Current Projects

Administrative Services Building-HVAC System Conversion
Construction
CP number: CP002721
Total Construction Budget: $2,049,650
includes the bid estimate and contingency for this scope of work
Bid date: 6/23/2022
Begin construction: 10/1/2022
Occupancy / completion: 05/14/2023
Gross sq.ft.: 1420
Net sq.ft.: 1420
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Mark Grief
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, the replacement of the building roof and removal of the underperforming HVAC system from the roof, replacing it with a new mechanical room building, new energy efficient air handling system, and connection to the adjacent campus chilled water system. This project includes removal of the existing HVAC system, connection to the campus chilled water loop, construction of a new two-story mechanical room on the west side of the building, installation of new air handling equipment, cooling coils and associated components, replacement of the existing ASB roof system, relocation of the existing emergency generator. All the work associated with this will require a phased approach and the new system must be operational prior to the removal of the existing HVAC systems.
Agronomy Hall-Common Area Improvements
Construction
CP number: CP941036
Total Construction Budget: $518,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/15/2022
Begin construction: 12/22/2022
Occupancy / completion: 05/31/2023
Gross sq.ft.: 8243
Net sq.ft.: 8243
Prime contractor: TRINITY CONSTRUCTION GRP LTD
Project manager:
Hayley Sandholm
Construction manager:
Steven Nelson
Design Professional: SVPA ARCHITECTS INC
Overall Project Description of Work
The project consists of, but is not limited to, remodeling three primary corridor spaces. Improvements include removing and replacing old ceiling systems with new lay-in and decorative ceilings, new lighting, new paint finishes on walls and any exposed ceiling, and new floor base. The common student hub area will be updated to receive new carpet and a coffee bar. A new rated glass door will be installed to improve visibility and to better welcome students into the space.
Agronomy Hall-Masonry Repairs-Phase 1
Construction
CP number: CP002641
Total Construction Budget: $387,600
includes the bid estimate and contingency for this scope of work
Bid date: 12/1/2022
Begin construction: 12/29/2022
Occupancy / completion: 06/30/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: BI STATE MASONRY INC
Project manager:
Angela Solberg
Construction manager:
Barton Dobson
Design Professional: I&S GROUP INC
Overall Project Description of Work
The project consists of, but is not limited to, tuckpointing of exterior masonry, re-caulking of control joints and around windows, cleaning of exterior masonry and windows, and replacement of a metal frame skylight window system.
Agronomy Hall-Room 1102-Remodel
DP Selection
CP number: CP1159336
Total Construction Budget: $64,800
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 1540
Net sq.ft.: 1540
Prime contractor: TBD
Project manager:
Josef Biechler
Construction manager:
Josef Biechler
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, remodeling the existing office space. Work to include asbestos abatement, architectural, electrical, and furniture and carpet replacement.
Agronomy Hall-Room B0534-Growth Chambers Replacement
Post Construction
CP number: CP1097593
Total Construction Budget: $122,500
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remove the existing growth chambers and install new ones. This project includes, but is not limited to, mechanical and electrical work. The project does not include procurement of the new growth chambers, which are being purchased separately by the college.
AM Transmitter Building-KURE Relocation
Construction
CP number: CP002715
Total Construction Budget: $40,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Christine Reinders-Caron
Construction manager:
Christine Reinders-Caron
Design Professional: ISU - FDC
Overall Project Description of Work
THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, STRUCTURAL EVALUATION OF THE EXISTING WOI-AM TOWER, MODIFICATIONS TO THE AM TRANSMITTER BUILDING, AND RELOCATION OF SOME EXISTING EQUIPMENT AND PURCHASE OF NEW EQUIPMENT REQUIRED TO RELOCATE KURE 88.5 FROM ZAFFARANO.
Applied Science Complex 1-Room 0222-Remodel
DP Selection
CP number: CP1158811
Total Construction Budget: $84,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Josef Biechler
Construction manager:
Josef Biechler
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel an existing laboratory to accommodate new faculty research. This project includes, but is not limited to architectural, mechanical, electrical and fixed equipment.
Applied Science Complex 4-Renovation
Construction
CP number: CP002734
Total Construction Budget: $292,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/19/2021
Begin construction: 10/28/2021
Occupancy / completion: 05/06/2022
Gross sq.ft.: 3969
Net sq.ft.: N/A
Prime contractor: HPC LLC
Project manager:
Elizabeth Clarke
Construction manager:
Steven Nelson
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, mechanical and electrical upgrades to an existing single story metal building. Mechanical scope includes new unitary heating and cooling equipment and ductwork, new dust collector, and updates to existing building automation system to support new equipment. Electrical scope includes new electrical transformer and panel, new lighting, and new fire alarm panel. Scope of work includes replacement of existing interior doors with rated doors and modifications to existing gypsum walls to meet fire rating requirements.
Atanasoff Hall-Hallway Improvements
Post Construction
CP number: CP921495
Total Construction Budget: $64,800
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Leigh Wiand
Construction manager:
Leigh Wiand
Design Professional: ISU - FDC
Overall Project Description of Work
This project will add additional fixed seating, work surfaces, whiteboards, and monitors for student study and collaboration to the first and second floor hallways.
Atanasoff Hall-Office Space-Improvements
Construction
CP number: CP1042019
Total Construction Budget: $72,200
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Leigh Wiand
Construction manager:
Leigh Wiand
Design Professional: ISU - FDC
Overall Project Description of Work
This project will improve seven private offices. The project includes, but is not limited to, paint, carpet with a rubber base, and furniture.
Barbara E Forker Building-Room 0196-Improvements
Construction
CP number: CP1085389
Total Construction Budget: $89,700
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Josef Biechler
Construction manager:
Josef Biechler
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remove light fixtures, switches and controls from the existing room and install new dimmable LED fixtures, LED color lights, lighting controls, and light switches.
Barton Residence Hall-Window Replacement
On Hold
CP number: CP002483
Total Construction Budget: $500,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/27/2019
Begin construction: 3/15/2019
Occupancy / completion: 02/28/2020
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
The project consists of, but is not limited to, the replacement of approximately 118 windows.
Beardshear Hall-Chilled Water Line Replacement-Phase 2
Bid
CP number: CP002646
Total Construction Budget: $240,900
includes the bid estimate and contingency for this scope of work
Bid date: 4/27/2023
Begin construction: 5/11/2023
Occupancy / completion: 02/25/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Mark Grief
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, the replacement of the main chilled water lines in the basement, installation of additional gate valves to provide for improved zoning of the chilled water service, preparation for the replacement of the risers and returns for the next phase, and relocation of existing cable trays for better access.
Beardshear Hall-Room 1350-Remodel
Design-SD
CP number: CP1095296
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Hayley Sandholm
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
This project includes, but is not limited to, remodeling the existing office suite. The existing conference room will be expanded, individual office spaces will be created, and finishes updated.
Beardshear Hall-Rooms 1550L & 2510-Remodel
Construction
CP number: CP947833
Total Construction Budget: $61,150
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing conference rooms to accommodate
virtual and hybrid meetings. This project includes, but is not limited to,
replacement of electrical power, lighting, mechanical system components,
plumbing lines and fixtures, existing furniture, and upgrade audio/visual
equipment
Bergstrom Indoor Training Facility-LED Lighting Upgrades
Post Construction
CP number: CP002599
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 10/13/2020
Begin construction: 2/28/2020
Occupancy / completion: 03/31/2020
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Jonathan Harvey
Construction manager:
John Boehmer
Design Professional:
Overall Project Description of Work
THIS PROJECT WILL CONVERT THE INDOOR LIGHTING OF BERGSTROM INDOOR PRACTICE FACILITY TO LED. PROJECT WILL REMOVE THE EXISTING LIGHTING AND REPLACE WITH NEW COLOR CHANGING LED LIGHTS. THIS WILL INCREASE THE OVERALL LIGHT LEVELS TO AN AVERAGE OF 70 FC (FOOT CANDLES).
Bessey Hall-Room 0003-Remodel
Construction
CP number: CP1007392
Total Construction Budget: $85,800
includes the bid estimate and contingency for this scope of work
Bid date: 2/10/2023
Begin construction: 3/20/2023
Occupancy / completion: 03/31/2023
Gross sq.ft.: 1183
Net sq.ft.: 1183
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing storage space for the installation of
insect rearing chambers. The project includes, but is not limited to,
architectural work, mechanical and electrical work, and the purchase of
three pervical insect rearing chambers.
Beyer Hall-Elevator 1181 Modernization
Construction
CP number: CP002513
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 2/28/2022
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Jonathan Harvey
Design Professional:
Overall Project Description of Work
PROJECT SCOPE IS AS FOLLOWS: NEW CAR AND CORRIDOR FIXTURES; NEW DOOR OPERATORS AND RELATED CAR AND CORRIDOR DOOR OPERATING EQUIPMENT; NEW CAB SHELL, PLATFORM, AND INTERIOR FINISHES; NEW STRUCTURAL COMPONENTS TO SUITE CAPACITY AND C1 LOADING; NEW CODE COMPLIANT MACHINE ROOM.
Beyer Hall-Room 2500-Remodel
Design-CD
CP number: CP942796
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 5/11/2023
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Jonathan Harvey
Construction manager:
Barton Dobson
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to removal of existing partial 5ft high raised floor, installation of a new 6ft high raised floor, creation of landing pits deep enough to help prevent injuries, and provision of stairs and a ramp to existing doors.
Beyer Hall-Rooms 1312 and 1316-Renovation
Post Construction
CP number: CP002617
Total Construction Budget: $393,600
includes the bid estimate and contingency for this scope of work
Bid date: 2/20/2020
Begin construction: 3/4/2020
Occupancy / completion: 09/10/2020
Gross sq.ft.: 1945
Net sq.ft.: 1945
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
David Blum
Construction manager:
Darrell Reeves
Design Professional:
Overall Project Description of Work
The project consists of, but is not limited to, the demolition of two existing recreational squash court interiors and renovating the existing space into a recreational electronic sports and gaming computer lab.
Beyer Hall-Swimming Pool-Repairs
Bid
CP number: CP1088360
Total Construction Budget: $177,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/11/2023
Begin construction:
Occupancy / completion: 08/20/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Mark Grief
Construction manager:
Steven Nelson
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, replacement of existing pool steam-to-water heat exchanger and associated piping and controls. Replacement of several manual isolation valves and pipe couplings.
Project must be completed by 6:00 a.m. on August 20, 2023.
BioCentury Research Farm-AHU1-Modifications
Pre-Design
CP number: CP002759
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Design Professional: RESOURCE CONSULTING ENGINEERS
Overall Project Description of Work
This project includes, but is not limited to, modifications to air handler unit 1 (AHU1) serving the main building for the BioCentury Research Farm.
Biocentury Research Farm-Vehicle Dynamometer Facility-Concrete
Post Construction
CP number: CP002214
Total Construction Budget: $240,000
includes the bid estimate and contingency for this scope of work
Bid date: 11/19/2019
Begin construction: 11/25/2019
Occupancy / completion: 02/06/2020
Gross sq.ft.: 3015
Net sq.ft.: 3015
Prime contractor: WOODRUFF CONSTRUCTION INC
Project manager:
Mark Huss
Construction manager:
Troy Chandler
Design Professional: OPN INC
Overall Project Description of Work
The project consists of, but is not limited to, materials and labor for the installation of a storm sewer system and regrading of existing gravel lots.
Biocentury Research Farm-Vehicle Dynamometer Facility-Electrical Improvements
Construction
CP number: CP002214
Total Construction Budget: $175,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/29/2020
Begin construction: 10/30/2020
Occupancy / completion: 01/28/2021
Gross sq.ft.: 9000
Net sq.ft.: 9000
Prime contractor: JASPERING ELECTRIC INC
Project manager:
Mark Huss
Construction manager:
Troy Chandler
Design Professional: RESOURCE CONSULTING ENGINEERS
Overall Project Description of Work
The project consists of, but is not limited to, materials and labor to increase the electrical service for the operation of a new vehicle dynamometer in an existing building. The project includes new 2500 amp service, switchboard, and disconnect.
Biocentury Research Farm-Vehicle Dynamometer Facility-Interior Remodeling
Post Construction
CP number: CP002214
Total Construction Budget: $270,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/28/2020
Begin construction: 6/15/2020
Occupancy / completion: 09/13/2020
Gross sq.ft.: 9000
Net sq.ft.: 9000
Prime contractor: BRENTON BUILDINGS LLC
Project manager:
Mark Huss
Construction manager:
Troy Chandler
Design Professional: ISU
Overall Project Description of Work
The project consists of, but is not limited to, providing transportation, equipment, materials, construction, and services necessary to remodel the interior of a pre-engineered steel farm building. Work will include steel wall liner, miscellaneous carpentry, mechanical, and electrical work.
Birch, Welch, and Roberts Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
Design-CD
CP number: CP1001532
Total Construction Budget: $46,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/31/2023
Begin construction: 5/22/2023
Occupancy / completion: 07/28/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
This project includes, but is not limited, to installation of new sub drain along the south exterior wall of Welch Hall and west exterior wall of Birch Hall, within the south courtyard. This new sub drain will be connected to a new area intake. There will be additional storm pipe connecting the new intake to an existing manhole. On the west side of the courtyard, the area of an existing intake will be regraded, the intake itself removed and replaced at a lower elevation to help move water away from the sidewalk. The entire site will be regraded for improved drainage.
Black Engineering-Room 2043-Remodel
Construction
CP number: CP969523
Total Construction Budget: $76,500
includes the bid estimate and contingency for this scope of work
Bid date: 4/29/2022
Begin construction: 5/2/2022
Occupancy / completion: 07/29/2022
Gross sq.ft.: 526
Net sq.ft.: 526
Prime contractor: STORY CONSTRUCTION CO SM PROJ
Project manager:
Christine Reinders-Caron
Construction manager:
Christine Reinders-Caron
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing office space into two offices. The project includes, but is not limited to, architectural, electrical, lighting, painting, mechanical work, and any necessary repairs to existing walls. Installation of new doors and frames, carpet, and vinyl floor tile. Removal of existing ductwork and install new.
Buchanan Residence Hall-Water Service Piping-Replacement
Bid
CP number: CP1094910
Total Construction Budget: $86,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/13/2023
Begin construction: 5/15/2023
Occupancy / completion: 07/21/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
David Blum
Construction manager:
Barton Dobson
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, new 8 inch Ductile Iron water pipe, remove abandoned utilities, remove and replace PCC sidewalk, and grading with topsoil.
Carver Hall-Fire System Standpipes-Improvements
Design-CD
CP number: CP917640
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 7/11/2023
Begin construction: 8/8/2023
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Hayley Sandholm
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, the installation of four Class 1 fire system standpipes to serve the building, a new fire hydrant, and a new fire department connection on the east side of the building. The northwest standpipe will have tamper switch valves for a future sprinkler system.
Carver Hall-Room 0101-Renovation
Post Construction
CP number: CP002650
Total Construction Budget: $265,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/14/2021
Begin construction: 1/6/2022
Occupancy / completion: 08/13/2022
Gross sq.ft.: 2286
Net sq.ft.: 2286
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Angela Solberg
Construction manager:
Steven Nelson
Design Professional: FREVERT-RAMSEY-KOBES ARCHITECT
Overall Project Description of Work
The project consists of, but is not limited to, removal and replacement of flooring and seating, painting, lighting, acoustical wall panel installation, handrails and minor electrical work.
College of Design-Room 0101-Renovation
Post Construction
CP number: CP002669
Total Construction Budget: $225,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/9/2021
Begin construction: 12/10/2021
Occupancy / completion: 08/15/2022
Gross sq.ft.: 2984
Net sq.ft.: 2910
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Angela Solberg
Construction manager:
Mick McBride
Design Professional: FREVERT-RAMSEY-KOBES ARCHITECT
Overall Project Description of Work
The project consists of, but is not limited to, demolition of framed walls and concrete risers; construction of new pipe enclosure walls; removal and replacement of flooring, seating, and rubber stair tread/risers; painting; drop ceiling tile replacement; and minor electrical work.
College of Design-Window Replacement
Construction
CP number: CP002720
Total Construction Budget: $2,214,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/28/2021
Begin construction: 11/1/2021
Occupancy / completion: 04/17/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: WILSON GROUP INC
Project manager:
David Blum
Construction manager:
Steven Nelson
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, cleaning the existing exterior concrete building surface, removing and replacing existing sealant joints at exterior concrete walls, removing and replacing existing ribbon window units, and replacing identified damaged interior wall assembly and finishes.
Communications Building-Room 1055-Remodel
Post Construction
CP number: CP1007874
Total Construction Budget: $77,350
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 1000
Net sq.ft.: 1000
Prime contractor: Multiple Constructors
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Overall Project Description of Work
This project will make modifications for installing a 3D concrete printer. This project includes, but is not limited to, concrete site work, architectural, and mechanical and electrical work.
Curtiss Farm-Feed Mill and Grain Science Complex
Construction
CP number: CP002509
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 12/5/2019
Begin construction: 9/28/2020
Occupancy / completion: 02/19/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TODD & SARGENT INC
Project manager:
Mark Huss
Construction manager:
Darrell Reeves
Design Professional: OPUS HOLDING LLC
Overall Project Description of Work
CONSTRUCTION OF A FEED MILL AND EDUCATION BUILDING FOR THE PRODUCTION OF MULTI-SPECIES ANIMAL FEED TO SUPPORT AND ENHANCE TEACHING, EXTENSION, AND RESEARCH GRAIN SCIENCE ACTIVITIES FOR THE UNIVERSITY. THESE FACILITIES WILL BE REPRESENTATIVE OF A COMMERCIAL FEED MILL OPERATION, WITH ADDITIONAL DESIGN DETAILS RELATED TO THE EDUCATION, RESEARCH AND OUTREACH NEEDS OF THE UNIVERSITY RELATED TO THE FEED INDUSTRY. THESE FACILITIES WILL BE USED TO PRODUCE FEED FOR THE UNIVERSITYS ANIMAL FACILITIES, AS WELL AS BE USED FOR TEACHING ACTIVITIES AND WILL DEMONSTRATE FEED MILL AND GRAIN STORAGE OPERATIONS. RESEARCH ACTIVITIES RELATED TO THE INDUSTRY WILL ALSO TAKE PLACE IN THIS COMPLEX.
Curtiss Farm-Feed Mill and Grain Science Complex-Sanitary Sewer Extension
Construction
CP number: CP002509
Total Construction Budget: $730,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/9/2023
Begin construction: 3/10/2023
Occupancy / completion: 07/08/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: J&K CONTRACTING LLC
Project manager:
Mark Huss
Construction manager:
Darrell Reeves
Design Professional: CIVIL DESIGN ADVANTAGE
Overall Project Description of Work
The project consists of, but is not limited to, the installation of approximately 2500 feet of sanitary sewer line along State Ave. Work includes a combination of trenchless and trenched installation. Work also includes supplying and installing several manholes.
Curtiss Hall-Exterior Masonry Repair
Construction
CP number: CP002623
Total Construction Budget: $345,000
includes the bid estimate and contingency for this scope of work
Bid date: 8/30/2022
Begin construction: 9/15/2022
Occupancy / completion: 07/14/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: AJWD
Project manager:
Angela Solberg
Construction manager:
Steven Nelson
Design Professional: SCHEMMER ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, stone repair, stone mortar repointing, joint sealant replacement and masonry cleaning.
Curtiss Hall-Room 0209C-Remodel
Construction
CP number: CP930220
Total Construction Budget: $221,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/10/2022
Begin construction: 5/19/2022
Occupancy / completion: 11/13/2022
Gross sq.ft.: 670
Net sq.ft.: 670
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
Mick McBride
Design Professional: CANNON MOSS BRYGGER & ASSOC
Overall Project Description of Work
This project includes, but is not limited to, demolition of existing walls, finishes, furniture, and MEP equipment; installation of new walls, doors, frames, ceilings, and finishes for two to three offices; new MEP equipment and lighting to serve new office spaces; and installation of new furnishings.
Cyclone Sports Complex-Soccer Field-Replacement
Construction
CP number: CP905958
Total Construction Budget: $660,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/15/2022
Begin construction: 12/20/2022
Occupancy / completion: 07/14/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: IOWA SPORTS TURF
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, demolition and disposal of the existing synthetic turf field, rock subbase and drainage system. Proposed improvements also include grading, import of proposed pea gravel, sand, subdrain system, irrigation system, PCC curb, installation of sod that is provided by owner, and miscellaneous associated work necessary to complete the project.
Cyclone Sports Complex-Soccer Field-Replacement-Practice Field Drainage Improvements
Post Construction
CP number: CP905958
Total Construction Budget: $60,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/9/2022
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
This project will install 6 inch perforated subdrain and a sand slit drainage system to improve
drainage on the practice soccer field at the Cyclones Sports Complex on Iowa State University Campus.
CYTown-Parking and Infrastructure Improvements
Construction
CP number: CP1004288
Total Construction Budget: $17,785,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/24/2023
Begin construction: 2/9/2023
Occupancy / completion: 08/16/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: ELDER CORP
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, demolition of existing parking lots A3, A4, B5, B6, C5, C6, D1, D2, D3 and D4 and adjacent drives, soil import, grading, installation of underground utilities (including sanitary sewer, storm sewer, water main, electric and communications), subgrade preparation, PCC paving, HMA paving, parking lot lighting and surface restoration.
Dairy Farm-Cow Bedding System Conversion
Post Construction
CP number: CP917722
Total Construction Budget: $125,000
includes the bid estimate and contingency for this scope of work
Bid date: 8/23/2022
Begin construction: 8/26/2022
Occupancy / completion: 12/19/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: WOODRUFF CONSTRUCTION INC
Project manager:
Mark Huss
Construction manager:
Mick McBride
Design Professional: CURRY WILLE & ASSOC
Overall Project Description of Work
The project consists of, but is not limited to, the materials and labor to remove the concrete in the lactating cow free stall pens and replacing with new concrete designed for the use of sand bedding.
Department of Residence-Elevator Safety Improvements FY18
Construction
CP number: CP002469
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 08/31/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional:
Overall Project Description of Work
THIS PROJECT CONSISTS OF REPLACING AND ADDING SAFETY EQUIPMENT TO TWO ELEVATORS LOCATED IN MAPLE RESIDENCE HALL AND ONE IN MAPLE-WILLOW-LARCH COMMONS. THE AREAS OF WORK WILL INCLUDE FIRE RECALL, REPLACEMENT OF OBSOLETE PARTS, AND UPGRADES OF EQUIPMENT.
Durham Center-Clean Agent Fire Suppression System-Improvements
Construction
CP number: CP907055
Total Construction Budget: $700,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/27/2022
Begin construction: 1/31/2022
Occupancy / completion: 01/12/2023
Gross sq.ft.: 7646
Net sq.ft.: 7646
Prime contractor: WOODRUFF CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
Barton Dobson
Design Professional: RESOURCE CONSULTING ENGINEERS
Overall Project Description of Work
The project consists of, but is not limited to, installation of new clean agent fire suppression system to serve data center space. Project also includes limited modifications to double-interlock pre-action system serving space, installation of combination fire/smoke dampers in ductwork serving space, limited architectural modifications, etc. All work associated with fire alarm systems shall be included as part of Bid Alternate #2 or Bid Alternate #3. Refer to Bid Alternate descriptions and documents for additional information.
East of University Boulevard Site Improvements-Recreation Services
Post Construction
CP number: CP002439
Total Construction Budget: $5,852,300
includes the bid estimate and contingency for this scope of work
Bid date: 3/21/2019
Begin construction: 4/11/2019
Occupancy / completion: 08/21/2020
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: HPC LLC
Project manager:
Wesley Gee
Construction manager:
Troy Chandler
Design Professional: HASTINGS & CHIVETTA ARCHITECTS
Overall Project Description of Work
THIS PROJECT WILL RENOVATE THE EXISTING SOUTHEAST RECREATION COMPLEX LOCATED EAST OF UNIVERSITY BOULEVARD BETWEEN SOUTH 4TH AND SOUTH 16TH STREETS. THIS RENOVATION OF THE EXISTING COMPLEX WILL ILLUMINATE THE PLAYING FIELDS TO LIGHTING LEVELS RECOMMENDED FOR SPORT CLUBS AND AMATEUR FACILITIES, PROVIDE IRRIGATION, IMPROVE FIELD DRAINAGE, PLAYING SURFACE DURABILITY, AND MAINTAINABILITY.
East of University Boulevard Site Improvements-Recreation Services-Field Lighting
Post Construction
CP number: CP002439
Total Construction Budget: $1,569,604
includes the bid estimate and contingency for this scope of work
Bid date: 4/2/2019
Begin construction: 4/15/2019
Occupancy / completion: 08/21/2020
Gross sq.ft.: 3989
Net sq.ft.: 3026
Prime contractor: ARDENT LIGHTING GROUP LLC
Project manager:
Wesley Gee
Construction manager:
Troy Chandler
Design Professional: HASTINGS & CHIVETTA ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, athletic field lighting and installation, including lighting controls, poles and lighting fixtures.
EHSSB-Interior Improvements
Construction
CP number: CP1088271
Total Construction Budget: $275,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/9/2023
Begin construction: 3/22/2023
Occupancy / completion: 10/01/2023
Gross sq.ft.: 9920
Net sq.ft.: 9920
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, architectural, electrical, and interior design work required to replace the existing raised floor system. The existing system furniture will be removed, prior to the new raised floor installation, and reinstalled at completion. New carpet tiles and floor base will also be installed.
Enrollment Services Center-Emergency Elevator Modernization
Construction
CP number: CP1042797
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, replacement of elevator controls, hydraulic equipment, signals, door equipment and associated components. This is a modular modernization solution for elevator control and electrical systems based on the latest in control technology and will replace outdated technology and improve the levels of performance, reliability and safety, and energy efficiency of the elevator.
Enrollment Services Center-Fire Sprinkler Leak Repairs
Post Construction
CP number: CP946728
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will provide clean-up, drying, demolition of damaged
materials and extensive repairs to the existing building. This
project includes, but is not limited to, cleaning and dehumidifying
the building, removal of damaged materials, and architectural,
electrical, mechanical, and elevator repairs. Additional minor
alternations will be accomplished concurrently, taking advantage
of the opportunity to work in the now vacant spaces.
Equine Learning Center-Hay Storage Shed-Replacement
Post Construction
CP number: CP988205
Total Construction Budget: $56,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/29/2022
Begin construction: 5/12/2022
Occupancy / completion: 07/22/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: CLEARY BUILDING CORP
Project manager:
Christine Reinders-Caron
Construction manager:
Christine Reinders-Caron
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, demolition and replacement of the existing hay storage shed.
Farm House Lane-Reconstruction
Construction
CP number: CP002663
Total Construction Budget: $440,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/3/2022
Begin construction: 2/7/2022
Occupancy / completion: 08/22/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: CALIBER CONCRETE LLC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, reconstruction and widening of Farm House Lane from Parking Lot 49 to Troxel Hall, storm sewer, lighting, bike parking and concrete sidewalks.
Firemanship Training-ISD Finance Office-Remodel
Post Construction
CP number: CP002732
Total Construction Budget: $350,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/25/2021
Begin construction: 5/26/2021
Occupancy / completion: 10/23/2021
Gross sq.ft.: 3592
Net sq.ft.: 3592
Prime contractor: HPC LLC
Project manager:
Elizabeth Clarke
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, interior finish updates, layout alterations, updating the building entry and restroom for ADA compliance, new roof, new LED lighting fixtures and controls, new power receptacles and data jacks, and mechanical infrastructure updates as needed to support the remodel.
Forestry Greenhouse-Demolition
Construction
CP number: CP1001237
Total Construction Budget: $356,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/20/2022
Begin construction: 12/21/2022
Occupancy / completion: 05/25/2023
Gross sq.ft.: 12461
Net sq.ft.: 12461
Prime contractor: LINNCO INC
Project manager:
Jennifer Evans
Construction manager:
Barton Dobson
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, demolition of the remaining Greenhouse structure and selected site facilities. Final site to be restored including grading and seeding. The abatement of all asbestos containing pipe-fitting insulation, glazing/glazing compound, transite wall paneling, and all associated sealants will be complete prior to building demolition.
Frederiksen Court-Building 31-Fire Alarm System Upgrade
Construction
CP number: CP986875
Total Construction Budget: $280,500
includes the bid estimate and contingency for this scope of work
Bid date: 2/16/2023
Begin construction: 3/10/2023
Occupancy / completion: 07/28/2023
Gross sq.ft.: 19662
Net sq.ft.: 19662
Prime contractor: COMMONWEALTH ELECTRIC
Project manager:
Mark Grief
Construction manager:
Danelda Allen
Design Professional: JOHNSON CONTROLS FIRE PROTECT
Overall Project Description of Work
The project consists of, but is not limited to, fire alarm system upgrade including replacement of panel and all wiring according to Department of Residence standards and replacement of the apartment devices with addressable devices.
Frederiksen Court-Buildings 31, 32, 33, & 34-Life Cycle Improvements
Construction
CP number: CP930492
Total Construction Budget: $1,110,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/6/2022
Begin construction: 1/31/2022
Occupancy / completion: 07/15/2022
Gross sq.ft.: 30027
Net sq.ft.: 30027
Prime contractor: Multiple Constructors
Project manager:
Hayley Sandholm
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, replacement of the broadloom carpet and VCT in the apartment bedrooms, living rooms, and kitchens with wood-look vinyl plank; replacement of the VCT and/or sheet vinyl in the bathrooms with sheet vinyl; replacement of the broadloom carpet and VCT in the corridors with carpet tile and rubber tile; replacement of the stairway broadloom carpet with rubber tile and treads; patch and paint the apartments, corridors, and stairways; and moving of furniture and fixtures.
Friley Residence Hall-Bathroom Improvements-Locations 7 & 8
Bid
CP number: CP002724
Total Construction Budget: $738,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/25/2023
Begin construction: 8/28/2023
Occupancy / completion: 12/21/2023
Gross sq.ft.: 1385
Net sq.ft.: 1300
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Locations 7 and 8. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack A
Design-CD
CP number: CP002724
Total Construction Budget: $3,450,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/18/2025
Begin construction: 5/18/2026
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack A. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack B
Design-CD
CP number: CP002724
Total Construction Budget: $3,900,000
includes the bid estimate and contingency for this scope of work
Bid date: 7/9/2026
Begin construction: 12/18/2026
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack B. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack C
Design-CD
CP number: CP002724
Total Construction Budget: $4,650,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/12/2024
Begin construction: 5/19/2025
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack C. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack D
Design-CD
CP number: CP002724
Total Construction Budget: $3,800,000
includes the bid estimate and contingency for this scope of work
Bid date: 7/31/2025
Begin construction: 12/22/2025
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack D. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack E
Design-CD
CP number: CP002724
Total Construction Budget: $3,400,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/6/2024
Begin construction: 1/6/2025
Occupancy / completion: 07/31/2024
Gross sq.ft.: 11500
Net sq.ft.: 5000
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack E. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack F
Design-CD
CP number: CP002724
Total Construction Budget: $3,375,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/5/2023
Begin construction: 5/13/2024
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack F. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack G
Construction
CP number: CP002724
Total Construction Budget: $1,950,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/18/2022
Begin construction: 11/21/2022
Occupancy / completion: 08/04/2023
Gross sq.ft.: 11500
Net sq.ft.: 5000
Prime contractor: EMPIRE CONSTRUCTION COMPANY
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack G. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Bathroom Improvements-Stack H
Design-CD
CP number: CP002724
Total Construction Budget: $4,025,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/17/2026
Begin construction: 5/17/2027
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Kasi Province
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of bathrooms in Stack H. The bathrooms will be converted from mass, shared bathrooms to private, accessible units. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Friley Residence Hall-Roof Replacement
Construction
CP number: CP002538
Total Construction Budget: $3,580,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/4/2021
Begin construction: 3/11/2021
Occupancy / completion: 08/15/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: BLACK HAWK ROOF CO INC
Project manager:
David Blum
Construction manager:
Danelda Allen
Design Professional: SCHEMMER ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, roof shingle replacement, membrane roof replacement, flat seam metal roof, and new dormer windows. See drawings for slate shingle and window abatement removals by others.
Friley Residence Hall-Roof Replacement-Dock Roof
Construction
CP number: CP002538
Total Construction Budget: $304,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/8/2022
Begin construction: 12/20/2022
Occupancy / completion: 07/28/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: BLACK HAWK ROOF CO INC
Project manager:
David Blum
Construction manager:
Danelda Allen
Design Professional: SCHEMMER ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, metal coping, roof hatch, roof membrane, and roof insulation replacement at the Friley Hall dock roof.
General Services Building-Room 0192-Remodel
Post Construction
CP number: CP996546
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 1806
Net sq.ft.: 1806
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing Central Stores sales counter area, remove the air handling unit, and install one new air handling unit. The project includes, but is not limited to, abatement, architectural, electrical, and mechanical work.
General Services Building-Sprinkler System Installation
Design-CD
CP number: CP002630
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 9/28/2023
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Kelly Kalvelage
Construction manager:
Danelda Allen
Design Professional: RESOURCE CONSULTING ENGINEERS
Overall Project Description of Work
The project consists of, but is not limited to, modifications to the water service entrance, new main sprinkler piping and valves, and updating the fire detection and alarm system.
Gilman Hall-Accessible Restroom Improvements
Construction
CP number: CP002672
Total Construction Budget: $225,730
includes the bid estimate and contingency for this scope of work
Bid date: 7/14/2022
Begin construction: 8/10/2022
Occupancy / completion: 03/18/2023
Gross sq.ft.: 495
Net sq.ft.: 495
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
Mick McBride
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, the renovation of existing space on level 1 in Gilman Hall into a new mens restroom including plumbing improvements, electrical improvements and the installation of new lighting.
Gilman Hall-Rooms 3605 and 3611-Remodel
Post Construction
CP number: CP946487
Total Construction Budget: $96,300
includes the bid estimate and contingency for this scope of work
Bid date: 2/25/2022
Begin construction: 2/28/2022
Occupancy / completion:
Gross sq.ft.: 1305
Net sq.ft.: 1305
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will renovate rooms 3605 & 3611 at Gilman Hall. The scope of work will include but not be limited to: general construction, architectural, electrical, plumbing, and HVAC. Refer to Drawings for complete scope of Work. Refer to the Drawings for complete scope of Work.
Gilman Hall-Wayfinding and Signage-Improvements
On Hold
CP number: CP1010532
Total Construction Budget: $208,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to evaluation of existing building signage to determine exact quantity, correct numbering and notable space labeling for installation of new room signage. At applicable locations, existing room signage will be removed and wall surfaces will be patched and repaired ready for installation of new, accessible room signage.
Heady Hall-Rooms 0178, 0180, 0180A, and 0180B-Remodel
Construction
CP number: CP1004872
Total Construction Budget: $62,400
includes the bid estimate and contingency for this scope of work
Bid date: 7/6/2022
Begin construction:
Occupancy / completion: 09/30/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing spaces to create a graduate student lounge. The project includes, but is not limited to, architectural, mechanical, and electrical work, a new audio-visual system, and carpet and furniture installation.
Helser Residence Hall-Exterior Grading, Waterproofing, and Sidewalk Repair
Bid
CP number: CP1001574
Total Construction Budget: $75,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/31/2023
Begin construction: 5/22/2023
Occupancy / completion: 07/28/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
This project includes, but is not limited to, installation of additional area drains and new storm pipe to help divert water away from the north west entrance door of Helser Hall and lower level window wells along the north side of the building. A portion of an existing sidewalk will be removed and replaced to meet ADA slope requirements and to prevent water from ponding. Rock bed will be used for erosion protection and to keep water from collecting against face of the building. The area of Work will be regraded for overall improved
Helser Residence Hall-Laundry Improvements
Construction
CP number: CP1001298
Total Construction Budget: $360,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/4/2022
Begin construction: 10/5/2022
Occupancy / completion: 05/25/2023
Gross sq.ft.: 550
Net sq.ft.: 550
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Angela Solberg
Construction manager:
Mick McBride
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, remodel of an existing first floor bathroom into new resident laundry area. The work includes mechanical, electrical, and plumbing system modifications, interior finish updates, and layout changes.
Hilton Coliseum-Rooms 0176, 0176A, 0188, and 0188A-Renovation
Bid
CP number: CP964884
Total Construction Budget: $667,800
includes the bid estimate and contingency for this scope of work
Bid date: 4/27/2023
Begin construction:
Occupancy / completion: 10/06/2023
Gross sq.ft.: 3280
Net sq.ft.: 2740
Prime contractor: TBD
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
The project consists of, but is not limited to, demolition of existing finishes and walls; installation of new stud walls, flooring, finishes, and ceilings; new lighting; and modifications to existing mechanical system.
Horticulture Research Station-AVES Building
Construction
CP number: CP002762
Total Construction Budget: $230,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/21/2022
Begin construction: 6/22/2022
Occupancy / completion: 09/20/2022
Gross sq.ft.: 2240
Net sq.ft.: 2240
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Huss
Construction manager:
Mick McBride
Design Professional: CURRY WILLE & ASSOC
Overall Project Description of Work
The project consists of, but is not limited to, the materials and labor to construct a wood frame building with metal siding and roofing. The building will be approximately 2240 square feet. The project will include site work and footings excavation. The building will have concrete foundations, a partial concrete floor, metal exterior doors and frames, and eight interior metal doors and frames.
Horticulture Research Station-Machine Storage Building
Design-DD
CP number: CP1053242
Total Construction Budget: $143,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Mark Huss
Construction manager:
Mick McBride
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, the design and construction of a 6000 square feet post frame storage building. The building will be uninsulated and not heated. The building will have a concrete floor, a metal roof, and metal siding.
Howe Hall-Room 2304-Remodel
Construction
CP number: CP1007423
Total Construction Budget: $80,900
includes the bid estimate and contingency for this scope of work
Bid date: 7/13/2022
Begin construction:
Occupancy / completion: 09/16/2022
Gross sq.ft.: 764
Net sq.ft.: 764
Prime contractor: TBD
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing computer lab with 25 workstations. The project includes, but is not limited to, architectural, mechanical and electrical work, and the addition of new furniture.
Howe Hall-Room 2344-Remodel
Construction
CP number: CP1007447
Total Construction Budget: $109,800
includes the bid estimate and contingency for this scope of work
Bid date: 7/13/2022
Begin construction:
Occupancy / completion: 09/16/2022
Gross sq.ft.: 1390
Net sq.ft.: 1390
Prime contractor: TBD
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing computer lab with 34 workstations. The project includes, but is not limited to, architectural, mechanical and electrical work, and the addition of new furniture.
Howe Hall-Room 2622-Remodel
Pre-Design
CP number: CP1146403
Total Construction Budget: $107,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 1670
Net sq.ft.: 1670
Prime contractor: TBD
Project manager:
Leigh Wiand
Construction manager:
Leigh Wiand
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, the remodeling of the existing office space to collocate staff of the Center for Excellence in Learning and Teaching in Howe Hall. Work will include architectural, mechanical, and electrical work, and fixed equipment and furniture.
Howe Hall-Room 2624-Remodel
Post Construction
CP number: CP1091732
Total Construction Budget: $90,000
includes the bid estimate and contingency for this scope of work
Bid date: 11/18/2022
Begin construction:
Occupancy / completion: 01/17/2023
Gross sq.ft.: 5328
Net sq.ft.: 5328
Prime contractor: TBD
Project manager:
Christine Reinders-Caron
Construction manager:
Christine Reinders-Caron
Design Professional: ISU - FDC
Overall Project Description of Work
The project includes, but is not limited to the remodel of the existing office space including architectural, mechanical, electrical and furniture installation.
Information Technology Services-Central Campus-Fiber and Wireless Expansion
Pre-Design
CP number: CP1118671
Total Construction Budget: $133,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Caleb Barduson
Construction manager:
Caleb Barduson
Design Professional: ISU - Utilities
Overall Project Description of Work
This project includes, but is not limited to, the installation of conduit, vaults, and ground boxes for future fiber and wireless internet expansion of central campus.
Institutional Roads 2022-Pavement Preservation-Union Drive
Post Construction
CP number: CP913244
Total Construction Budget: $395,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/16/2021
Begin construction: 12/17/2021
Occupancy / completion: 08/10/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: CON STRUCT INC
Project manager:
Angela Solberg
Construction manager:
Danelda Allen
Design Professional: SHIVE HATTERY INC
Overall Project Description of Work
The project consists of, but is not limited to, removal and replacement of concrete pavement, concrete sidewalks, reconstruction of storm sewer structure, new and relocated roadway and sidewalk lighting, pavement markings and finish grading.
Iowa School for the Deaf-Long Hall High School-Upgrades
Post Construction
CP number: CP002648
Total Construction Budget: $3,707,720
includes the bid estimate and contingency for this scope of work
Bid date: 6/17/2021
Begin construction: 6/23/2021
Occupancy / completion: 07/29/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: DOWNS ELECTRIC INC
Project manager:
Jonathan Harvey
Construction manager:
Barton Dobson
Design Professional: HDR ARCHITECTURE INC
Overall Project Description of Work
The project consists of, but is not limited to, removal and replacement of existing exterior windows; miscellaneous exterior masonry repair; mechanical, electrical, and life safety upgrades; and new floor and ceiling finishes.
Iowa School for the Deaf-Pool Dehumidification System-Replacement
Post Construction
CP number: CP002723
Total Construction Budget: $390,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/2/2021
Begin construction: 3/18/2021
Occupancy / completion: 09/24/2021
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: GRUNWALD MECHANICAL CONTRACTOR
Project manager:
Jonathan Harvey
Construction manager:
Barton Dobson
Design Professional: HDR ARCHITECTURE INC
Overall Project Description of Work
The project consists of, but is not limited to, removal and replacement of the existing pool dehumidification system. Contractor is responsible for any required new steel and electrical work.
ISU Family Resource Center-Playground Landscape Improvements
Construction
CP number: CP1042380
Total Construction Budget: $120,100
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will provide several safety improvements to the playground. The project includes, but is not limited to, concrete repairs, repair and sealing of the splintering wood fence panels and wood beams throughout the playground, fine grade and sod lawn areas, and adding wood safety mulch to the playground areas.
Jack Trice Stadium-East Gateway Bridge
Construction
CP number: CP002683
Total Construction Budget: $7,886,635
includes the bid estimate and contingency for this scope of work
Bid date: 5/27/2021
Begin construction: 6/4/2021
Occupancy / completion: 09/01/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Jonathan Harvey
Construction manager:
Darrell Reeves
Design Professional: SUBSTANCE ARCHITECTURE
Overall Project Description of Work
The project consists of, but is not limited to, the construction of an elevated gateway bridge over South University Boulevard to connect the east concourse of Jack Trice Stadium and game day parking east of South University Boulevard. A sidewalk will be added along the east side of the existing stadium ring road. The existing Reiman Gardens fencing on the north will be continued along the west side of University Boulevard.
Jack Trice Stadium-Electrical Panel Installation
Post Construction
CP number: CP987748
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will install new panels at the 50-yard line on both sides of the field at Jack Trice Stadium. The project includes, but is not limited to, electrical work to install electrical panels for new heated and cooling benches.
Jack Trice Stadium-Field Renovation
Post Construction
CP number: CP002638
Total Construction Budget: $154,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/12/2020
Begin construction: 3/13/2020
Occupancy / completion: 03/10/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: IOWA SPORTS TURF
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, removal and off-site hauling of existing root zone materials, finish grading, sod installation and irrigation system adjustments. Contractor shall provide all incidental materials and equipment to install to specifications the system shown in the construction documents.
Jack Trice Stadium-Press Box-Roof Replacement
Post Construction
CP number: CP002611
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Jonathan Harvey
Construction manager:
Jonathan Harvey
Design Professional:
Overall Project Description of Work
REPLACE ROOF ON THE EXISTING PRESS BOX TOWER AT JACK TRICE STADIUM.
Jacobson Athletic Building-Room 2035-Remodel
Post Construction
CP number: CP942806
Total Construction Budget: $115,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/12/2022
Begin construction: 5/19/2022
Occupancy / completion: 09/11/2022
Gross sq.ft.: 1470
Net sq.ft.: 1470
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Jonathan Harvey
Construction manager:
Danelda Allen
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, demolition of existing flooring, stairs, walls, and doors. Construction of new glass partition walls, raised floor platform, new doors, electrical and mechanical modifications to existing, and new lighting.
Johnny Majors Practice Field-Expansion
Post Construction
CP number: CP002556
Total Construction Budget: $170,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/6/2019
Begin construction: 6/17/2019
Occupancy / completion: 05/02/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: IOWA SPORTS TURF
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, the expansion of Johnny Majors Practice Field 35 feet to the east. This requires stripping the top organics from the existing field, removing the existing top 3 inches of sand and relocating to the east to create a new 10 inch sand profile. Scope also includes demolition of the existing east chain-link fence and installing new fence; grading from the new field edge to the new parkway; modifications to the existing irrigation system; and installation of subdrain.
Johnny Majors Practice Field-Turf Improvements
Post Construction
CP number: CP940361
Total Construction Budget: $350,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/22/2022
Begin construction: 3/28/2022
Occupancy / completion: 05/15/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: IOWA SPORTS TURF
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
This project will prepare the northern portion of Johnny Majors Practice Field for a synthetic turf surface to be installed by others. The project consists of, but is not limited to, subdrain, granular subbase, nailer board, laser grading, electrical improvements and associated site upgrades adjacent to the practice field.
Kildee Hall-AHU2 and UVU4-Replacement
Design-CD
CP number: CP002632
Total Construction Budget: $627,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/11/2023
Begin construction: 7/31/2023
Occupancy / completion: 03/15/2025
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Mark Grief
Construction manager:
John Boehmer
Design Professional: RESOURCE CONSULTING ENGINEERS
Overall Project Description of Work
This project will replace Air Handling Unit (AHU) 2 and Unit Ventilator Unit (UVU) 4 with a new semi-custom designed unit to serve the west laboratory spaces in the building. Additionally, mechanical room M0026 will be prepared for future AHU replacements and to improve maintenance access. The project includes, but is not limited to, replacement of AHU2 and UVU4 with a new AHU, ductwork and pipe reconfiguration, motor control center and control panel relocation and upgrade, and improved access.
Kildee Hall-Roof Replacement-Sections A and B
Construction
CP number: CP002758
Total Construction Budget: $470,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/26/2022
Begin construction: 5/23/2022
Occupancy / completion: 07/28/2023
Gross sq.ft.: 20000
Net sq.ft.: 20000
Prime contractor: CENTRAL STATES ROOFING INC
Project manager:
Hayley Sandholm
Construction manager:
John Boehmer
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, replacing the roof system with a more substantial replacement, increasing insulation to current energy codes, and adding the appropriate roof safety systems and equipment.
Lagomarcino Hall-Roof Replacement-Sections C, G, and H
Post Construction
CP number: CP002760
Total Construction Budget: $500,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/7/2022
Begin construction: 6/8/2022
Occupancy / completion: 07/28/2023
Gross sq.ft.: 22000
Net sq.ft.: 22000
Prime contractor: CENTRAL STATES ROOFING INC
Project manager:
Jonathan Harvey
Construction manager:
Kasi Province
Design Professional: ISU - FDC
Overall Project Description of Work
This project will replace roof sections C, G, and H at Lagomarcino Hall. The project includes, but is not limited to, replacement with a new roof designed that has a minimum useful life expectancy of 30 years. Roof insulation will be increased to current energy codes, and the appropriate roof safety systems and equipment will be installed to current University standards. All masonry walls and features above this roofline that tie directly into this system will be repaired, tuck-pointed, or caulked to prevent water infiltration through these critical interfaces.
LIDIF-Boiler System-Replacement
Post Construction
CP number: CP1000416
Total Construction Budget: $175,000
includes the bid estimate and contingency for this scope of work
Bid date: 8/30/2022
Begin construction: 9/6/2022
Occupancy / completion: 12/09/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: MANNING SEIVERT MECHANICAL CONTRACTORS INC
Project manager:
Mark Grief
Construction manager:
Kasi Province
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, the replacement of the existing boiler system in the Livestock Infectious Disease Isolation Facility. Work includes replacement of the three existing 1997 boilers, piping installation, combustion air supply, electrical power connections, control wiring connections, and necessary inspections. Boilers are OFCI.
Lied Athletic Center-Room 0152-Remodel
Post Construction
CP number: CP1006636
Total Construction Budget: $45,700
includes the bid estimate and contingency for this scope of work
Bid date: 5/19/2022
Begin construction:
Occupancy / completion: 08/15/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing space by adding a single-user restroom at the entry of Room 0152 with a new door into Room C0130. This project includes, but is not limited to, architectural, mechanical and electrical work, plumbing repairs, and patching of existing concrete floors.
Linden Residence Hall & Wallace Wilson Commons-Elevator Safety Improvements
Construction
CP number: CP002373
Total Construction Budget: $235,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 08/31/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional: ISU - Department of Residence
Overall Project Description of Work
This project consists of replacing and adding safety equipment to two (2) freight elevators located in the Linden Residence Hall and the Wallace Wilson commons. Several deficiencies will be corrected including, fire recall, replace obsolete parts, and upgrade of equipment that has exceeded life expectancy.
Lloyd Veterinary Medical Center-Recovery Stall Padding-Replacement
Post Construction
CP number: CP913667
Total Construction Budget: $200,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
he Equine Surgery Induction/Recovery Stalls 1443, 1445, 1449, and 1451 require replacement of seamless, permanently installed wall and floor padding systems.
Lloyd Veterinary Medical Center-Room 1310 and Hallways-Repairs
Construction
CP number: CP999511
Total Construction Budget: $133,400
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 4225
Net sq.ft.: 4225
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, repair of water damage, replacement of the existing flooring, and adding plastic wall panels in the 1300 suite of rooms (1310 and hallways 1330, 1340, 1350, 1360)
Memorial Union-Bookstore-Lighting Replacement
Design-SD
CP number: CP1118655
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Hayley Sandholm
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
This project includes, but is not limited to replacing the lighting throughout the University Bookstore. New fixtures, LED bulbs, and additional lighting solutions are needed throughout the space.
Memorial Union-Dining Services-Poco Picante-Remodel
Post Construction
CP number: CP002657
Total Construction Budget: $157,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/9/2021
Begin construction: 2/10/2021
Occupancy / completion: 09/22/2021
Gross sq.ft.: 250
Net sq.ft.: 250
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
David Blum
Construction manager:
Darrell Reeves
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, renovation of 250 square foot food service venue located on the first floor of the Memorial Union. Scope includes installation of new counters & food service equipment, and lighting fixtures. Demolition and installation of modified plumbing and electrical to support the renovated space.
Memorial Union-Floors 4-6-Renovation
Post Construction
CP number: CP002541
Total Construction Budget: $4,875,000
includes the bid estimate and contingency for this scope of work
Bid date: 11/12/2020
Begin construction: 11/13/2020
Occupancy / completion: 04/05/2022
Gross sq.ft.: 23400
Net sq.ft.: 23400
Prime contractor: HPC LLC
Project manager:
Kelly Kalvelage
Construction manager:
Barton Dobson
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
The project consists of, but is not limited to, the renovation of approximately 23,400 square feet on the upper three floors in the Memorial Union. Work includes demolition of existing walls, floors and ceilings, removal of mechanical, electrical and fire protection systems. New work includes gypsum board partitions, finishes, and painting and associated mechanical, electrical, plumbing and telecommunications modifications.
Memorial Union-Fountain of the Four Seasons-Renovation
Bid
CP number: CP1017470
Total Construction Budget: $938,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/20/2023
Begin construction: 5/4/2023
Occupancy / completion: 10/27/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
David Blum
Construction manager:
Barton Dobson
Design Professional: WISS JANNEY ELSTNER ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, the renovation of the Memorial Union Fountain of the Four Seasons. Salvage and reinstallation of paving system and limestone units, select limestone unit replacements, select plumbing salvage, demolition and reconstruction of concrete structures, mechanical, electrical, and waterproofing systems. Coordination with Owners representative of installation of limestone sculptures and terra cotta units by others.
Memorial Union-Graphic and Wayfinding-Improvements
Construction
CP number: CP965450
Total Construction Budget: $93,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/13/2023
Begin construction: 2/13/2023
Occupancy / completion: 04/14/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Hayley Sandholm
Construction manager:
Hayley Sandholm
Design Professional: BAILEY LAUERMAN & ASSOCIATES INC
Overall Project Description of Work
This project includes, but is not limited to, improving the signage, graphical identification, and wayfinding in the Memorial Union.
Memorial Union-Life Cycle Improvements
Construction
CP number: CP002642
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 2/28/2022
Begin construction: 7/31/2021
Occupancy / completion: 03/31/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Kelly Kalvelage
Construction manager:
Kelly Kalvelage
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, painting, carpet replacement, and refinishing wood floors.
Memorial Union-Roof Replacement
Construction
CP number: CP002749
Total Construction Budget: $600,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/5/2022
Begin construction: 7/11/2022
Occupancy / completion: 01/27/2023
Gross sq.ft.: 19500
Net sq.ft.: N/A
Prime contractor: CENTRAL STATES ROOFING INC
Project manager:
Kelly Kalvelage
Construction manager:
Mick McBride
Design Professional: I&S GROUP INC
Overall Project Description of Work
The project consists of, but is not limited to, full replacement of roof sections D, F, H, L, M, N, O, P, Q, R, S, T and U.
Memorial Union-Second Floor-Remodel
Design-CD
CP number: CP002644
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 6/30/2023
Begin construction: 7/31/2023
Occupancy / completion: 07/31/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Hayley Sandholm
Construction manager:
Kasi Province
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
This project will remodel approximately 5,000 square feet on the second floor of the Memorial Union to provide additional lounge and gathering space for students within the Memorial Union. The project will provide students with an enlarged and more attractive space to meet friends and dine on existing food service offerings. The work will better connect the main building corridor to the Colonel Pride Lounge and expand the lounge area into space formerly occupied by the Lectures Program, Post Office Branch, and hotel desk. The project will also create two tenant spaces for vendors to provide services to students.
Memorial Union-Soults Family Visitor Center-Remodel
Post Construction
CP number: CP002747
Total Construction Budget: $850,000
includes the bid estimate and contingency for this scope of work
Bid date: 11/18/2021
Begin construction: 12/3/2021
Occupancy / completion: 06/15/2022
Gross sq.ft.: 3000
Net sq.ft.: 2700
Prime contractor: BREIHOLZ CONSTRUCTION COMPANY
Project manager:
Kelly Kalvelage
Construction manager:
Danelda Allen
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
This project will expand and remodel the existing Soults Family Visitor Center to improve the campus visitor experience. The project consists of, but is not limited to, expanded office spaces; updated finishes; new technology, equipment, and furniture; and restroom modernization.
Memorial Union-Third Floor-Remodel
Design-CD
CP number: CP002643
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 7/13/2023
Begin construction: 8/10/2023
Occupancy / completion: 08/02/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Hayley Sandholm
Construction manager:
Kasi Province
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
This project will remodel approximately 12,500 square feet of the third floor of the Memorial Union vacated by tenants relocating to recently remodeled space on Memorial Union floors 4-6. This project will provide new office, conference and collaboration spaces for the Office of Multicultural Student Affairs and the Student Support Services Program. Both units will be relocating to the Memorial Union from undersized spaces in the Student Services Building.
Molecular Biology Building-Elevator Repairs
Pre-Design
CP number: CP1085447
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor:
Project manager:
Christine Maduro
Construction manager:
Christine Maduro
Design Professional: LERCH BATES INC.
Overall Project Description of Work
This project includes, but is not limited to, the evaluation of existing conditions of both Molecular Biology elevator systems and reporting of those conditions and recommended scope of work for repairs including budget estimates.
Molecular Biology Building-Room 0121-Remodel
Post Construction
CP number: CP941665
Total Construction Budget: $244,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/28/2022
Begin construction: 7/22/2022
Occupancy / completion: 01/04/2023
Gross sq.ft.: 1500
Net sq.ft.: 1500
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Jennifer Evans
Construction manager:
Kasi Province
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, remodeling an existing animal holding room into a laboratory. The project includes replacement of interior finishes, lighting and controls, mechanical system components, plumbing lines, fixed casework, and the addition of a fume hood.
National Pan-Hellenic Council Plaza
Post Construction
CP number: CP002731
Total Construction Budget: $227,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/15/2021
Begin construction: 4/16/2021
Occupancy / completion: 10/15/2021
Gross sq.ft.: 300
Net sq.ft.: N/A
Prime contractor: HPC LLC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: BOLTON & MENK INC
Overall Project Description of Work
The project consists of, but is not limited to, installation of poured-in-place concrete plaza and sidewalks, cast stone pillars and benches, lighting, site clearing, and grading.
Oak-Elm Residence Hall-Window Replacement
On Hold
CP number: CP002486
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Mark Huss
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
Project scope as follows: remove and replace windows, replace blinds, remove and replace associated window sealants, provide abatement and monitoring services.
Oak-Elm Residence-Life Cycle Improvements
On Hold
CP number: CP002473
Total Construction Budget: $1,055,840
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 137120
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional: ISU - Department of Residence
Overall Project Description of Work
The student rooms with hardwood will be refinished. The student rooms with VCT flooring will be replaced with LVT (wood-look vinyl tile). Student rooms, hallways and common areas will be patched and painted. Hallway and common area carpet will be replaced with carpet squares. Lighting throughout the building will be replaced with LED lighting.
Parking Lot G7-RV Parking Construction
Construction
CP number: CP002741
Total Construction Budget: $6,169,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/25/2022
Begin construction: 1/31/2022
Occupancy / completion: 09/02/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, removal of existing site features, erosion control, storm sewer and subdrain, new PCC and recycled asphalt pavement, lighting, RV power hookups, irrigation, electrical systems and equipment enclosure, finish grading/topsoil and sod.
Parking Lot G7-RV Parking Construction-Worle Creek Bridge
Post Construction
CP number: CP002741
Total Construction Budget: $375,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/25/2022
Begin construction: 2/16/2022
Occupancy / completion: 08/26/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: PETERSON CONTRACTORS INC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY
Overall Project Description of Work
The project consists of, but is not limited to, removal of existing trees, erosion control, PCC sidewalks, lighting, pre-engineered steel truss recreational trail bridge, stream channel modifications, and finish grading.
Parking Lots 2020-Pavement Preservation-Richardson Court
Post Construction
CP number: CP002604
Total Construction Budget: $2,169,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/22/2020
Begin construction: 11/4/2020
Occupancy / completion: 08/19/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: SYNERGY CONTRACTING LLC
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, removal of existing concrete and asphalt pavement, new asphalt pavement with concrete curb and gutter, concrete sidewalks, storm sewer structures and piping, water main installation, sanitary sewer installation, medium voltage electrical and power service to Linden Hall, parking lot and sidewalk lighting, subsurface detention, pavement markings and finish grading.
Parking Lots 2021-Special Maintenance
Post Construction
CP number: CP002750
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 07/31/2021
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Barton Dobson
Design Professional:
Overall Project Description of Work
THIS PROJECT WILL PROVIDE ASPHALT PATCHING, CRACK-FILLING, SEALCOATING AND PAINTING OF APPROXIMATELY 16 LOTS IDENTIFIED ON THE 5-YEAR SEAL COATING PLAN FOR WORK IN 2021. THE WORK WILL BE COMPLETED USING CONTRACTS THAT HAVE BEEN COMPETITIVELY BID THROUGH PROCUREMENT SERVICES.
Parking Lots 2022-Special Maintenance
Post Construction
CP number: CP1000670
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 07/31/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Construction manager:
Kasi Province
Design Professional:
Overall Project Description of Work
This project will provide asphalt patching, crack filling, seal coating, and painting of approximately 15 lots identified on the 5-year seal coating plan for work in 2022. The work will be completed using contracts that have been competitively bid through Procurement Services.
Parking Lots 2023-Special Maintenance
Pre-Design
CP number: CP1146234
Total Construction Budget: $331,500
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Angela Solberg
Design Professional:
Overall Project Description of Work
This project will provide asphalt patching, crack filling, seal coating, and painting of approximately 16 lots identified on the 5-year seal coating plan for work in 2023.
Parking Lots B1 and F-Resurfacing and Expansion
Construction
CP number: CP002742
Total Construction Budget: $3,308,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/1/2022
Begin construction: 2/2/2022
Occupancy / completion: 09/02/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: MANATTS INC
Project manager:
Angela Solberg
Construction manager:
Barton Dobson
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, removal of existing concrete and asphalt pavement, structural demolition, new asphalt and concrete pavement with concrete curb and gutter, concrete sidewalks, storm sewer structures, piping and subsurface detention, parking lot lighting, pavement markings, concrete retaining wall, compactor enclosure and finish grading/topsoil.
Parks Library-AHU-Replacement
Construction
CP number: CP002717
Total Construction Budget: $175,000
includes the bid estimate and contingency for this scope of work
Bid date: 8/26/2021
Begin construction: 9/2/2021
Occupancy / completion: 05/02/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: ACI MECHANICAL INC
Project manager:
Kelly Kalvelage
Construction manager:
Barton Dobson
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, replacement of Air Handling Unit # 1.
Parks Library-Room 0199-Remodel
Post Construction
CP number: CP002719
Total Construction Budget: $425,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/6/2021
Begin construction: 5/7/2021
Occupancy / completion: 10/22/2021
Gross sq.ft.: 3310
Net sq.ft.: 2985
Prime contractor: HPC LLC
Project manager:
Elizabeth Clarke
Construction manager:
John Boehmer
Design Professional: HANBURY
Overall Project Description of Work
The project consists of, but is not limited to, replacement of the ADA ramp, new wall construction for offices and meeting spaces, finish updates, new lighting, and updates to mechanical, power, and telecommunication systems to support the remodeled space.
Parks Library-Rooms 440 and 450-Remodel
Post Construction
CP number: CP930313
Total Construction Budget: $107,400
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Christine Reinders-Caron
Construction manager:
Christine Reinders-Caron
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, removal of study carrels, removal and abatement of carpet tile, seal and polish concrete floor, installation of whiteboards and lockers, and HVAC duct modifications. Cameras and access control will be installed, windows will be tinted, lights replaced, and a new door installed to secure the space.
Parks Library-Second Floor-Improvements
DP Selection
CP number: CP1146553
Total Construction Budget: $62,100
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 4524
Net sq.ft.: 4524
Prime contractor: TBD
Project manager:
Jennifer Warrick
Construction manager:
Jennifer Warrick
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, the replacement of furniture, carpet, and the addition of electrical wiring.
Parks Library-South Window System-Repairs
Post Construction
CP number: CP002582
Total Construction Budget: $1,175,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/28/2021
Begin construction: 2/3/2021
Occupancy / completion: 08/20/2021
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: WILSON GROUP INC
Project manager:
Elizabeth Clarke
Construction manager:
Nathan Graves
Design Professional: BNIM ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, replacement of curtainwall components outside of the structural back members including glazing, entrance door replacement, and interior finish repairs as a result of water intrusion damage.
Parks Library-Wayfinding Improvements
Construction
CP number: CP921835
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Jennifer Evans
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, the addition of building directories, wayfinding signage (approximately 140 locations), and amenity identification signage throughout Parks Library. Applications include a stand-alone building directory, vinyl signage applied to wall surfaces and at selected columns, vinyl signage over new frosted glass covering on specific glazed openings, projecting signage from walls, and surface-mounted acrylic lettering.
Pearson Hall-Accessibility, Wayfinding, and Signage-Improvements
Design-SD
CP number: CP1003356
Total Construction Budget: $128,800
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU
Overall Project Description of Work
This project includes, but is not limited to, a survey of existing interior room signage to determine the exact quantity, correct numbering, and notable space labeling for the installation of new room signage. Existing room signage will be removed and wall surfaces will be patched and repaired for installation of new accessible room signage.
Physics Hall-Accessibility Improvements 2022
Construction
CP number: CP1000419
Total Construction Budget: $140,000
includes the bid estimate and contingency for this scope of work
Bid date: 11/10/2022
Begin construction: 12/2/2022
Occupancy / completion: 06/30/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
Angela Solberg
Construction manager:
John Boehmer
Design Professional: HARTMAN TRAPP ARCHITECTURE STUDIO LLC
Overall Project Description of Work
The project consists of, but is not limited to, modifications to the interior and exterior accessible ramps at the lower level of Physics Hall to provide compliant access into and throughout the lower level. The project also includes replacement of various sections of guardrail, handrail, and doors along the accessible routes undergoing modifications.
Poultry Farm-Teaching and Research Facilities-Turkey Facility
Post Construction
CP number: CP002490
Total Construction Budget: $690,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/1/2021
Begin construction: 4/5/2021
Occupancy / completion: 01/02/2022
Gross sq.ft.: 19770
Net sq.ft.: 19770
Prime contractor: BRENTON BUILDINGS LLC
Project manager:
Mark Huss
Construction manager:
Troy Chandler
Design Professional: CURRY WILLE & ASSOC
Overall Project Description of Work
The project consists of, but is not limited to, materials and labor to construct a 19,770 square foot turkey research facility. The project shall include the foundation, the structure (either wood or steel), concrete floors, insulated walls and roof, and doors and windows.
Poultry Farm-Teaching and Research Facilities-Turkey Facility-Phase 2
Construction
CP number: CP002490
Total Construction Budget: $700,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/13/2022
Begin construction: 1/14/2022
Occupancy / completion: 08/10/2022
Gross sq.ft.: 3920
Net sq.ft.: 2940
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Huss
Construction manager:
Troy Chandler
Design Professional: CURRY WILLE & ASSOC
Overall Project Description of Work
The project consists of, but is not limited to, materials and labor to build-out a 3920 square foot work area. This area has all of the under floor utilities installed, has a concrete floor, is in an insulated building enclosure, has drywall ceiling and perimeter walls. The ceiling and walls are not taped or finished. The project shall include constructing interior walls, electrical, mechanical, and plumbing.
Psychology Department-Wayfinding Improvements
Post Construction
CP number: CP002733
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction: 11/1/2021
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Kelly Kalvelage
Construction manager:
Kelly Kalvelage
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
The Department of Psychology is spread out amongst four buildings. To assist students, visitors, and staff navigate to and within the various buildings, there is a need to create consistent wayfinding and identity.
Reiman Gardens-Conservatory Chiller-Replacement
Bid
CP number: CP1110586
Total Construction Budget: $181,500
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will replace an existing air-conditioning chiller with a new chiller and downsize the breaker to match the new chiller electrical load. This project includes, but is not limited to mechanical and electrical work.
Reiman Gardens-Southwest Corner Improvements-Landscaping
Construction
CP number: CP002363
Total Construction Budget: $2,450,219
includes the bid estimate and contingency for this scope of work
Bid date: 3/1/2018
Begin construction: 3/6/2018
Occupancy / completion: 12/23/2018
Gross sq.ft.: 55000
Net sq.ft.: N/A
Prime contractor: GRAPHITE CONSTRUCTION GROUP INC
Project manager:
Mark Huss
Construction manager:
John Boehmer
Design Professional: SPURLOCK LANDSCAPE ARCHITECTS
Overall Project Description of Work
The project consists of, but is not limited to, construction of plant gardens, connecting paths, water features, a single restroom building with mechanical space, a 40-foot-tall steel and wood tower, and associated earth work and utility services.
Roberts Residence Hall-Patio Repairs-West
Bid
CP number: CP1001602
Total Construction Budget: $450,450
includes the bid estimate and contingency for this scope of work
Bid date: 3/28/2023
Begin construction: 5/15/2023
Occupancy / completion: 09/07/2023
Gross sq.ft.: 1455
Net sq.ft.: 1455
Prime contractor: TBD
Project manager:
Jennifer Evans
Construction manager:
Kasi Province
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, the repair and replacement of the patio structure, surface, stairs, and railings on the west exterior patio at Roberts Residence Hall. Interior patio walls below the surface will be repointed and waterproofed. The current patio crawlspace will be regraded, filled with geofoam, and topped with a new concrete base and patio surface. New subdrainage, downspouts, and patio surface drains will be connected to the existing storm drain.
ROTC Obstacle Course
Construction
CP number: CP988030
Total Construction Budget: $285,000
includes the bid estimate and contingency for this scope of work
Bid date: 11/3/2022
Begin construction: 12/8/2022
Occupancy / completion: 06/30/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Angela Solberg
Construction manager:
Nathan Graves
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, site grading, obstacle course equipment and footings, mulch, drainage, fencing, finish grading and topsoil.
Roy J. Carver Co-Laboratory-Room 0027-Remodel
Construction
CP number: CP1044309
Total Construction Budget: $68,600
includes the bid estimate and contingency for this scope of work
Bid date: 10/26/2022
Begin construction:
Occupancy / completion: 01/01/2023
Gross sq.ft.: 676
Net sq.ft.: 676
Prime contractor: IRON HILL CONSTRUCTION LLC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing space for testing and demonstration of robotic instrumentation. This project includes, but is not limited to, architectural, mechanical, and electrical work.
Schilletter Village-Exterior Improvements-Phase 2
Construction
CP number: CP002499
Total Construction Budget: $650,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 08/31/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Huss
Construction manager:
Mark Huss
Design Professional: ISU - Department of Residence
Overall Project Description of Work
CURRENT MAIN ENTRANCE DECKS WILL BE REMOVED, BUILDING FRAMING AND SIDING WILL BE REPAIRED AS NEEDED, AND THE DECKS WILL BE REPLACED. SECTIONS OF CONCRETE SIDEWALKS THAT HAVE SETTLED OVER TIME WILL BE REPLACED AS NEEDED. WINDOWS AND SOME EXTERIOR DOORS WILL BE REPLACED. THE SITE WILL BE REGRADED TO ROUTE WATER AWAY FROM THE WINDOW WELLS OF BUILDINGS WHERE THE BASEMENT FLOODS CONSISTENTLY.
Science Hall 2-Accessibility, Wayfinding, and Signage-Improvements
Design-SD
CP number: CP1003358
Total Construction Budget: $126,300
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Jennifer Evans
Construction manager:
Jennifer Evans
Design Professional: ISU
Overall Project Description of Work
This project includes, but is not limited to, evaluation of existing signage conditions, room count, numbering and specific space allocations; and design and documentation for new wayfinding and accessible signage/
Science Hall-AHU 2-Replacement
Construction
CP number: CP1006645
Total Construction Budget: $535,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/1/2022
Begin construction: 1/5/2023
Occupancy / completion: 09/14/2023
Gross sq.ft.: 897
Net sq.ft.: 897
Prime contractor: DAHL AIR COND & HEATING LLC
Project manager:
Mark Grief
Construction manager:
Steven Nelson
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, the replacement of AHU 2, in Room 061, minor demolition of existing plaster bulkheads, repair and replacement of existing acoustical tile ceilings, in corridors C0101, C0155, C0255, and C0355 and electrical work associated with AHU 2 and ceilings in corridors C0101, C0155, C0255, and C0355.
Science Hall-AHU 3-Replacement
Construction
CP number: CP1006655
Total Construction Budget: $235,330
includes the bid estimate and contingency for this scope of work
Bid date: 12/8/2022
Begin construction: 12/22/2022
Occupancy / completion: 08/21/2024
Gross sq.ft.: 513
Net sq.ft.: 513
Prime contractor: STEIN HEATING & COOLING INC
Project manager:
Mark Grief
Construction manager:
Steven Nelson
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, the removal and replacement of Air Handling Unit 3 in Room 0074A of Science Hall. This work includes minor demolition of a masonry wall for a new door opening, demolition of existing piping, and demolition of existing ductwork associated with the demolition of the existing Air Handling Unit 3. Work also includes installing a new door and frame, insulating an existing wall, and installing a new air handling unit, ductwork, controls and associated piping with the installation of the unit.
Science Hall-Rooms 0102 & 0152-Ventilation Improvements
Bid
CP number: CP942926
Total Construction Budget: $250,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/4/2023
Begin construction: 5/28/2023
Occupancy / completion: 11/30/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Elizabeth Clarke
Construction manager:
Mick McBride
Design Professional: DESIGN ENGINEERS PC
Overall Project Description of Work
The project consists of, but is not limited to, the replacement of two air handling units and the installation of two new energy recovery ventilators.
Seed Science Building-Room M0260-Vacuum Pump System
Construction
CP number: PR024332
Total Construction Budget: $72,930
includes the bid estimate and contingency for this scope of work
Bid date: 5/20/2022
Begin construction:
Occupancy / completion: 10/14/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will disconnect, remove, and install a new vacuum pump in Room M0260 at the Seed Science Building. The scope of work will include but not be limited to: general construction, electrical, and Owner provided control work.
Snedecor Hall-Rooms 1108, 2101, and 3105-Remodel
Construction
CP number: CP986791
Total Construction Budget: $64,200
includes the bid estimate and contingency for this scope of work
Bid date: 4/11/2022
Begin construction: 4/14/2022
Occupancy / completion: 07/31/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Christine Reinders-Caron
Construction manager:
Christine Reinders-Caron
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, renovation of a restroom, lounge, and seminar room, including replacement of countertops, plumbing fixtures and furniture, and minor electrical work.
Sports Performance Center & Jack Trice Stadium Improvements North-Bergstrom Football Complex-Rooms 2050, 2054, and 2056 Remodel
Construction
CP number: CP002505
Total Construction Budget: $570,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/5/2022
Begin construction: 5/12/2022
Occupancy / completion: 08/19/2022
Gross sq.ft.: 3200
Net sq.ft.: 1575
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: SUBSTANCE ARCHITECTURE
Overall Project Description of Work
The project consists of, but is not limited to, interior demolition of existing metal stud walls and finishes. New construction to include new metal stud walls and finishes, ceilings, lighting, mechanical and new corridor carpeting.
Sports Performance Center & Jack Trice Stadium Improvements North-Jacobson & Concourse
Post Construction
CP number: CP002505
Total Construction Budget: $15,000,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/5/2020
Begin construction: 3/10/2020
Occupancy / completion: 07/30/2021
Gross sq.ft.: 52000
Net sq.ft.: 41500
Prime contractor: NEUMANN BROTHERS INC
Project manager:
Jonathan Harvey
Construction manager:
Danelda Allen
Design Professional: SUBSTANCE ARCHITECTURE
Overall Project Description of Work
The project consists of, but is not limited to, remodeling within the existing Jacobson Building, demolition of the existing Olsen Building, constructing a new concourse and connection bridge, and stadium hillside upgrades. Work includes concrete foundations, steel structure, precast concrete, metal wall panels, glazing, PVC roofing, CMU, metal stud framing, interior glazing, interior finishes, mechanical, and electrical systems.
Sports Performance Center & Jack Trice Stadium Improvements North-Sports Performance Center
Post Construction
CP number: CP002505
Total Construction Budget: $45,000,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/20/2019
Begin construction: 7/12/2019
Occupancy / completion: 07/16/2021
Gross sq.ft.: 144795
Net sq.ft.: 1474795
Prime contractor: NEUMANN BROTHERS INC
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: SUBSTANCE ARCHITECTURE
Overall Project Description of Work
The project consists of, but is not limited to, new construction for a 4-story plus basement, 98,626 sf Sports Performance Center. New construction for a single-story plus mezzanine, 13,832 sf West Bergstrom addition. Remodeling to the existing Bergstrom Facility, 18,827 sf with associated utility, building systems, site, and landscape work. Work includes concrete foundations, drilled piers, steel structure, precast concrete, metal wall panels, glazed curtain walls, PVC roofing, metal roofing panels, CMU, metal stud framing, interior glazing, interior finishes, lockers, kitchen equipment, mechanical, and electrical systems.
Stephens Auditorium-Main Lobby Carpet-Replacement
Construction
CP number: CP1097770
Total Construction Budget: $167,400
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, the replacement of the existing carpet in the main lobby.
Stephens Auditorium-Restrooms-Remodel
Design-CD
CP number: CP999526
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 6/29/2023
Begin construction: 7/17/2023
Occupancy / completion: 12/15/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Hayley Sandholm
Design Professional: SVPA ARCHITECTS INC
Overall Project Description of Work
This project will convert storage space on the main floor into eight single user accessible restrooms and remodel one existing multiple user mens
room and one existing multiple user womens room on the ground floor. The project includes, but is not limited to new bathroom fixtures,
plumbing, finishes and partitions in existing restrooms and constructing complete new accessible restrooms.
Stephens Auditorium-Roof Replacement-Section A
Post Construction
CP number: CP002745
Total Construction Budget: $410,000
includes the bid estimate and contingency for this scope of work
Bid date: 4/28/2022
Begin construction: 5/3/2022
Occupancy / completion: 10/30/2022
Gross sq.ft.: 23550
Net sq.ft.: 23550
Prime contractor: BLACK HAWK ROOF CO INC
Project manager:
Jonathan Harvey
Construction manager:
Steven Nelson
Design Professional: I&S GROUP INC
Overall Project Description of Work
The project consists of, but is not limited to, installing new fully adhered 90 mil EPDM roof membrane and insulation system over the existing roof membrane and insulation. Provide and install new flashings and roof expansion covers.
Student Innovation Center-Dust Collection System
Post Construction
CP number: CP002225
Total Construction Budget: $350,000
includes the bid estimate and contingency for this scope of work
Bid date: 12/17/2020
Begin construction: 12/18/2020
Occupancy / completion: 04/02/2021
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: ACI MECHANICAL INC
Project manager:
Elizabeth Clarke
Construction manager:
Nathan Graves
Design Professional: SUBSTANCE ARCHITECTURE
Overall Project Description of Work
The project consists of, but is not limited to, installation of a new dust collection system serving the level 1 fabrication space in the Student Innovation Center. Work requires selective demolition, installation of a full dust collection system including controls, fire suppression, compressed air, and all other items to support the full system, and integration with existing building systems.
Student Innovation Center-Room 1858-Modifications
Design-CD
CP number: CP1105833
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Elizabeth Clarke
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, the removal of the metal screen partition and track system used to enclosure the Innovate 1858 shop, and replacement with a glass sliding door panel system. Work also includes the relocation of existing ductwork and junction box at the northwest corner to accommodate the new panel system.
Student Services Building-Common Area Improvements
Post Construction
CP number: CP002756
Total Construction Budget: $320,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/26/2021
Begin construction: 10/27/2021
Occupancy / completion: 05/02/2022
Gross sq.ft.: 1900
Net sq.ft.: 1900
Prime contractor: HPC LLC
Project manager:
Jennifer Evans
Construction manager:
John Boehmer
Design Professional: HARTMAN TRAPP ARCHITECTURE STUDIO LLC
Overall Project Description of Work
This project will improve the overall first impressions and circulation of the Student Services building common areas. This project includes, but is not limited to, space reconfiguration, updating finishes, new furniture, and new technology.
Sukup Basketball Complex-Rooms 1124 & 1125-Renovation
Bid
CP number: CP964890
Total Construction Budget: $648,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/2/2023
Begin construction: 5/16/2023
Occupancy / completion: 09/01/2023
Gross sq.ft.: 2860
Net sq.ft.: 2680
Prime contractor: TBD
Project manager:
Jonathan Harvey
Construction manager:
Nathan Graves
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
The project consists of, but is not limited to, demolition of existing finishes and walls; installation of new stud walls, flooring, finishes, and ceilings; new lighting; and modifications to existing mechanical system.
Surplus Warehouse
Design-CD
CP number: CP1000965
Total Construction Budget: $422,500
includes the bid estimate and contingency for this scope of work
Bid date: 5/25/2023
Begin construction:
Occupancy / completion:
Gross sq.ft.: 6600
Net sq.ft.: 6600
Prime contractor: TBD
Project manager:
Jennifer Evans
Design Professional: CURRY WILLE & ASSOC
Overall Project Description of Work
This project includes, but is not limited to, the construction of a new 6,600 sf warehouse, north of the existing Surplus Facility.
Therkildsen Industrial Engineering Building
Construction
CP number: CP002619
Total Construction Budget: $32,250,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction: 9/29/2022
Occupancy / completion: 11/30/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: STORY CONSTRUCTION CO
Project manager:
Elizabeth Clarke
Construction manager:
Danelda Allen
Design Professional: S-L-A-M COLLABORATIVE INC
Overall Project Description of Work
The project consists of, but is not limited to, the design and construction of a new four-story stand-alone building located southwest of Howe Hall and north of Thielen Student Health Center for the Department of Industrial and Manufacturing Systems Engineering (IMSE) of the College of Engineering including site development, utility infrastructure improvements, and building construction.
Therkildsen Industrial Engineering Building-Parking Lot 1 Expansion
Construction
CP number: CP002619
Total Construction Budget: $1,355,000
includes the bid estimate and contingency for this scope of work
Bid date: 9/8/2022
Begin construction: 9/26/2022
Occupancy / completion: 05/20/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: CONCRETE PROFESSIONALS
Project manager:
Angela Solberg
Construction manager:
Danelda Allen
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
This project will construct an addition to Parking Lot 1, west of Friley Hall and south of Martin Residence Hall and realign Sheldon Avenue Extension, west of Town Engineering and Lot 10. The project consists of, but is not limited to, pavement removal, grading, storm drainage, underground and surface detention, PCC paving, communication utilities and lighting.
Therkildsen Industrial Engineering Building-Parking Lot 10 Expansion
Construction
CP number: CP002619
Total Construction Budget: $1,045,000
includes the bid estimate and contingency for this scope of work
Bid date: 3/7/2023
Begin construction: 3/9/2023
Occupancy / completion: 08/04/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: ELDER CORP
Project manager:
Angela Solberg
Construction manager:
Danelda Allen
Design Professional: SNYDER & ASSOC INC
Overall Project Description of Work
The project consists of, but is not limited to, expansion of Parking Lot 10, located west of Town Engineering Building. The project includes pavement removal, grading, storm drainage utilities, underground storm detention, asphalt paving, asphalt mill and overlay, concrete curb and gutter, sidewalks and lighting.
Town Engineering Building-Facility and Infrastructure-Improvements
Pre-Design
CP number: CP1001182
Total Construction Budget: $209,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor:
Project manager:
Angela Solberg
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, the purchase of a 3D concrete printer and electrohydraulic pump system, as well as mechanical, electrical, ventilation, storage, and other facility improvements to support the equipment and other analytical instrumentation for instructional and research laboratory needs. Dock improvements to support storage and access for materials handling equipment; renovations to rooms that support the geotechnical and materials engineering, environmental engineering, and water resources engineering research and instruction will be designed and implemented as feasible.
Town Engineering Building-Wireless Card Access-Improvements
Construction
CP number: CP1001624
Total Construction Budget: $165,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor:
Project manager:
Angela Solberg
Construction manager:
Angela Solberg
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, installation of new wireless card access readers on approximately 44 doors in the Town Engineering Building.
Union Drive Community Center-Union Drive Marketplace-Renovation-Venues
Construction
CP number: CP002589
Total Construction Budget: $1,857,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/7/2023
Begin construction: 2/8/2023
Occupancy / completion: 08/04/2023
Gross sq.ft.: 6088
Net sq.ft.: 6088
Prime contractor: HENKEL CONSTRUCTION COMPANY
Project manager:
David Blum
Construction manager:
Darrell Reeves
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, renovation of interior finishes and equipment in seating area and foodservice venues in the Union Drive Community Center. Upgrades include polishing of existing concrete flooring, wall and ceiling finishes, replacement of existing doors, new cooking and foodservice equipment, plumbing improvements, electrical power improvements, and installation of new lighting.
Union Drive Community Center-Union Drive Marketplace-Renovation-Venues and Seating
Construction
CP number: CP002589
Total Construction Budget: $1,893,000
includes the bid estimate and contingency for this scope of work
Bid date: 1/6/2022
Begin construction: 1/12/2022
Occupancy / completion: 08/22/2022
Gross sq.ft.: 8325
Net sq.ft.: 8325
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
David Blum
Construction manager:
Darrell Reeves
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
The project consists of, but is not limited to, renovation of interior finishes and equipment in seating area and three foodservice venues in the Union Drive Community Center. Upgrades include polishing of existing concrete flooring, wall and ceiling finishes, replacement of existing doors, new cooking and foodservice equipment, plumbing improvements, electrical power improvements, and installation of new lighting.
Union Drive Community Center-Various Repairs
Construction
CP number: CP941101
Total Construction Budget: $88,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 10/04/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
David Blum
Design Professional: BROOKS BORG SKILES ARCH ENGR
Overall Project Description of Work
This project includes, but is not limited to, modification of existing dryer exhaust system, cleaning of VAV/AHU coils and associated ductwork, steam condensate vent modifications, replacement of glycol heating water pumps and VFD pumps serving AHU-1 and AHU-2, replacement of heating water pumps that serve VAV reheat coils and perimeter radiation, and addition of VFDs and associated controls.
Union Drive Community Center-Water Heater Replacements
Post Construction
CP number: CP926435
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 07/15/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
David Blum
Construction manager:
Darrell Reeves
Design Professional: ISU
Overall Project Description of Work
This project includes, but is not limited to, removing and replacing two domestic water heaters, piping, and accessories in Room M180.
Utilities-Applied Science Complex-Deaerator Installation
Post Construction
CP number: CP002736
Total Construction Budget: $101,105
includes the bid estimate and contingency for this scope of work
Bid date: 2/1/2022
Begin construction: 2/7/2022
Occupancy / completion: 05/08/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: MANNING SEIVERT MECHANICAL CONTRACTORS INC
Project manager:
Lee Mason
Construction manager:
Lee Mason
Design Professional: FARRIS ENGINEERING INC
Overall Project Description of Work
The project consists of, but is not limited to, removal of existing condensate tank, feed pumps, concrete bases and miscellaneous equipment, valves, piping, wiring, and conduit. Also includes installation of a new Owner-furnished deaerator tank and pump units, piping, and electrical work.
Utilities-Campus Sidewalk Lighting Improvements-Phase 2
Post Construction
CP number: CP002671
Total Construction Budget: $148,318
includes the bid estimate and contingency for this scope of work
Bid date: 6/10/2021
Begin construction: 6/11/2021
Occupancy / completion: 08/15/2021
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: JASPERING ELECTRIC INC
Project manager:
Caleb Barduson
Construction manager:
Caleb Barduson
Design Professional: SHIVE HATTERY ENGR & ARCH INC
Overall Project Description of Work
The project consists of, but is not limited to, improving lighting on campus sidewalks by installing new poles and light fixtures, relocating existing sidewalk poles, installing solar-powered sidewalk lights, and adding/replacing building mounted lights.
Utilities-Hilton Coliseum-High Voltage Feeder Replacement
Post Construction
CP number: CP002637
Total Construction Budget: $215,000
includes the bid estimate and contingency for this scope of work
Bid date: 8/20/2020
Begin construction: 8/21/2020
Occupancy / completion: 10/04/2020
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: C GREEN CONTRACTOR INC
Project manager:
Michael Olson
Construction manager:
Travis Van Dyke
Design Professional: KFI ENGINEERS PC
Overall Project Description of Work
The project consists of, but is not limited to, demolition and reconstruction of an existing electrical high voltage vault with energized cables, concrete and asphalt demolition and replacement, conduit trench excavation, installation of underground concrete encased PVC conduits, concrete core drills, and installation of RGS conduits in an unexcavated area inside Hilton Coliseum.
Utilities-Pearson Substation-13.8kV Feeder Cable Replacement
Construction
CP number: CP923004
Total Construction Budget: $310,000
includes the bid estimate and contingency for this scope of work
Bid date: 7/19/2022
Begin construction: 7/29/2022
Occupancy / completion: 08/11/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TRI CITY ELECTRIC CO OF IA
Project manager:
Travis Van Dyke
Construction manager:
Travis Van Dyke
Design Professional: ISU - Utilities
Overall Project Description of Work
The project consists of, but is not limited to, removal and replacement of 13,800V cable in existing conduits between underground vaults and above ground switchgear, cable splices in existing underground vaults, and cable terminations in above ground switchgear. Perform hi-pot cable tests on installed cable, splices, and terminations.
Utilities-Power Plant-ABB Software and SCADA Upgrades
Construction
CP number: CP002626
Total Construction Budget: $342,776
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction: 12/1/2019
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Kruse
Construction manager:
Nicholas Kolbet
Design Professional: ISU - Utilities
Overall Project Description of Work
This project will upgrade existing Power Plant operator consoles and SCADA System.
Utilities-Power Plant-Balance of Plant Programmable Logic Controller
Post Construction
CP number: CP002629
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Mark Kruse
Construction manager:
Mark Kruse
Design Professional: KFI ENGINEERS PC
Overall Project Description of Work
This project will replace increasingly dated controls for power plant auxiliary equipment, including service water pumps, feed water pumps, pressure reducing station controls, and condensate tank level controls.
Utilities-Power Plant-Chiller 1 Turbine Overhaul FY23
Construction
CP number: CP1015183
Total Construction Budget: $218,110
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion: 05/01/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Matthew Shriver
Construction manager:
Matthew Shriver
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, opening, cleaning, and inspecting the steam turbine on Chiller 1. Any turbine components found worn or damaged will be repaired or replaced.
Utilities-Power Plant-Chiller 5 Compressor Overhaul FY23
On Hold
CP number: CP1044984
Total Construction Budget: $320,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor:
Project manager:
Matthew Shriver
Construction manager:
Matthew Shriver
Design Professional: ISU - Utilities
Overall Project Description of Work
This project includes, but is not limited to, opening, cleaning, and inspecting the refrigerant compressor on Chiller 5. Compressor components found worn or damaged will be repaired or replaced.
Utilities-Power Plant-Coal Boilers Natural Gas Conversion
Construction
CP number: CP002712
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction: 10/8/2021
Occupancy / completion: 09/28/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: BOWEN ENGINEERING CORP
Project manager:
Mark Kruse
Construction manager:
Lee Mason
Design Professional: ISU - Utilities
Overall Project Description of Work
This project will convert the two remaining coal-fired boilers (Boilers #1 & #2) in the University's central cogeneration plant to natural gas-fired boilers, ending the use of coal by Iowa State University. The conversion includes modifying the boiler's existing burners and fans along with removing the auxiliary coal handling systems. In addition, the project will restore two coal storage sites (east of Haber Road and adjacent to the Power Plant).
Utilities-Power Plant-Condenser Water Piping-Repairs
Construction
CP number: CP002753
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Design Professional: ISU - Utilities
Overall Project Description of Work
This project includes, but is not limited to, emergency excavation and repair of buried condenser water pipes between the Utility Plant and Cooling Towers upon discovery of significant surface level water leaks.
Utilities-Power Plant-External Stack Repairs
On Hold
CP number: CP002607
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Lee Mason
Construction manager:
Lee Mason
Design Professional:
Overall Project Description of Work
This project will replace existing platforms, install a new stack fall protection system, replace conduits, and clean and paint the exterior of the stack.
Utilities-Power Plant-Station Power Improvements-Phase 1
Post Construction
CP number: CP002466
Total Construction Budget: $1,048,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/11/2021
Begin construction: 2/16/2021
Occupancy / completion: 11/15/2021
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: C GREEN CONTRACTOR INC
Project manager:
Michael Olson
Construction manager:
Caleb Barduson
Design Professional: SEBESTA INC
Overall Project Description of Work
The project consists of, but is not limited to, expanding the existing 4160 volt electrical substation located south of the General Services Building to accommodate a new 8.4 MVA transformer, 13,800 volt switchgear, a high voltage feeder cable from Haber Road substation to service the new transformer and switchgear and high voltage feeder cables from the new transformer to the existing 4160 volt switchgear along with new underground raceway systems. Site work includes the removal of the existing site masonry enclosure, construction of new footings and enclosure walls, relocation of an existing underground water main, replacement of a section of stream tunnel roof and replacement of affected roadway and parking lot pavement.
Utilities-Power Plant-Station Power Improvements-Phase 2
Post Construction
CP number: CP002466
Total Construction Budget: $183,000
includes the bid estimate and contingency for this scope of work
Bid date: 7/2/2020
Begin construction: 7/6/2020
Occupancy / completion: 08/24/2020
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: WALDINGER CORP
Project manager:
Michael Olson
Construction manager:
Caleb Barduson
Design Professional: SEBESTA INC
Overall Project Description of Work
The project consists of, but is not limited to, installation of ridged steel conduit and high voltage cable bored from one existing underground electrical vault to another. Additional work includes the energization and testing of the high voltage cable and breaker.
Utilities-Power Plant-Station Power Improvements-Phase 4
Construction
CP number: CP002466
Total Construction Budget: $2,899,000
includes the bid estimate and contingency for this scope of work
Bid date: 2/8/2022
Begin construction: 2/21/2022
Occupancy / completion: 07/06/2023
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: WOODRUFF CONSTRUCTION INC
Project manager:
Michael Olson
Construction manager:
Caleb Barduson
Design Professional: SEBESTA INC
Overall Project Description of Work
The project consists of, but is not limited to, the replacement of two each 4160-volt Metal clad switchgears, installation of new medium voltage cables, expansion of an existing SCADA control system, installation of 480-volt panels, 120/208-volt panels, 125-volt DC Panels, transfer switches, 480:120/208-volt transformers and associated 600-volt class cables within the Iowa State University Power Plant. Additional work includes the demolition of 2 existing 4160-volt Metal clad switchgears, one 4160-volt metal enclosed switchgear, one 4160-volt Motor Control Center, one 480-volt Motor Control Center and multiple 480-volt and less power panels and associated equipment, raceways and cables. Architectural/Structural work includes, but is not limited to, the construction of two rooms, demolition of two rooms and the infill of a large opening on the first floor of the Power Plant. Mechanical work includes, but is not limited to, the relocation and installation of steam, condensate, chilled water, domestic water, fire protection, and demineralizer piping systems, relocation of steam supplied unit heaters, the replacement of one roof top HVAC unit and the installation of two new air handling units. All work will occur and be scheduled while keeping the Power Plant fully operational.
Utilities-Various Buildings-Fire Detection System
On Hold
CP number: CP002667
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Lee Mason
Construction manager:
Lee Mason
Design Professional: HR GREEN INC
Overall Project Description of Work
This project will install a fire alarm and detection system for auxiliary buildings that support the Power Plant. These buildings include Cooling Tower Service Building, Cooling Tower Control Building and the Veterinary Medicine Pump House. The project will connect the new alarm and detection systems to existing master fire alarm panels located in the main and Veterinary Medicine power plants.
Various Building Automation Improvements 2020 and 2021
Construction
CP number: CP002701
Total Construction Budget: $200,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Christine Maduro
Construction manager:
Christine Maduro
Design Professional: ISU - Utilities
Overall Project Description of Work
THIS PROJECT WILL PROVIDE FOR A NUMBER OF BUILDING AUTOMATION SYSTEM UPGRADES FOR CONTROLLING OUR HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) SYSTEMS.
Various Building Automation Improvements FY21
Construction
CP number: CP002722
Total Construction Budget: $210,808
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Christine Maduro
Construction manager:
Christine Maduro
Design Professional: ISU - Utilities
Overall Project Description of Work
THIS PROJECT WILL PROVIDE FOR A NUMBER OF BUILDING AUTOMATION SYSTEM UPGRADES FOR CONTROLLING OUR HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) SYSTEMS.
Various Building Automation Improvements FY22
Construction
CP number: CP898550
Total Construction Budget: $234,800
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Robert Currie
Construction manager:
Robert Currie
Design Professional: ISU - FDC
Overall Project Description of Work
This project will provide for a number of building automation system upgrades for controlling our heating, ventilation, and air conditioning (HVAC) systems.
Various Building Automation Improvements FY23
Construction
CP number: CP1087290
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor:
Project manager:
Christine Maduro
Construction manager:
Christine Maduro
Design Professional:
Overall Project Description of Work
This project includes, but is not limited to, building automation upgrades for controlling HVAC systems.
Various Building Safety Improvements FY22
Construction
CP number: CP898531
Total Construction Budget: $100,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Iowa State University
Project manager:
Robert Currie
Construction manager:
Robert Currie
Design Professional: ISU - FDC
Overall Project Description of Work
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Various Building Safety Improvements FY23
Construction
CP number: CP1017209
Total Construction Budget: $100,000
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Robert Currie
Construction manager:
Robert Currie
Design Professional: ISU - FDC
Overall Project Description of Work
This project will provide for a number of small building system improvement projects addressing EPA and OSHA compliance, life safety, occupant safety, and maintenance needs in various campus buildings.
Various Campus Locations-Ash Tree Removal and Replacement
Pre-Design
CP number: CP1105518
Total Construction Budget: $121,480
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: Multiple Constructors
Project manager:
Rhonda Martin
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, the removal of approximately 73 remaining ash trees and the installation of approximately 120 replacement trees of various varieties in general fund maintained areas of central campus.
Veterinary Medicine-Core Lab-Remodel
Construction
CP number: CP987945
Total Construction Budget: $464,000
includes the bid estimate and contingency for this scope of work
Bid date: 10/27/2022
Begin construction: 10/31/2022
Occupancy / completion: 05/09/2023
Gross sq.ft.: 1841
Net sq.ft.: 1841
Prime contractor: HPC LLC
Project manager:
Mark Grief
Construction manager:
Kasi Province
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, the remodeling of existing laboratory and office space, into a Core Laboratory. This project includes minor demolition, new walls, new doors, finishes and equipment to create the new Core laboratory.
Veterinary Medicine-Domestic Water Line Replacement-Phases 5 and 6
Design-CD
CP number: CP002621
Total Construction Budget: $420,750
includes the bid estimate and contingency for this scope of work
Bid date: 6/1/2023
Begin construction: 7/31/2023
Occupancy / completion: 07/01/2024
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: TBD
Project manager:
Mark Grief
Construction manager:
Mick McBride
Design Professional: ISU - FDC
Overall Project Description of Work
This project includes, but is not limited to, removing the old piping system, replacing it with copper piping, and adding additional gate valves to provide for improved zoning of the domestic water service.
Veterinary Medicine-Room 1330-Remodel
Construction
CP number: CP002761
Total Construction Budget: $148,830
includes the bid estimate and contingency for this scope of work
Bid date: 2/3/2022
Begin construction: 2/9/2022
Occupancy / completion: 07/24/2022
Gross sq.ft.: 890
Net sq.ft.: 890
Prime contractor: GTG CONSTRUCTION LLC
Project manager:
Mark Grief
Construction manager:
Nathan Graves
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel an underutilized existing storage space into a kenneling room. This project includes, but is not limited to, reconfiguration of the room layout, finish updates, modification of mechanical equipment, piping, and ductwork, new light fixtures, receptacles, and fire alarm devices.
Veterinary Medicine-Room 1351-Remodel
Bid
CP number: CP930111
Total Construction Budget: $929,680
includes the bid estimate and contingency for this scope of work
Bid date: 2/23/2023
Begin construction: 3/24/2023
Occupancy / completion: 02/06/2024
Gross sq.ft.: 2651
Net sq.ft.: 2651
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
John Boehmer
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
This project includes, but is not limited to the demolition of the existing interior horse stalls, new LED lighting and electrical outlets, new finishes, including impervious surfaces, floor, walls, and ceiling in specified areas, mechanical upgrades to maintain a minimum required air changes, and biosafety Level 2 Lab requirement in a small portion of the lab.
Veterinary Medicine-Room 2280-Improvements
Post Construction
CP number: CP998648
Total Construction Budget: $17,800
includes the bid estimate and contingency for this scope of work
Bid date:
Begin construction:
Occupancy / completion:
Gross sq.ft.: 5265
Net sq.ft.: 2565
Prime contractor: Multiple Constructors
Project manager:
Leigh Wiand
Construction manager:
Leigh Wiand
Design Professional: ISU - FDC
Overall Project Description of Work
This project will add new furniture to the Veterinary Medicine Library. The project includes, but is not limited to, electrical work, acoustic screens, dividing panels, booth/banquette seating, tables, and lounge furniture.
Veterinary Medicine-Rooms 1039 and 1059-Remodel
Post Construction
CP number: CP1002165
Total Construction Budget: $51,000
includes the bid estimate and contingency for this scope of work
Bid date: 6/8/2022
Begin construction:
Occupancy / completion: 10/14/2022
Gross sq.ft.: 449
Net sq.ft.: 354
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will remodel the existing laboratories. The project includes, but is not limited to, abatement, electrical, mechanical, and casework.
Veterinary Medicine-Rooms 2401, 2402, 2403, and 2404-Remodel
Construction
CP number: CP936596
Total Construction Budget: $209,000
includes the bid estimate and contingency for this scope of work
Bid date: 5/3/2022
Begin construction: 5/4/2022
Occupancy / completion: 08/09/2022
Gross sq.ft.: 2500
Net sq.ft.: 2500
Prime contractor: RH GRABAU CONSTRUCTION INC
Project manager:
Mark Grief
Construction manager:
Kasi Province
Design Professional: ISU - FDC
Overall Project Description of Work
The project consists of, but is not limited to, remodeling existing meeting rooms with new partition walls, carpet, ceiling tiles, windows, and doors. Also replacing light fixtures, receptacles, and furniture.
Veterinary Medicine-Veterinary Diagnostic Laboratory
Construction
CP number: CP002554
Total Construction Budget:
includes the bid estimate and contingency for this scope of work
Bid date: 10/2/2020
Begin construction: 10/6/2020
Occupancy / completion: 09/21/2023
Gross sq.ft.: 68624
Net sq.ft.: 41200
Prime contractor: WEITZ COMPANY INC
Project manager:
David Blum
Construction manager:
Nathan Graves
Design Professional: INVISION ARCHITECTURE LTD
Overall Project Description of Work
The Project consists of, but is not limited to, the design and construction of a new two story stand-alone Veterinary Diagnostic Laboratory (VDL) building on the College of Veterinary Medicine campus. This new facility will serve the diagnostic medicine needs of Iowa livestock and poultry, pets and wildlife, and in the process, protect human health and grow Iowa economy. In addition, the facility will address the most urgent space requirements for the laboratory, improve biocontainment, and enhance biosafety standards to protect employee and student health.
Zaffarano Physics Addition-Rooms A0213 and A0215-Remodel
Post Construction
CP number: CP926444
Total Construction Budget: $76,365
includes the bid estimate and contingency for this scope of work
Bid date: 12/3/2021
Begin construction: 12/6/2021
Occupancy / completion: 02/28/2022
Gross sq.ft.: N/A
Net sq.ft.: N/A
Prime contractor: BERGSTROM CONSTRUCTION INC
Project manager:
Eric Ohrt
Construction manager:
Eric Ohrt
Design Professional: ISU - FDC
Overall Project Description of Work
This project will renovate labs on the second floor of the Zaffarano Physics Addition. Work includes, but is not limited to, general construction, architectural, electrical, plumbing, and HVAC.