- Download electronic documents below
- Obtain printed copies from Iowa State Printing Services
- Examine at Plan Room (see project for list of plan holders)
- Email plans@iastate.edu to be added to plan holders list
Project Bid Dates
Projects Above $100,000
Bidding Documents
Bid Submission
- Bids must be submitted prior to 2:01 PM on bid date
- Submit bids electronically through Bid Express
- Refer to "Instructions to Bidders" in the project manual for bid submission requirements
Projects
Veenker Golf Course Grounds-Bridge Number 15 Replacement
Prebid Meeting: 9/30/2026 2:00:00 PM
Prebid location: Veenker Golf Course Grounds-Bridge Number 15 Replacement prebid: via Microsoft Teams
Tours: 9/30/2026 9:00 AM and 10/7/2026 10:00 AM
Bid date: 10/13/2026
Veenker Golf Course Grounds-Bridge Number 15 Replacement Bid opening online
Substantial completion: 220 days (Approximately June 4, 2027)
Cost estimate: $564,000
TSB goal: 10%
Project manager: Jennifer Evans
Construction manager:
Claire Vorthmann
Design Professional: Eric Vermeer, 515-292-0007
10FOLD ARCHITECTURE & ENGINEERING LTD
Bid Documents
Plan Holders
Power Plant-Mechanical Room 0125 Remodel
Prebid Meeting: 10/7/2026 2:00:00 PM
Prebid location: Power Plant-Mechanical Room 0125 Remodel prebid: via Microsoft Teams
Tours: 10/7/2026 1:00 PM and 10/14/2026 10:30 AM
Bid date: 10/22/2026
Power Plant-Mechanical Room 0125 Remodel Bid opening online
Substantial completion: January 15, 2027
Cost estimate: $185,400
TSB goal: 10%
Project manager: Chad Gourley
Construction manager:
Chad Gourley
Design Professional: Matthew Cole, 515-244-7167
BROOKS BORG SKILES ARCHITECTURE ENGINEERING LLP
Plan Holders
Lake LaVerne-Improvements-Bridge and Amphitheater
Prebid Meeting: 10/14/2026 11:00:00 AM
Tours: 10/13/2026 10:00 AM and 10/21/2026 11:00 AM
Bid date: 10/29/2026
Lake LaVerne-Improvements-Bridge and Amphitheater Bid opening online
Substantial completion: 180 days (Approximately May 11, 2027)
Cost estimate: $1,925,000
TSB goal: 10%
Project manager: Angela Solberg
Construction manager:
Claire Vorthmann
Design Professional: Alyssa Iverson, 515-415-4356
SHIVE HATTERY ARCHITECTURE & ENGINEERING
Bid Documents
Plan Holders
Utilities-Pearson Substation-4.16kV Switchgear and Cable Infrastructure Upgrade
Prebid Meeting: 10/21/2026 11:00:00 AM
Prebid location: Utilities-Pearson Substation-4.16kV Switchgear and Cable Infrastructure Upgrade prebid: via Microsoft Teams
Tour: 10/21/2026 1:00 PM
Bid date: 11/3/2026
Utilities-Pearson Substation-4.16kV Switchgear and Cable Infrastructure Upgrade Bid opening online
Substantial completion: August 6, 2027
Cost estimate: $285,900
TSB goal: 10%
Project manager: Travis Van Dyke
Construction manager:
Travis Van Dyke
Design Professional: Kevin Voss, 563-554-0129
PRVN CONSULTANTS INC
Plan Holders
Projects Under $100,000
Bid Submission
- Bids must be submitted prior to 4:00 PM on bid date
- Submit bids by emailing spbids@iastate.edu
- Refer to "Instructions to Bidders" in the project manual for bid submission requirements
Projects
- No projects scheduled -
