- Download electronic documents below
- Obtain printed copies from Iowa State Printing Services
- Examine at Plan Room (see project for list of plan holders)
- Email plans@iastate.edu to be added to plan holders list
Project Bid Dates
Upcoming Change
Beginning January 1, 2026, all bid openings will be conducted via Microsoft Teams (instead of Webex).
Please take time now to prepare by ensuring you have access to Teams before this transition.
Projects Above $100,000
Bidding Documents
Bid Submission
- Bids must be submitted prior to 2:01 PM on bid date
- Submit bids electronically through Bid Express
- Refer to "Instructions to Bidders" in the project manual for bid submission requirements
Projects
Parks Library-Room 0005 Film Vault Dehumidification
Prebid Meeting: 1/22/2026 11:00:00 AM
Tours: 1/22/2026 10:00 AM and 1/27/2026 10:00 AM
Bid date: 2/5/2026
Parks Library-Room 0005 Film Vault Dehumidification Bid opening online
Substantial completion: 180 days (Approximately August 18, 2026)
Cost estimate: $82,200
TSB goal: 10%
Project manager: Mitchell Hlavacek
Construction manager:
Mark Huss
Design Professional: Mike McCoy, 515-294-8313
ISU - FDC
Plan Holders
Utilities-Maple to Hixson-Lied Steam Vault Condensate Piping-Replacement
Prebid Meeting: 1/28/2026 10:00:00 AM
Prebid location: Utilities-Maple to Hixson-Lied Steam Vault Condensate Piping-Replacement prebid: via Microsoft Teams
Tours: 1/28/2026 9:00 AM and 2/2/2026 1:00 PM
Bid date: 2/10/2026
Utilities-Maple to Hixson-Lied Steam Vault Condensate Piping-Replacement Bid opening online
Substantial completion: August 10, 2026
Cost estimate: $210,000
TSB goal: 10%
Project manager: Sarah Witte
Construction manager:
Chad Gourley
Design Professional: Matthew Klein, 319-354-3040
SHIVE HATTERY ARCHITECTURE & ENGINEERING
Plan Holders
General Services Building-First Floor Renovation
Prebid Meeting: 1/28/2026 1:00:00 PM
Tours: 1/28/2026 12:00 PM and 2/2/2026 9:00 AM
Bid date: 2/12/2026
General Services Building-First Floor Renovation Bid opening online
Substantial completion: 156 days (Approximately August 1, 2026)
Cost estimate: $150,000
TSB goal: 10%
Project manager: Jennifer Evans
Construction manager:
Nathan Graves
Design Professional: Steven Daniels, 515-290-1967
ISU - FDC
Bid Documents
Plan Holders
Utilities-Electrical and Steam Infrastructure Improvements FY26
Prebid Meeting: 1/29/2026 11:00:00 AM
Prebid location: Utilities-Electrical and Steam Infrastructure Improvements FY26 prebid: via Microsoft Teams
Tours: 1/29/2026 10:00 AM and 2/5/2026 10:00 AM
Bid date: 2/12/2026
Utilities-Electrical and Steam Infrastructure Improvements FY26 Bid opening online
Substantial completion: Multiple (Final: August 13, 2027)
Cost estimate: $1,450,000
TSB goal: 10%
Project manager: Sarah Witte
Construction manager:
Chad Gourley
Design Professional: Matthew Klein, 319-354-3040
SHIVE HATTERY ARCHITECTURE & ENGINEERING
Plan Holders
Town Engineering Building-Rooms 0130, 0138 and 0138B Improvement
Prebid Meeting: 2/3/2026 10:00:00 AM
Prebid location: Town Engineering Building-Rooms 0130, 0138 and 0138B Improvement prebid: via Microsoft Teams
Tours: 2/3/2026 9:00 AM and 2/9/2026 10:00 AM
Bid date: 2/17/2026
Town Engineering Building-Rooms 0130, 0138 and 0138B Improvement Bid opening online
Substantial completion: June 5, 2026
Cost estimate: $130,000
TSB goal: 10%
Project manager: Angela Solberg
Construction manager:
John Boehmer
Design Professional: Brendan Harms, 515-294-7198
ISU - FDC
Plan Holders
Surplus Facility-Parking Lot Improvement
Prebid Meeting: 2/4/2026 10:00:00 AM
Prebid location: Surplus Facility-Parking Lot Improvement prebid: via Microsoft Teams
Tour: 2/4/2026 Following prebid meeting
Bid date: 2/19/2026
Surplus Facility-Parking Lot Improvement Bid opening online
Substantial completion: July 31, 2026
Cost estimate: $270,000
TSB goal: 10%
Project manager: Angela Solberg
Construction manager:
John Boehmer
Design Professional: Brandon Niebuhr, 515-964-2020
SNYDER & ASSOC INC
Plan Holders
Parking Lots 2026-Pavement Preservation-Concrete Patching
Prebid Meeting: 2/11/2026 10:00:00 AM
Prebid location: Parking Lots 2026-Pavement Preservation-Concrete Patching prebid: via Microsoft Teams
Tour: Following Prebid Meeting
Bid date: 2/24/2026
Parking Lots 2026-Pavement Preservation-Concrete Patching Bid opening online
Substantial completion: August 7, 2026
Cost estimate: $647,000
TSB goal: 10%
Project manager: Angela Solberg
Construction manager:
John Boehmer
Design Professional: Matthew Klein, 319-354-3040
SHIVE HATTERY ARCHITECTURE & ENGINEERING
Plan Holders
College of Design-Roof Replacement-Sections A, B, C, D, G, J and I
Prebid Meeting: 2/11/2026 2:00:00 PM
Prebid location: College of Design-Roof Replacement-Sections A, B, C, D, G, J and I prebid: via Microsoft Teams
Tours: 2/11/2026 1:00 PM and 2/18/2026 2:00 PM
Bid date: 2/26/2026
College of Design-Roof Replacement-Sections A, B, C, D, G, J and I Bid opening online
Substantial completion: July 31, 2026
Cost estimate: $1,480,000
TSB goal: 10%
Project manager: Angela Solberg
Construction manager:
John Boehmer
Design Professional: Bruce Bonestroo, 515-441-3011
10FOLD ARCHITECTURE & ENGINEERING LTD
Plan Holders
Projects Under $100,000
Bid Submission
- Bids must be submitted prior to 4:00 PM on bid date
- Submit bids by emailing spbids@iastate.edu
- Refer to "Instructions to Bidders" in the project manual for bid submission requirements
Projects
- No projects scheduled -
