager:
Ben Haywood
Design Professional: CURRY WILLE & ASSOC
Contract description of work:
This project includes, but is not limited to, the construction of a new 6,600 sf warehouse, north of the existing Surplus Facility.
Subcontractors (7)
Sweeney Hall-Room 1058-Remodel
CP number: CP1175457
Total Construction Budget: $120,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Sweeney Hall-Room 1058-Remodel
Post Construction
Scope number: PS01
Construction Budget: $146,960
Begin construction: 03/28/2024
Occupancy / completion: 07/03/2024
Gross sq.ft.: 800
Net sq.ft.: 800
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Hayley Sandholm
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Contract description of work:
This project will remodel an existing research lab space to accommodate the needs and usage of Chemical and Biological Engineering and to make space for the new Biomedical Engineering major program. This project includes, but is not limited to, the demolition of existing wall-mounted items, patching and repairing of walls, new flooring, a new water line, compressed air, and reconfiguring power to accommodate new lab usage.
Subcontractors (6)
Sweeney Hall-Rooms 2038 and 2058-Remodel
CP number: CP1200333
Total Construction Budget: $237,490
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Sweeney Hall-Rooms 2038 and 2058-Remodel
Scope number: PS01
Construction Budget: $227,900
Begin construction: 06/18/2024
Occupancy / completion: 11/17/2024
Gross sq.ft.: 1700
Net sq.ft.: 1700
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Hayley Sandholm
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, remodeling two adjacent laboratories to connect them and add the infrastructure needed for research. Work will include new data, lighting, ceilings, finish patch and repair as needed, corrected water and air locations, and new lab casework.
Subcontractors (10)
Therkildsen Industrial Engineering Building
CP number: CP002619
Total Construction Budget: $54,928,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will build a new facility for the Department of Industrial and Manufacturing Systems Engineering (IMSE) of the College of Engineering. The new building will provide space for teaching and research labs, classrooms, and office space. Parking will also be provided to replace that displaced by the new building
This project will build a new facility for the Department of Industrial and Manufacturing Systems Engineering (IMSE) of the College of Engineering. The new building will provide space for teaching and research labs, classrooms, and office space. Parking will also be provided to replace that displaced by the new building
Therkildsen Industrial Engineering Building
Construction
Scope number: PS01
Construction Budget: $50,250,000
Begin construction: 09/29/2022
Occupancy / completion: 11/30/2024
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Elizabeth Clarke
Construction manager:
Danelda Allen
Design Professional: S-L-A-M COLLABORATIVE INC
Contract description of work:
The project consists of, but is not limited to, the design and construction of a new four-story stand-alone building located southwest of Howe Hall and north of Thielen Student Health Center for the Department of Industrial and Manufacturing Systems Engineering (IMSE) of the College of Engineering including site development, utility infrastructure improvements, and building construction.
Therkildsen Industrial Engineering Building Bid Date: 08/19/2022
Subcontractors (39)
Town Engineering Building-AHU2 Supply Fan-Replacement
CP number: CP1251054
Total Construction Budget: $67,600
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Town Engineering Building-AHU2 Supply Fan-Replacement
Design-CD
Scope number: PS01
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Contract description of work:
This project will replace the supply fan, SF2, within air handling unit, AHU2 in Room 0500. This project includes, but is not limited to, mechanical and electrical work.
Town Engineering Building-AHU2 Supply Fan-Replacement Bid Date: TBD
Town Engineering Building-Common Area Improvements
CP number: CP1167152
Total Construction Budget: $233,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Town Engineering Building-Common Area Improvements
Quote
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, updating finishes, graphics and signage, wayfinding, and improving views into existing laboratories with new doors from corridors.
Town Engineering Building-Common Area Improvements Bid Date:
Town Engineering Building-Facility and Infrastructure-Improvements
CP number: CP1001182
Total Construction Budget: $240,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to, the purchase of a 3D concrete printer and electrohydraulic pump system, as well as mechanical, electrical, ventilation, storage, and other facility improvements to support the equipment and other analytical instrumentation for instructional and research laboratory needs. Dock improvements to support storage and access for materials handling equipment; renovations to rooms that support the geotechnical and materials engineering, environmental engineering, and water resources engineering research and instruction will be designed and implemented as feasible.
This project includes, but is not limited to, the purchase of a 3D concrete printer and electrohydraulic pump system, as well as mechanical, electrical, ventilation, storage, and other facility improvements to support the equipment and other analytical instrumentation for instructional and research laboratory needs. Dock improvements to support storage and access for materials handling equipment; renovations to rooms that support the geotechnical and materials engineering, environmental engineering, and water resources engineering research and instruction will be designed and implemented as feasible.
Town Engineering Building-Facility and Infrastructure-Improvements-480V Electric and Chilled Water
Post Construction
Scope number: PS01
Construction Budget: $234,750
Begin construction: 08/03/2023
Occupancy / completion: 02/16/2024
Prime contractor: PROCTOR MECHANICAL
Project manager:
Angela Solberg
Construction manager:
Kasi Province
Design Professional: BROOKS BORG SKILES ARCH ENGR
Contract description of work:
This project consists of, but is not limited to, tap existing chilled water mains in basement and install chilled water piping to new heat exchanger in the basement mechanical room. Install pump, air/dirt separator, expansion tank and process water loop piping for two electrohydraulic pumps. Tap existing 480V service, install new disconnect, two new panels, conduit, wiring and hook-ups for concrete robot, two stud welders, two hydraulic pumps and one process chilled water pump and VFD.
Subcontractors (3)
Utilities-Gilman Steam Tunnel-Repairs
CP number: CP002740
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO: • RECONSTRUCTION OF APPROXIMATELY 40 FEET OF THE STEAM TUNNEL LOCATED BENEATH THE SOUTH ENTRANCE OF GILMAN HALL • RECONSTRUCTION OF THE SOUTH ENTRY STEPS INTO GILMAN HALL • REMOVAL AND RECONSTRUCTION OF A SECTION OF OSBORN STREET
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO: • RECONSTRUCTION OF APPROXIMATELY 40 FEET OF THE STEAM TUNNEL LOCATED BENEATH THE SOUTH ENTRANCE OF GILMAN HALL • RECONSTRUCTION OF THE SOUTH ENTRY STEPS INTO GILMAN HALL • REMOVAL AND RECONSTRUCTION OF A SECTION OF OSBORN STREET
Utilities-Gilman Steam Tunnel-Repairs
On Hold
Scope number: PS01
Project manager:
Michael Olson
Construction manager:
Michael Olson
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
Utilities-Gilman Steam Tunnel-Repairs Bid Date: TBD
Utilities-NW Campus Substation to EE Substation Cable Infrastructure Upgrade
CP number: CP1238639
Total Construction Budget: $385,100
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-NW Campus Substation to EE Substation Cable Infrastructure Upgrade
Design-CD
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Caleb Barduson
Construction manager:
Caleb Barduson
Design Professional: ISU - Utilities
Contract description of work:
This project includes, but is not limited to, installation and splicing of new 13,800 volt, 3-phase, 750kcmil cable, and #3/0 ground wire through existing underground conduits and vaults between NW Campus Substation and EE Substation switchgear. The cable will be hi-pot tested after installation. Utility Distribution High Voltage Electricians will install cable terminations at each substation switchgear.
Utilities-NW Campus Substation to EE Substation Cable Infrastructure Upgrade Bid Date:
Utilities-Power Plant-Chiller #3 Turbine Overhaul FY25
CP number: CP1250472
Total Construction Budget: $320,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-Chiller #3 Turbine Overhaul FY25
Scope number: PS01
Project manager:
Lee Mason
Construction manager:
Lee Mason
Contract description of work:
This project includes, but is not limited to, opening, cleaning, and inspecting the steam turbine on Chiller #3.
Utilities-Power Plant-Chiller #3 Turbine Overhaul FY25 Bid Date: TBD
Utilities-Power Plant-Chiller 5 Compressor Overhaul FY23
CP number: CP1044984
Total Construction Budget: $320,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-Chiller 5 Compressor Overhaul FY23
On Hold
Scope number: PS01
Construction Budget: $320,000
Prime contractor: Multiple Constructors
Project manager:
Matthew Shriver
Construction manager:
Matthew Shriver
Design Professional: ISU - Utilities
Contract description of work:
This project includes, but is not limited to, opening, cleaning, and inspecting the refrigerant compressor on Chiller 5. Compressor components found worn or damaged will be repaired or replaced.
Utilities-Power Plant-Chiller 5 Compressor Overhaul FY23 Bid Date:
Utilities-Power Plant-Coal Boilers Natural Gas Conversion
CP number: CP002712
Total Construction Budget: $13,600,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project will convert the two remaining coal fired boilers (boilers #1 & #2) in the university central cogeneration plant to natural gas-fired boilers, ending the use of coal by Iowa State University. The conversion includes modifying the boiler existing burners and fans along with removing the auxiliary coal handling systems. In addition, the project will restore two coal storage sites (east of Haber road and adjacent to the plant).
This project will convert the two remaining coal fired boilers (boilers #1 & #2) in the university central cogeneration plant to natural gas-fired boilers, ending the use of coal by Iowa State University. The conversion includes modifying the boiler existing burners and fans along with removing the auxiliary coal handling systems. In addition, the project will restore two coal storage sites (east of Haber road and adjacent to the plant).
Utilities-Power Plant-Coal Boilers Natural Gas Conversion
Post Construction
Scope number: PS01
Construction Budget: $13,600,000
Begin construction: 10/08/2021
Occupancy / completion: 09/28/2023
Prime contractor: BOWEN ENGINEERING CORP
Project manager:
Construction manager:
Lee Mason
Design Professional: ISU - Utilities
Contract description of work:
This project will convert the two remaining coal-fired boilers (Boilers #1 & #2) in the University's central cogeneration plant to natural gas-fired boilers, ending the use of coal by Iowa State University. The conversion includes modifying the boiler's existing burners and fans along with removing the auxiliary coal handling systems. In addition, the project will restore two coal storage sites (east of Haber Road and adjacent to the Power Plant).
Utilities-Power Plant-Coal Boilers Natural Gas Conversion Bid Date: TBD
Subcontractors (5)
Utilities-Power Plant-External Stack Repairs
CP number: CP002607
Total Construction Budget: $960,730
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-External Stack Repairs
On Hold
Scope number: PS01
Prime contractor: Multiple Constructors
Project manager:
Lee Mason
Construction manager:
Lee Mason
Contract description of work:
THIS PROJECT WILL REPLACE EXISTING PLATFORMS, INSTALL A NEW STACK FALL PROTECTION SYSTEM, REPLACE CONDUITS, AND CLEAN AND PAINT THE EXTERIOR OF THE STACK.
Utilities-Power Plant-External Stack Repairs Bid Date:
Utilities-Power Plant-Post AC2 Fire-Improvements
CP number: CP1231604
Total Construction Budget: $81,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-Post AC2 Fire-Improvements
Scope number: PS01
Construction Budget: $90,000
Gross sq.ft.: 10000
Net sq.ft.: 6000
Prime contractor: Multiple Constructors
Project manager:
Matthew Shriver
Construction manager:
Matthew Shriver
Design Professional: ISU - Utilities
Contract description of work:
This project includes, but is not limited to, the replacement of equipment damaged when Air Compressor 2 caught on fire. A new air compressor and air dryer will be installed along with some new compressed air flow transmitters. The project also includes the removal of the damaged equipment and cleaning of the room where the fire occurred.
Utilities-Power Plant-Post AC2 Fire-Improvements Bid Date:
Utilities-Power Plant-Pressure Reducing Valve-Replacement
CP number: CP1261458
Total Construction Budget: $501,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-Pressure Reducing Valve-Replacement
Scope number: PS01
Project manager:
Ethan Gritton
Construction manager:
Contract description of work:
This project will increase the current capacity to directly convert 400 psi steam to heating steam by 100,000 pounds per hour. This project includes, but is not limited to, scanning the current plant piping, design solution for new piping arrangement, replacement of Pressure Reducing Valve and Desuperheater Valve, and the reconfiguration of pipe directly towards heating header.
Utilities-Power Plant-Pressure Reducing Valve-Replacement Bid Date: TBD
Utilities-Power Plant-Service Water Pump-Replacement
CP number: CP1240383
Total Construction Budget: $320,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-Service Water Pump-Replacement
Construction
Scope number: PS01
Construction Budget: $283,175
Begin construction: 08/13/2024
Occupancy / completion: 03/03/2025
Prime contractor: ARC MECHANICAL INC
Project manager:
Lee Mason
Construction manager:
Lee Mason
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
This project includes, but is not limited to, replacing the current 2 service water pumps with 4 service water pumps with VFDs (variable frequency drive), modified piping, manual valves, and new control valves.
Subcontractors (3)
Utilities-Power Plant-Station Power Improvements
CP number: CP002466
Total Construction Budget: $4,474,790
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL REPLACE AND RECONFIGURE THE STATION POWER SYSTEM WITHIN THE UNIVERSITY POWER PLANT. THE STATION POWER SYSTEM CONSISTS OF THE INTERNAL 15,000 AND 5,000 VOLT SWITCHGEAR, INTERNAL SUBSTATIONS, 480 VOLT LOAD CENTERS, MOTOR CONTROL CENTERS, AND ESSENTIAL POWER SYSTEMS. THE PROJECT WILL TAKE PLACE IN MULTIPLE PHASES OVER MULTIPLE YEARS IN ORDER TO MAINTAIN PLANT OPERATIONS.
THIS PROJECT WILL REPLACE AND RECONFIGURE THE STATION POWER SYSTEM WITHIN THE UNIVERSITY POWER PLANT. THE STATION POWER SYSTEM CONSISTS OF THE INTERNAL 15,000 AND 5,000 VOLT SWITCHGEAR, INTERNAL SUBSTATIONS, 480 VOLT LOAD CENTERS, MOTOR CONTROL CENTERS, AND ESSENTIAL POWER SYSTEMS. THE PROJECT WILL TAKE PLACE IN MULTIPLE PHASES OVER MULTIPLE YEARS IN ORDER TO MAINTAIN PLANT OPERATIONS.
Utilities-Power Plant-Station Power Improvements-Phase 4
Post Construction
Utilities-Power Plant-Station Power Improvements-Phase 5
Construction
Utilities-Power Plant-Turbine Generator #6 Overhaul FY24
CP number: CP1176045
Total Construction Budget: $697,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Power Plant-Turbine Generator #6 Overhaul FY24
Scope number: PS01
Construction Budget: $697,000
Prime contractor: Multiple Constructors
Project manager:
Nicholas Kolbet
Construction manager:
Nicholas Kolbet
Design Professional: ISU - Utilities
Contract description of work:
This project will inspect, overhaul and repair/replace damaged components within Turbine Generator #6 which may include, but is not limited to, steam turbine, rotor speed reduction gearbox, and electric generator.
Utilities-Power Plant-Turbine Generator #6 Overhaul FY24 Bid Date:
Utilities-Richardson Court-Water Main-Improvements
CP number: CP1233097
Total Construction Budget: $228,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Richardson Court-Water Main-Improvements
Post Construction
Scope number: PS01
Construction Budget: $197,186
Begin construction: 04/17/2024
Occupancy / completion: 08/09/2024
Prime contractor: SYNERGY CONTRACTING LLC
Project manager:
Laramie Heuser
Construction manager:
Laramie Heuser
Design Professional: ISU - Utilities
Contract description of work:
The project includes, but is not limited to, replacing approximately 950 feet of iron water main pipe with a larger diameter HDPE pipe in the Richardson Court Area. HDPE is an EPA and DNR-approved water main pipe material that will not corrode, which should reduce future maintenance costs.
Subcontractors (2)
Utilities-Switchgear Vault 24 and 25-Replacement
CP number: CP1146935
Total Construction Budget: $337,370
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Utilities-Switchgear Vault 24 and 25-Replacement
Construction
Scope number: PS01
Construction Budget: $393,170
Begin construction: 01/17/2025
Occupancy / completion: 08/14/2026
Prime contractor: C GREEN CONTRACTOR INC
Project manager:
Travis Van Dyke
Construction manager:
Travis Van Dyke
Design Professional: SHIVE HATTERY ARCHITECTURE & ENGINEERING
Contract description of work:
This project replaces two high-voltage electrical Switches, 24 and 25, with new switches near Estes Hall and Carver Hall, respectively. The new Switch 24 will be located at an above-ground pad north of Estes Hall. The new Switch 25 will be located in a new underground vault west of the existing vault. In both cases, the existing vaults will remain, repurposed to aid future cable installations. New underground conduit will also be added to each of the new vaults, and a new high-voltage cable will be installed between Switch 25 and Estes Hall.
Utilities-Various Buildings-Fire Detection System
CP number: CP002667
Total Construction Budget: $193,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL INSTALL A FIRE ALARM AND DETECTION SYSTEM FOR AUXILIARY BUILDINGS THAT SUPPORT THE POWER PLANT. THESE BUILDINGS INCLUDE COOLING TOWER SERVICE BUILDING, COOLING TOWER CONTROL BUILDING AND THE VET MED PUMP HOUSE. THE PROJECT WILL CONNECT THE NEW ALARM AND DETECTION SYSTEMS TO EXISTING MASTER FIRE ALARM PANELS LOCATED IN THE MAIN AND VET MED POWER PLANTS.
THIS PROJECT WILL INSTALL A FIRE ALARM AND DETECTION SYSTEM FOR AUXILIARY BUILDINGS THAT SUPPORT THE POWER PLANT. THESE BUILDINGS INCLUDE COOLING TOWER SERVICE BUILDING, COOLING TOWER CONTROL BUILDING AND THE VET MED PUMP HOUSE. THE PROJECT WILL CONNECT THE NEW ALARM AND DETECTION SYSTEMS TO EXISTING MASTER FIRE ALARM PANELS LOCATED IN THE MAIN AND VET MED POWER PLANTS.
Utilities-Various Buildings-Fire Detection System
On Hold
Scope number: PS01
Project manager:
Lee Mason
Construction manager:
Lee Mason
Design Professional: HR GREEN INC
Contract description of work:
This project will install a fire alarm and detection system for auxiliary buildings that support the Power Plant. These buildings include Cooling Tower Service Building, Cooling Tower Control Building and the Veterinary Medicine Pump House. The project will connect the new alarm and detection systems to existing master fire alarm panels located in the main and Veterinary Medicine power plants.
Utilities-Various Buildings-Fire Detection System Bid Date: TBD
Utilities-Veenker Memorial Golf Course-Well Installation
CP number: CP1161151
Total Construction Budget: $409,400
includes the bid estimate and contingency for this scope of work
Overall project description of work:
The project will install a water well and associated small pump house on Veenker Memorial Golf Course to provide water for course irrigation. The new well will replace a recently failed water line running between the main campus and the golf course irrigation pond.
The project will install a water well and associated small pump house on Veenker Memorial Golf Course to provide water for course irrigation. The new well will replace a recently failed water line running between the main campus and the golf course irrigation pond.
Utilities-Veenker Memorial Golf Course-Well Installation
Construction
Scope number: PS01
Construction Budget: $352,500
Begin construction: 12/01/2023
Occupancy / completion: 04/06/2024
Prime contractor: LARSON WELL CO LLC
Project manager:
Laramie Heuser
Construction manager:
Laramie Heuser
Design Professional: SNYDER & ASSOC INC
Contract description of work:
The project consists of, but is not limited to, the installation of an irrigation well, well pump, electrical service, pump controls, and associated piping.
Subcontractors (3)
Various Building Automation Improvements FY24
CP number: CP1176342
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Various Building Automation Improvements FY24
Construction
Scope number: PS01
Construction Budget: $257,666
Prime contractor: Iowa State University
Project manager:
Construction manager:
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, building automation upgrades for controlling HVAC systems.
Various Building Automation Improvements FY24 Bid Date:
Various Building Safety Improvements FY24
CP number: CP1176353
Total Construction Budget: $
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Various Building Safety Improvements FY24
Construction
Scope number: PS01
Construction Budget: $90,000
Prime contractor: Iowa State University
Project manager:
John Netwal
Construction manager:
John Netwal
Design Professional: ISU - FDC
Contract description of work:
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Various Building Safety Improvements FY24 Bid Date:
Various Campus Locations-Ash Tree Removal and Replacement
CP number: CP1105518
Total Construction Budget: $113,330
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Various Campus Locations-Ash Tree Removal and Replacement
Post Construction
Scope number: PS01
Construction Budget: $121,480
Prime contractor: Multiple Constructors
Project manager:
Rhonda Martin
Construction manager:
Rhonda Martin
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the removal of over 100 remaining ash trees and the installation of replacement trees of various varieties on campus. The trees must be removed as all will eventually be killed by the invasive emerald ash borer. The project will allow removal of dying ash trees in areas that are in general-fund maintained areas of campus and the responsibility of the Department of Residence and the Athletic Department.
Various Campus Locations-Ash Tree Removal and Replacement Bid Date:
Veterinary Diagnostic Laboratory-Phase 2
CP number: CP1119681
Total Construction Budget: $51,235,800
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project proposes an addition to the currently authorized and under-construction Veterinary Diagnostic Laboratory (VDL) Building, providing approximately 78,500 gsf of additional space to co-locate the remaining testing sections of the laboratory, diagnostic research activities, and administrative staff with the front-end sample processing and receiving functions of the lab. This project will include the following critical functions and sections: • Analytical Chemistry, Bioinformatics, BSL3 Diagnostic Lab Space, Molecular Diagnostics, Sequencing, Serology, and Virology • VDL administration, quality assurance, information technology, and epidemiological services. • Research space for development of new assays to detect emerging diseases and toxicosis This project will also evaluate the following program spaces as alternates: Basement (Storage) The additional space will provide optimal process flow, required functional relationships, appropriate biocontainment and biosafety, and address the required growth in critical programmatic space needs. It will provide additional space needed to further integrate diagnostic medicine education. Public access will be provided to administrative functions and meeting areas, while materials, samples, animal receiving, and disposal areas will be isolated from the public and other college receiving functions.
This project proposes an addition to the currently authorized and under-construction Veterinary Diagnostic Laboratory (VDL) Building, providing approximately 78,500 gsf of additional space to co-locate the remaining testing sections of the laboratory, diagnostic research activities, and administrative staff with the front-end sample processing and receiving functions of the lab. This project will include the following critical functions and sections: • Analytical Chemistry, Bioinformatics, BSL3 Diagnostic Lab Space, Molecular Diagnostics, Sequencing, Serology, and Virology • VDL administration, quality assurance, information technology, and epidemiological services. • Research space for development of new assays to detect emerging diseases and toxicosis This project will also evaluate the following program spaces as alternates: Basement (Storage) The additional space will provide optimal process flow, required functional relationships, appropriate biocontainment and biosafety, and address the required growth in critical programmatic space needs. It will provide additional space needed to further integrate diagnostic medicine education. Public access will be provided to administrative functions and meeting areas, while materials, samples, animal receiving, and disposal areas will be isolated from the public and other college receiving functions.
Veterinary Diagnostic Laboratory-Phase 2
Construction
Scope number: PS01
Construction Budget: $51,235,800
Begin construction: 03/27/2024
Occupancy / completion: 10/30/2026
Gross sq.ft.: 78805
Net sq.ft.: 75015
Prime contractor: HANSEN COMPANY INC
Project manager:
David Blum
Construction manager:
Troy Chandler
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
This project proposes an addition to the currently authorized and under-construction Veterinary Diagnostic Laboratory (VDL) Building, providing approximately 78,500 gsf of additional space to co-locate the remaining testing sections of the laboratory, diagnostic research activities, and administrative staff with the front-end sample processing and receiving functions of the lab.
Subcontractors (25)
Veterinary Medicine-Domestic Water Line Replacement-Phase 7
CP number: CP1170291
Total Construction Budget: $410,383
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Veterinary Medicine-Domestic Water Line Replacement-Phase 7
Scope number: PS01
Construction Budget: $355,279
Begin construction: 05/01/2024
Occupancy / completion: 01/06/2025
Prime contractor: MANNING SEIVERT MECHANICAL CONTRACTORS INC
Project manager:
Mark Grief
Construction manager:
Mick McBride
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the replacement of the deteriorating galvanized domestic water lines in the facility and to continue to add isolation values to improve the zoning of the domestic water service. The original galvanized piping will be replaced by copper piping and will include isolation gate valves to support ongoing and future maintenance of this facility.
Subcontractors (3)
Veterinary Medicine-Room 1351-Remodel
CP number: CP930111
Total Construction Budget: $1,550,974
includes the bid estimate and contingency for this scope of work
Overall project description of work:
This project includes, but is not limited to demolition of the existing interior horse stalls, new LED lighting and electrical outlets, new finishes, including impervious surfaces, floor, walls, and ceiling in specified areas, mechanical upgrades to maintain a minimum required air changes, and biosafety Level 2 Lab requirement in a small portion of the lab.
This project includes, but is not limited to demolition of the existing interior horse stalls, new LED lighting and electrical outlets, new finishes, including impervious surfaces, floor, walls, and ceiling in specified areas, mechanical upgrades to maintain a minimum required air changes, and biosafety Level 2 Lab requirement in a small portion of the lab.
Veterinary Medicine-Room 1351-Remodel
Scope number: PS01
Construction Budget: $1,497,598
Begin construction: 03/27/2023
Occupancy / completion: 02/10/2024
Gross sq.ft.: 2651
Net sq.ft.: 2651
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
John Boehmer
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
This project includes, but is not limited to the demolition of the existing interior horse stalls, new LED lighting and electrical outlets, new finishes, including impervious surfaces, floor, walls, and ceiling in specified areas, mechanical upgrades to maintain a minimum required air changes, and biosafety Level 2 Lab requirement in a small portion of the lab.
Subcontractors (15)
Veterinary Medicine-Veterinary Diagnostic Laboratory
CP number: CP002554
Total Construction Budget: $55,800,000
includes the bid estimate and contingency for this scope of work
Overall project description of work:
THIS PROJECT WILL CONSTRUCT A NEW TWO-STORY STAND-ALONE VDL ON THE COLLEGE OF VETERINARY MEDICINE CAMPUS TO SERVE THE DIAGNOSTIC MEDICINE NEEDS OF THE IOWA LIVESTOCK AND POULTRY INDUSTRIES, PETS AND WILDLIFE, AND PROTECT HUMAN HEALTH AND IOWA ECONOMY. THE NEW FACILITY WILL ADDRESS THE MOST URGENT SPACE REQUIREMENTS FOR THE LABORATORY, IMPROVE BIOCONTAINMENT, AND ENHANCE BIOSAFETY STANDARDS TO PROTECT EMPLOYEE AND STUDENT HEALTH AS THEY WORK TO PROCESS OVER 90,000 CASES EACH YEAR.
THIS PROJECT WILL CONSTRUCT A NEW TWO-STORY STAND-ALONE VDL ON THE COLLEGE OF VETERINARY MEDICINE CAMPUS TO SERVE THE DIAGNOSTIC MEDICINE NEEDS OF THE IOWA LIVESTOCK AND POULTRY INDUSTRIES, PETS AND WILDLIFE, AND PROTECT HUMAN HEALTH AND IOWA ECONOMY. THE NEW FACILITY WILL ADDRESS THE MOST URGENT SPACE REQUIREMENTS FOR THE LABORATORY, IMPROVE BIOCONTAINMENT, AND ENHANCE BIOSAFETY STANDARDS TO PROTECT EMPLOYEE AND STUDENT HEALTH AS THEY WORK TO PROCESS OVER 90,000 CASES EACH YEAR.
Veterinary Medicine-Veterinary Diagnostic Laboratory
Post Construction
Scope number: PS01
Construction Budget: $56,800,000
Begin construction: 10/06/2020
Occupancy / completion: 09/21/2023
Gross sq.ft.: 68624
Net sq.ft.: 41200
Prime contractor: WEITZ COMPANY INC
Project manager:
David Blum
Construction manager:
Nathan Graves
Design Professional: INVISION ARCHITECTURE LTD
Contract description of work:
The Project consists of, but is not limited to, the design and construction of a new two story stand-alone Veterinary Diagnostic Laboratory (VDL) building on the College of Veterinary Medicine campus. This new facility will serve the diagnostic medicine needs of Iowa livestock and poultry, pets and wildlife, and in the process, protect human health and grow Iowa economy. In addition, the facility will address the most urgent space requirements for the laboratory, improve biocontainment, and enhance biosafety standards to protect employee and student health.
Veterinary Medicine-Veterinary Diagnostic Laboratory Bid Date: 10/02/2020
Subcontractors (60)
VMRI Building 62-AHU Modifications
CP number: CP1121905
Total Construction Budget: $201,280
includes the bid estimate and contingency for this scope of work
Overall project description of work:
VMRI Building 62-AHU Modifications
Scope number: PS01
Construction Budget: $196,200
Begin construction: 06/19/2023
Occupancy / completion: 01/03/2024
Prime contractor: ACI MECHANICAL INC
Project manager:
David Blum
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Contract description of work:
This project includes, but is not limited to, the installation of an additional air handling unit with an outdoor condenser and an exhaust fan system to serve Room 1100.
Subcontractors (3)
Welch Road-Pedestrian Bridge-Replacement
CP number: CP1230628
Total Construction Budget: $305,910
includes the bid estimate and contingency for this scope of work
Overall project description of work:
Welch Road-Pedestrian Bridge-Replacement
Construction
Scope number: PS01
Construction Budget: $305,910
Begin construction: 11/19/2024
Occupancy / completion: 07/25/2025
Prime contractor: NB KOCH GENERAL CONTRACTORS INC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: SHUCK BRITSON INC
Contract description of work:
This project includes, but is not limited to, replacing the Welch Road pedestrian bridge over College Creek.